Thermal modernisation of the sports hall building near the School Complex in Radzyń Chełmiński with air conditioning. (Q98249)

From EU Knowledge Graph
Revision as of 13:26, 7 December 2021 by DG Regio (talk | contribs) (‎Changed label, description and/or aliases in de, and other parts: Adding German translations)
Jump to navigation Jump to search
Project Q98249 in Poland
Language Label Description Also known as
English
Thermal modernisation of the sports hall building near the School Complex in Radzyń Chełmiński with air conditioning.
Project Q98249 in Poland

    Statements

    0 references
    654,500.0 zloty
    0 references
    157,080.0 Euro
    13 January 2020
    0 references
    999,000.0 zloty
    0 references
    239,760.0 Euro
    13 January 2020
    0 references
    65.52 percent
    0 references
    15 April 2018
    0 references
    15 October 2018
    0 references
    GMINA MIASTO I GMINA RADZYŃ CHEŁMIŃSKI
    0 references
    0 references
    Tytuł projektu to „Termomodernizacja budynku hali sportowej przy Zespole Szkół w Radzyniu Chełmińskimwraz z klimatyzacją”. Przedmiotem projektu są prace termomodernizacyjne, którym poddany zostanie budynek hali sportowej przy Zespole Szkół w Radzyniu Chełmińskim. Głównym problemem, jaki zdefiniowano w budynku to nieefektywne wykorzystywanie energii cieplnej i elektrycznej w obiekcie. Podstawowym celem projektu jest zwiększenie wykorzystywania efektywności energii cieplnej i elektrycznej w obiekcie. W ramach projektowanej termomodernizacji planuje się roboty budowlane obejmujące następujące branże: a) Ogólnobudowlaną b) Wentylacji mechanicznej i wewnętrznej instalacji c.o wraz z klimatyzacją c) Elektryczną Harmonogram projektu obejmuje: 1. Prace budowlane: 15.04.2018-15.10.2018 2. Promocja projektu: 15.04.2018-15.10.2018 (Polish)
    0 references
    The title of the project is “Termomodernisation of the sports hall building at the School Complex in Radzyń Chełmiński with air conditioning”. The subject of the project is thermal modernisation works, which will be subjected to the sports hall building at the School Complex in Radzyń Chełmiński. The main problem defined in the building is the inefficient use of heat and electricity in the building. The primary objective of the project is to increase the use of heat and electricity efficiency in the facility. As part of the planned thermo-modernisation, construction works covering the following sectors are planned: a) General built-in (b) Mechanical ventilation and internal central heating system with air conditioning (c) Electrical design schedule shall include: 1. Construction work: 15.04.2018-15.10.2018 2. Promotion of the project: 15.04.2018-15.10.2018 (English)
    15 October 2020
    0 references
    Le titre du projet est «Termomodernisation du bâtiment de la salle de sport du complexe scolaire de Radzyń Chełmiński avec climatisation». L’objet du projet est les travaux de thermomodernisation, qui feront l’objet de la construction de la salle de sport du complexe scolaire de Radzyń Chełmiński. Le principal problème défini dans le bâtiment est l’utilisation inefficace de la chaleur et de l’électricité dans l’installation. L’objectif principal du projet est d’accroître l’utilisation de la chaleur et de l’électricité dans l’installation. La thermomodernisation prévue est prévue pour les travaux de construction couvrant les secteurs suivants: a) Construction générale b) Installation mécanique de ventilation et de chauffage interne, y compris la climatisation (c) Le calendrier du projet électrique comprend: 1. Travaux de construction: 15.04.2018-15.10.2018 2. Promotion du projet: 15.04.2018-15.10.2018 (French)
    1 December 2021
    0 references
    Der Titel des Projekts lautet „Termomodernisierung des Gebäudes der Sporthalle des Schulkomplexes in Radzyń Chełmiński zusammen mit Klimaanlage“. Gegenstand des Projekts sind die Thermomodernisierungsarbeiten, die dem Bau der Sporthalle des Schulkomplexes in Radzyń Chełmiński unterzogen werden. Das Hauptproblem des Gebäudes ist die ineffiziente Nutzung von Wärme und Strom in der Anlage. Hauptziel des Projekts ist die Steigerung der Nutzung von Wärme und Strom in der Anlage. Die geplante Thermomodernisierung ist für Bauarbeiten in folgenden Bereichen geplant: a) Allgemeiner Bau b) Mechanische Lüftungs- und Innenheizungsanlage einschließlich Klimaanlage (c) Elektrischer Projektplan umfasst: 1. Bauarbeiten: 15.04.2018-15.10.2018 2. Förderung des Projekts: 15.04.2018-15.10.2018 (German)
    7 December 2021
    0 references

    Identifiers

    RPKP.03.03.00-04-0084/16
    0 references