2,393,403.96 Euro
0 references
2,815,769.37 Euro
0 references
85.0 percent
0 references
1 May 2019
0 references
1 January 2021
0 references
SPRAVBYTKOMFORT, a.s. Prešov
0 references
Projekt rieši modernizáciu a rekonštrukciu rozvodov tepla v 2 existujúcich samostatných účinných systémoch/okruhoch CZT v Prešove. Rekonštrukciou a optimalizáciou primárnych rozvodov tepla CK Jazdecká a CK Sekčov sa rozvody tepla prispôsobia zníženému dopytu po využiteľnom teple a vytvoria sa predpoklady na zníženie spotreby primárnej energie. Znížia straty tepla vznikajúce v rozvodoch, čo sa prejaví v nižšej potrebe výroby tepla. Hlavným cieľom projektu je rozvoj účinnejších systémov centralizovaného zásobovania teplom založených na dopyte po využiteľnom teple. Špecifickým cieľom projektu je zníženie strát tepla a úspora PEZ v systémoch CZT v meste Prešov prostredníctvom rekonštrukcie a modernizácie časti primárnych rozvodov CK Jazdecká a CK Sekčov. Projekt bude realizovaný prostredníctvom 1 hlavnej aktivity „Rekonštrukcia a modernizácia 2 samostatných okruhov CZT v meste Prešov - CK Jazdecká a CK Sekčov“. V rámci nej sa budú realizovať 3 stavby, na ktoré boli vydané samostatné stavebné povolenia a to v dvoch etapách.etapa: 2018 - Rekonštrukcia primárneho vykurovacieho okruhu CK Jazdecká, Prešovetapa: 2018-2019 - Preložka primárneho potrubia DN500 na okruhu CK Sekčov, Prešov a Rekonštrukcia primárneho vykurovacieho okruhu CK Sekčov, PrešovNa základe energetického auditu bol stanovený potenciál úspor tepla znížením tepelných strát rozvodov tepla ako aj úspor primárnych energetických zdrojov - priemerná ročná strata rozvodov sa zníži o 14 913 GJ (4 142,638 MWh/rok), čo predstavuje približne 30 % úsporu. Projekt má aj výrazné environmentálne prínosy v znížení emisií.Projektom budú dosiahnuté nasledovné merateľné ukazovatele:Počet systémov centralizovaného zásobovania teplom s vyššou účinnosťou: 2 Úspora PEZ v systémoch centralizovaného zásobovania teplom: 14 913 GJ/r, 4 142,638 MWh/rOdhadované ročné zníženie emisií skleníkových plynov: 1 127 t/rok (Slovak)
0 references
The project deals with modernisation and reconstruction of heat distribution systems in 2 existing individual efficient systems/circuits of CZT in Prešov. By reconstructing and optimising the primary heat distributions of CK Jazdecká and CK Sekčov, the heat distribution system adapts to the reduced demand for useful heat and creates the preconditions for reducing primary energy consumption. They will reduce the heat losses generated by the distribution system, which will translate into a lower need for heat production. The main objective of the project is to develop more efficient district heating systems based on useful heat demand. The specific objective of the project is to reduce heat loss and save PEZ in CZT systems in Prešov through the reconstruction and modernisation of part of the primary distribution of CK Jazdecká and CK Sekčov. The project will be implemented through 1 main activity “Reconstruction and modernisation of 2 separate CZT circuits in Prešov – CK Jazdecká and CK Sekčov”. It will carry out 3 construction works for which separate building permits have been issued in two stages. Stage: 2018 – Reconstruction of primary heating circuit CK Jazdecká, Prešovetapa: 2018-2019 – Translating the primary pipe DN500 on the circuit CK Sekčov, Prešov and Reconstruction of the primary heating circuit CK Sekčov, Prešov Based on the energy audit, the potential for heat savings by reducing heat loss of heat distribution as well as savings of primary energy sources has been determined – the average annual distribution loss will be reduced by 14 913 GJ (4142,638 MWh/year), which represents about 30 % saving. The project also has significant environmental benefits in reducing emissions.The project will achieve the following measurable ukazovatele:Počet district heating systems with higher efficiency: 2 Saving of PEZs in district heating systems: 14 913 GJ/r, 4142,638 MWh/rEstimated annual greenhouse gas emission reductions: 1127 t/year (English)
28 September 2021
0 references
Identifiers
310041I329