Increasing the use of renewable energy sources through the construction of a photovoltaic installation with a capacity of 1.999 MW in Mirosławice in Trzebiatów (Q2718698)

From EU Knowledge Graph
Revision as of 12:24, 4 December 2021 by DG Regio (talk | contribs) (‎Changed label, description and/or aliases in fr, and other parts: Adding French translations)
Jump to navigation Jump to search
Project Q2718698 in Poland
Language Label Description Also known as
English
Increasing the use of renewable energy sources through the construction of a photovoltaic installation with a capacity of 1.999 MW in Mirosławice in Trzebiatów
Project Q2718698 in Poland

    Statements

    0 references
    2,377,719.96 zloty
    0 references
    528,567.15 Euro
    0.2223 Euro
    0 references
    2,972,150.0 zloty
    0 references
    660,708.94 Euro
    0.2223 Euro
    0 references
    80.0 percent
    0 references
    2 January 2021
    0 references
    31 July 2022
    0 references
    PV 3 SOLAR SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
    0 references
    0 references

    54°3'45.7"N, 15°15'56.5"E
    0 references
    Przedmiotem projektu będzie budowa elektrowni solarnej produkującej energię elektryczną na sprzedaż. W ramach przedsięwzięcia planuje się wybudowanie farmy fotowoltaicznej o mocy instalacji brutto wynoszącej 1,999 MW, wraz z linią kablową niskiego i średniego napięcia oraz stacją transformatorową. Wnioskowany projekt zrealizowany zostanie w miejscowości Mirosławice w powiecie gryfickim, na terenie woj. zachodniopomorskiego. Farma zlokalizowana zostanie na działce 111/4 obręb Mirosławice w gminie Trzebiatów. Projektowane przedsięwzięcie polegać będzie na montażu zespołu wolnostojących ogniw fotowoltaicznych wraz z budową infrastruktury towarzyszącej, w postaci stacji transformatorowo-rozdzielczej SN/nn, inwerterów oraz okablowania. Do zakresu rzeczowego przedsięwzięcia należą następujące elementy: (1) zakup instalacji fotowoltaicznej: paneli PV, inwerterów, konstrukcji wsporczych; (2) zakup elementów infrastruktury elektrycznej: instalacji wewnętrznej nn - trasy kablowe, wyposażenia stacji transformatorowo-rozdzielczej; (3) montaż instalacji fotowoltaicznej; (4) montaż stacji transformatorowo-rozdzielczej, tras kablowych instalacji wewnętrznej nn oraz instalacji zewnętrznej SN. Budżet projektu obejmuje także wydatki na: (5) przygotowanie i zabezpieczenie terenu budowy elektrowni fotowoltaicznej; (6) pozostałe wydatki związane z procesem budowlanym, w tym obsługa geodezyjna oraz wydatki na usługi dotyczące czynności nadzoru w procesie budowlanym. (Polish)
    0 references
    The project will focus on the construction of a solar power plant producing electricity for sale. The project plans to build a photovoltaic farm with a gross installation capacity of 1.999 MW, together with a low and medium voltage cable line and a transformer station. The proposed project will be carried out in Mirosławice in Gryficki district, in the West Pomeranian Voivodeship. The farm will be located on plot 111/4 of Mirosławice in the municipality of Trzebiatów. The project will consist of the assembly of a set of free-standing photovoltaic cells together with the construction of associated infrastructure, in the form of SN/nn transformer and resolution stations, inverters and wiring. The material scope of the project includes the following elements: (1) purchase of photovoltaic installations: PV panels, inverters, support structures; (2) purchase of electrical infrastructure: internal installation nn – cable routes, transformer-resolution station equipment; (3) installation of photovoltaic installation; (4) Assembly of transformer-resolution station, cable routes of internal installation nn and external installation of SN. The budget of the project shall also include expenditure on: (5) Preparing and securing the site for the construction of a photovoltaic power plant; (6) Other expenditure relating to the construction process, including surveying and expenditure on services relating to supervision activities in the construction process. (English)
    8 July 2021
    0 references
    Le projet se concentrera sur la construction d’une centrale solaire produisant de l’électricité destinée à la vente. Le projet prévoit la construction d’une ferme photovoltaïque d’une capacité brute d’installation de 1,999 MW, ainsi que d’une ligne de câbles basse et moyenne tension et d’une station de transformateur. Le projet proposé sera réalisé à Mirosławice, dans le district de Gryficki, dans la voïvodie de Poméranie occidentale. La ferme sera située sur la parcelle 111/4 de Mirosławice dans la municipalité de Trzebiatów. Le projet consistera en l’assemblage d’un ensemble de cellules photovoltaïques autonomes ainsi que la construction d’infrastructures associées, sous la forme de transformateurs et de stations de résolution SN/nn, d’onduleurs et de câblage. La portée matérielle du projet comprend les éléments suivants: (1) achat d’installations photovoltaïques: Panneaux photovoltaïques, onduleurs, structures de soutènement; (2) achat d’infrastructures électriques: installation interne nn — voies de câbles, équipements de poste de transformateur-résolution; (3) installation de l’installation photovoltaïque; (4) Montage de la station de résolution des transformateurs, voies de câbles de l’installation interne nn et installation externe de SN. Le budget du projet comprend également des dépenses pour: 5) Préparation et sécurisation du site pour la construction d’une centrale photovoltaïque; (6) Autres dépenses relatives au processus de construction, y compris l’arpentage et les dépenses de services liés aux activités de supervision dans le processus de construction. (French)
    4 December 2021
    0 references

    Identifiers

    RPZP.02.10.00-32-C110/20
    0 references