Construction of water retention tanks and pumping room II° at water treatment station and construction of sewage system I stage, in Łabiszyn (Q98498)
Jump to navigation
Jump to search
Project Q98498 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of water retention tanks and pumping room II° at water treatment station and construction of sewage system I stage, in Łabiszyn |
Project Q98498 in Poland |
Statements
2,358,158.18 zloty
0 references
2,774,303.75 zloty
0 references
85.0 percent
0 references
1 July 2017
0 references
31 January 2018
0 references
GMINA ŁABISZYN
0 references
Przedmiotowy projekt to inwestycja polegająca na budowie zbiorników retencyjnych wody i pompowni II° na stacji uzdatniania wody oraz budowa sieci kanalizacyjnej w Łabiszynie. W związku z dużą dysproporcją między długością sieci wodociągowej i kanalizacyjnej, niezbędna jest budowa infrastruktury kanalizacyjnej, która jest przedmiotem projektu. Biorąc pod uwagę niesprzyjające położenie (przejście przez Kanał Notecki) zastosowano mieszany system odbioru ścieków z budynków mieszkalnych znajdujących się w rejonie realizowanego projektu, tj. system grawitacyjny jako bezpośredni odbiór ścieków z budynków mieszkalnych i ciśnieniowy z zastosowaniem przepompowni ścieków, które będą przepompowywać odebrane ścieki do istniejącego systemu grawitacji po zachodniej stronie Kanału Noteckiego (lewy brzeg). Zostanie również zamontowana rura ochronna pod dnem kanału Noteckiego. W ramach realizacji przedsięwzięcia do sieci kanalizacyjnej zostanie podłączonych 130 mieszkańców Łabiszyna.. Z kolei budowa zbiorników retencyjnych pozwoli na gromadzenie zapasu wody pitnej, aby uzupełnić jej braki w okresie zwiększonego zapotrzebowania oraz magazynowanie wody dla celów ppoż. Zmiana systemu jednostopniowego dostarczania wody do sieci wodociągowej, na dwustopniowy, usprawni funkcjonowanie stacji uzdatniania wody. Komora pompowni II° będzie składać się z następujących elementów: zestaw hydroforowy, pompa płuczna, osuszacz powietrza i wciągnik ręczny. Wybudowane zostaną cztery zbiorniki o pojemności 100 m3 każdy. Pracę zbiorników zaprojektowano, aby zapewnić ich niezależną eksploatację, zabezpieczając niezbędną retencję wody podczas ewentualnego wyłączenia jednego z nich.Mając na uwadze lokalizację projektu, jego realizacja umożliwi odniesienie korzyści środowiskowych w postaci zmniejszenia zanieczyszczeń odprowadzanych do środowiska poprzez nieszczelne zbiorniki bezodpływowe (szamba). W ramach realizacji projektu poprawi się jakość wód powierzchniowych i podziemnych oraz gleby. (Polish)
0 references
This project is an investment involving the construction of water retention tanks and the II° pumping room at the water treatment station and the construction of a sewerage network in Łabiszyn. Due to the large disparity between the length of the water supply and sewage network, it is necessary to build the sewage infrastructure, which is the subject of the project. Taking into account the unfavourable location (passing through the Notecki Canal), a mixed system of wastewater collection from residential buildings located in the area of the project was used, i.e. gravity system as a direct reception of sewage from residential and pressure buildings using a sewage pumping plant, which will pump the received sewage into the existing gravity system on the western side of Notecki Canal (left bank). A protective pipe under the bottom of Notecki canal will also be installed. As part of the implementation of the project, 130 inhabitants of Łabiszyna will be connected to the sewage network. In turn, the construction of storage tanks will allow the storage of drinking water to replenish its shortages during the period of increased demand and storage of water for firefighting purposes. Changing the single-stage water supply system to a two-stage water supply system will improve the operation of water treatment stations. The II° pumping chamber shall consist of the following elements: hydrophore unit, pulmonary pump, air dryer and manual hoist. Four tanks with a capacity of 100 m³ each will be built. The operation of the tanks was designed to ensure their independent operation, safeguarding the necessary water retention during a possible shutdown of one of them.In view of the location of the project, its implementation will enable the environmental benefits of reducing pollutants discharged into the environment through leaky waste water tanks (chamba). The project will improve the quality of surface and groundwater and soil. (English)
15 October 2020
0 references
Le projet en question est un investissement consistant en la construction de réservoirs de rétention d’eau et d’une station de pompage II° de la station de traitement des eaux et la construction d’un réseau d’assainissement à Łabiszyn. En raison de la grande disproportion entre la longueur des réseaux d’approvisionnement en eau et d’assainissement, la construction de l’infrastructure d’assainissement, qui fait l’objet du projet, est nécessaire. Compte tenu de l’emplacement défavorable (passage par le canal de Notecki), un système mixte de collecte des eaux usées provenant de bâtiments résidentiels situés dans la zone du projet est utilisé, c’est-à-dire un système gravitationnel comme collecte directe des eaux usées des bâtiments résidentiels et sous pression à l’aide d’une station de pompage des eaux usées, qui pompera les eaux usées reçues dans le système de gravité existant du côté ouest du canal de Notecki (côté gauche). Un tube de protection sera également monté sous le fond du canal Notecki. Dans le cadre de la mise en œuvre du projet, 130 habitants de Łabiszyn seront raccordés au réseau d’assainissement. À son tour, la construction de réservoirs de rétention permettra l’accumulation d’approvisionnement en eau potable afin de combler ses pénuries en période d’augmentation de la demande et d’entreposer l’eau à des fins de lutte contre les incendies. Le passage d’un système d’approvisionnement en eau à une étape unique à un système d’approvisionnement en eau en deux étapes améliorera le fonctionnement de la station de traitement de l’eau. La salle de pompage II° sera composée des éléments suivants: set d’hydrophore, pompe à chasse d’eau, séchoir à air et palan à main. Quatre réservoirs d’une capacité de 100 m³ chacun seront construits. L’exploitation des réservoirs a été conçue pour assurer leur fonctionnement indépendant et assurer la rétention d’eau nécessaire lors de l’arrêt éventuel de l’un d’entre eux.En ce qui concerne l’emplacement du projet, sa mise en œuvre permettra d’obtenir des avantages pour l’environnement sous la forme d’une réduction de la pollution rejetée dans l’environnement par des réservoirs sans fuite (citernes septiques). Le projet améliorera la qualité des eaux de surface et des eaux souterraines et du sol. (French)
1 December 2021
0 references
Identifiers
RPKP.04.06.01-04-0002/17
0 references