Conversion of 110/15 kV Nidzica station to enable the development of renewable energy (Q84413)

From EU Knowledge Graph
Revision as of 16:34, 30 November 2021 by DG Regio (talk | contribs) (‎Created claim: summary (P836): Le projet comprend la reconstruction de la centrale GPZ 110/15 kV Nidzica afin de permettre le développement des énergies renouvelables. La station fait partie d’un réseau de distribution de 110 kV sur lequel l’électricité est transformée en une tension de 15 kV. La gare de Nidzica est située à l’avenue 59 sur le terrain 1, division 3, unité cadastrale de Nidzica. Le terrain est en usage perpétuel d’ENERGA-OPERATOR S. A. La superficie de la prop...)
Jump to navigation Jump to search
Project Q84413 in Poland
Language Label Description Also known as
English
Conversion of 110/15 kV Nidzica station to enable the development of renewable energy
Project Q84413 in Poland

    Statements

    0 references
    2,255,663.47 zloty
    0 references
    541,359.23 Euro
    13 January 2020
    0 references
    3,095,000.0 zloty
    0 references
    742,800.0 Euro
    13 January 2020
    0 references
    72.88 percent
    0 references
    20 December 2018
    0 references
    30 September 2020
    0 references
    ENERGA-OPERATOR SPÓŁKA AKCYJNA
    0 references
    0 references
    0 references
    0 references
    Zakres Projektu obejmuje przebudowę stacji elektroenergetycznej GPZ 110/15 kV Nidzica celem umożliwienia rozwoju energetyki odnawialnej. Stacja stanowi element sieci dystrybucyjnej na napięciu 110kV, na której odbywa się transformacja energii elektrycznej na napięcie 15 kV. Stacja Nidzica zlokalizowana jest przy Alei Sprzymierzonych 59 na działce nr 1, obręb 3, jednostka ewidencyjna Nidzica. Grunt znajduje się w użytkowaniu wieczystym ENERGA-OPERATOR S. A. Powierzchnia nieruchomości, na której zlokalizowana jest stacja wynosi 0,9408 ha. Celem bezpośrednim Projektu jest zwiększenie potencjału dla przyłączania źródeł energii odnawialnej do sieci, a także zwiększenie niezawodności dostaw energii elektrycznej na obszarze oddziaływania Projektu. Celami po pośrednimi Projektu są: 1) poprawa parametrów energetycznych dostarczanej energii; 2) przyczynienie się, poprzez zwiększenie możliwości przyjęcia do sieci większej ilości energii z OZE, do ograniczenia zapotrzebowania na produkcję energii ze źródeł konwencjonalnych, a tym samym, zmniejszenie zużycia paliw, a w konsekwencji obniżenie emisji zanieczyszczeń do atmosfery; 3) poprawa efektywności pracy systemu dystrybucyjnego. Celem Projektu na poziomie produktu jest: 1) modernizacja 1 stacji elektroenergetycznej; 2) dodatkowa zdolność przyłączania źródeł odnawialnych do sieci elektroenergetycznej w wysokości 8,37 MWe. Celem Projektu na poziomie rezultatu jest spadek emisji gazów cieplarnianych. Cel ten zostanie osiągnięty poprzez zwiększenie zdolności przyłączania źródeł energii odnawialnej do sieci. Przebudowa powyższej stacji przyczyni się do poprawy jakości i ciągłości dostaw energii elektrycznej, a nowoczesna aparatura ułatwi bieżącą obsługę stacji i przyspieszy reakcję na potencjalne sytuacje awaryjne w obszarze zasilania stacji. (Polish)
    0 references
    The scope of the project includes the reconstruction of the power station GPZ 110/15 kV Nidzica to enable the development of renewable energy. The station is part of a distribution network at a voltage of 110 kV, where electricity is transformed to a voltage of 15 kV. Nidzica station is located on Allied Avenue 59 on plot no. 1, perimeter 3, Nidzica registration unit. The land is in perpetual use of ENERGA-OPERATOR S.A. The area of the property on which the station is located is 0.9408 ha. The direct objective of the Project is to increase the potential for connecting renewable energy sources to the grid, and to increase the reliability of electricity supply in the area of impact of the Project. The indirect objectives of the Project are: 1) improving the energy performance of the energy supplied; 2) contributing, by increasing the capacity of more RES energy, to reducing the demand for conventional energy production, thereby reducing fuel consumption and consequently reducing emissions of pollutants into the atmosphere; 3) Improving the efficiency of the distribution system. The aim of the Project at product level is to: 1) modernisation of 1 power stations; 2) an additional capacity to connect renewables to the electricity grid of 8,37 MWe. The project’s objective at the result level is to reduce greenhouse gas emissions. This will be achieved by increasing the capacity to connect renewable energy sources to the grid. The conversion of this station will improve the quality and continuity of electricity supply, while modern apparatus will facilitate the day-to-day operation of the station and speed up the response to potential emergency situations in the station’s power supply area. (English)
    14 October 2020
    0 references
    Le projet comprend la reconstruction de la centrale GPZ 110/15 kV Nidzica afin de permettre le développement des énergies renouvelables. La station fait partie d’un réseau de distribution de 110 kV sur lequel l’électricité est transformée en une tension de 15 kV. La gare de Nidzica est située à l’avenue 59 sur le terrain 1, division 3, unité cadastrale de Nidzica. Le terrain est en usage perpétuel d’ENERGA-OPERATOR S. A. La superficie de la propriété sur laquelle se trouve la station est de 0,9408 ha. L’objectif direct du projet est d’accroître le potentiel de raccordement des sources d’énergie renouvelables au réseau et d’accroître la fiabilité de l’approvisionnement en électricité dans la zone touchée par le projet. Les jalons du projet sont les suivants: 1) l’amélioration des paramètres énergétiques de l’énergie fournie; 2) contribuer, en augmentant la capacité d’absorption d’énergie renouvelable dans le réseau, à réduire la demande de production d’énergie à partir de sources conventionnelles, réduisant ainsi la consommation de carburant et, partant, réduisant les émissions de polluants dans l’atmosphère; 3) l’amélioration de l’efficacité du système de distribution. L’objectif du projet au niveau des produits est de: 1) modernisation d’une centrale électrique; 2) capacité supplémentaire de raccordement des sources d’énergie renouvelables au réseau électrique de 8,37 MWe. L’objectif du projet au niveau du résultat est de réduire les émissions de gaz à effet de serre. Pour ce faire, il sera possible d’accroître la capacité de connecter les sources d’énergie renouvelables au réseau. La reconstruction de cette station améliorera la qualité et la continuité de l’approvisionnement en électricité, et l’équipement moderne facilitera le fonctionnement quotidien de la station et accélérera la réponse aux situations d’urgence potentielles dans la zone d’alimentation électrique de la station. (French)
    30 November 2021
    0 references

    Identifiers

    POIS.01.01.02-00-0003/18
    0 references