GRANDILLA CENTRAL EOLICO PARK (Q3170553)

From EU Knowledge Graph
Revision as of 12:49, 4 December 2021 by DG Regio (talk | contribs) (‎Changed label, description and/or aliases in fr, and other parts: Adding French translations)
Jump to navigation Jump to search
Project Q3170553 in Spain
Language Label Description Also known as
English
GRANDILLA CENTRAL EOLICO PARK
Project Q3170553 in Spain

    Statements

    0 references
    16,422,000.0 Euro
    0 references
    19,320,000.0 Euro
    0 references
    85.0 percent
    0 references
    2 April 2019
    0 references
    30 June 2022
    0 references
    ENEL GREEN POWER ESPAÑA, S.L.U
    0 references
    0 references

    28°7'19.70"N, 16°34'36.01"W
    0 references
    38017
    0 references
    PARQUE EOLICO CENTRAL DE GRANADILLA DE POTENCIA NOMINAL 16,1 MW, FORMADO POR 7 AEROGENERADORES ENERCON E70 DE 2.300 KW CADA UNO Y DE 98M DE ALTURA DE BUJE. _x000D_ LOS AEROGENERADORES Y EL CENTRO DE MANDO Y CONTROL DEL PARQUE EOLICO SE UBICARAN DENTRO DEL RECINTO DE LA CENTRAL TERMICA DE GRANADILLA, MIENTRAS QUE LA LINEA DE MEDIA TESION DE EVACUACION DISCURRIRA POR MARGENES DE VIALES Y ZONAS COMUNES DEL POLIGONO INDUSTRIAL DE GRANADILLA, HASTA LA UBICACION DE LA SUBESTACION ELECTRICA SE ITER, DENTRO DEL TERMINO MUNICIPAL DE GRANADILLA DE ABONA. (Spanish)
    0 references
    GRANADILLA CENTRAL EOLICO PARK OF RATED POWER 16.1 MW, CONSISTING OF 7 ENERCON E70 WIND TURBINES OF 2,300 KW EACH AND 98M OF BUSHING HEIGHT. _x000D_ the AEROGENERATORS AND THE COMMUNITY CENTER AND CONTROL OF THE EOLICAL PARK will be located within the RECINTE OF GRANADILLA TERMICAL CENTRAL, MIENTRAS THAT THE MEDIA LINE OF THE EVACUATION LINE DISCURRIED by margins of VIALAL AND COMMUNAL ZONAS OF GRANADILLA INDUSTRIAL POLIGONO, it HAS THE LOCATION OF THE ELECTRICA SE ITER substation, within the MUNICIPAL TERMINO DE GRANADILLA DE ABONA. (English)
    12 October 2021
    0 references
    GRANADILLA CENTRAL EOLICO PARC DE PUISSANCE NOMINALE 16,1 MW, COMPOSÉ DE 7 ÉOLIENNES ENERCON E70 DE 2300 KW CHACUNE ET 98M DE HAUTEUR DE BROUSSE. _x000D_ les aérogénérateurs ET LE CENTRE COMMUNAUTAIRE ET LE CONTRÔLE DU PARC EOLICAL seront situés dans le cadre de la reprise de Granadilla termical CENTRAL, Mientras QUE LA DINE MÉDIAS DE LA LINE ÉVACUATION DISCURRIÉE par les marges de ZONAS VIALAL ET COMMUNAL de Granadilla INDUSTRIAL POLIGONO, il SANS LA LOCATION DE LA sous-station ELECTRICA SE ITER, au sein de la TERMINO MUNICIPAL DE Granadilla DE Granadilla DE ABONA. (French)
    4 December 2021
    0 references
    Granadilla de Abona
    0 references

    Identifiers

    FE18EOC00068
    0 references