Expansion of photovoltaic farm – Grodzisko (Q131840): Difference between revisions
Jump to navigation
Jump to search
(Changed label, description and/or aliases in 2 languages: Changing unique label-description pair) |
(Removed claim: financed by (P890): Directorate-General for Regional and Urban Policy (Q8361), Removing unnecessary financed by statement) |
||
Property / financed by | |||
Property / financed by: Directorate-General for Regional and Urban Policy / rank | |||
Revision as of 18:55, 29 October 2020
Project Q131840 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | Expansion of photovoltaic farm – Grodzisko |
Project Q131840 in Poland |
Statements
1,227,149.82 zloty
0 references
1,533,937.27 zloty
0 references
80.0 percent
0 references
11 February 2020
0 references
30 June 2020
0 references
KANCELARIA PRAWNA „CONSULTOR” DANIEL GRAMATOWSKI
0 references
Kancelaria Prawna „Consultor” Daniel Gramatowski zakłada rozbudowę istniejącej instalacji fotowoltaicznej o panele o łącznej mocy 0,39 MW, zamontowane na gruncie wraz z niezbędną infrastrukturą techniczną, na terenie działki nr ewid. 368/2, położonej w obrębie geodezyjnym Grodzisko, gmina Banie Mazurskie, powiat gołdapski, województwo warmińsko-mazurskie. Ww. działka położona jest poza skupioną zabudową wsi Grodzisko. Działka 368/2 jest zabudowana w części istniejącą farmą PV Grodzisko o mocy 611 kW. Produkowana przez elektrownię energia elektryczna, będzie dostarczana do sieci elektroenergetycznej, zgodnie z wydanymi warunkami przyłączenia poprzez przyłącze energetyczne do linii 15 kV. Charakterystyczne parametry elektrowni fotowoltaicznej: • liczba modułów – 1 251 szt. o mocy jednostkowej 310 W każdy; • liczba inwerterów - 12 szt. o mocy 30 kW (po stronie AC) każdy. • stacja transformatorowa – 1 szt. Poszczególne rzędy paneli będą usytuowane na terenie działki na ustawionej tam typowej konstrukcji wsporczej. Posadowienie konstrukcji będzie następowało poprzez wbicie kafarem w grunt pionowych elementów podpór, a następnie wykonanie połączeń skręcanych z pozostałymi elementami konstrukcji. Konstrukcja wsporcza została zaprojektowana zgodnie z warunkami określonymi w decyzji o warunkach zabudowy. Panele będą stanowiły rozbudowę istniejącej instalacji fotowoltaicznej na działce 368/2 w miejscowości Grodzisko. Projekt poprzez produkcję energii odnawialnej ze słońca i ograniczenie emisji zanieczyszczeń do powietrza, wpisuje się w Cel tematyczny 4 – Wspieranie przejścia na gospodarkę niskoemisyjną we wszystkich sektorach, Priorytet inwestycyjny 4a – Wspieranie wytwarzania i dystrybucji energii pochodzącej ze źródeł odnawialnych SzOOP RPO WiM Dz.4.1 Wspieranie wytwarzania i dystrybucji energii pochodzącej ze OZE. (Polish)
0 references
The law firm “Consultor” Daniel Gramatowski assumes the extension of the existing photovoltaic installation with panels with a total capacity of 0.39 MW, mounted on the ground together with the necessary technical infrastructure, on the premises of the register plot. 368/2, located within the geodesy area of Grodzisko, the municipality of Banie Mazurskie, Gołdapski county, Warmińsko-Mazurskie voivodship. The plot is located outside the village of Grodzisko. Plot 368/2 is built in part by the existing PV Grodzisko farm with a capacity of 611 kW. The electricity produced by the power plant will be supplied to the electricity grid, in accordance with the released terms of connection via the power connection to the 15 kV line. Characteristic parameters of the photovoltaic power plant: • number of modules – 1 251 units with a unit capacity of 310 W each; • number of inverters – 12 units with a power of 30 kW (on the AC side) each. • transformer station – 1 pcs. Individual rows of panels will be located on the area of the plot on the typical support structure set there. The installation of the structure will be done by inserting vertical support elements into the ground with a cafare, followed by twisted connections with the other elements of the structure. The support structure has been designed in accordance with the conditions set out in the decision on the building conditions. The panels will be an extension of the existing photovoltaic installation on plot 368/2 in Grodzisko. The project through the production of renewable energy from the sun and the reduction of pollutant emissions into the air, is part of the Thematic Objective 4 – Supporting the transition to a low carbon economy in all sectors, Investment priority 4a – Supporting the production and distribution of energy from renewable sources SzOOP RPO WiM Dz.4.1 Supporting the production and distribution of energy from RES. (English)
21 October 2020
0 references
Identifiers
RPWM.04.01.00-28-0224/18
0 references