(Removed claim: summary (P836): The subject of the project is 197 building works in Stage II, leading to the achievement of energy savings of the current building and to ensure the repair of the non-compliant part of the façade. The insulation is hot, the insulation of soils, the exchange of window and door openings in the northern, southern and eastern façade, the replacement of the locksmith, the replacement of battery cages and the repair of the damaged paved surfaces. Af...) |
(Created claim: summary (P836): The object of the project are building modifications to house No. 197 within the second stage leading to energy savings of the existing building and ensuring repairs of unsatisfactory parts of the façades. These include insulated façades, insulation of soils, exchange of window and door openings on the northern, southern and eastern façades, exchange of locksmith elements, replacement of timber products and repair by construction of damaged rein...) |
||||||||||||||
Property / summary | |||||||||||||||
The object of the project are building modifications to house No. 197 within the second stage leading to energy savings of the existing building and ensuring repairs of unsatisfactory parts of the façades. These include insulated façades, insulation of soils, exchange of window and door openings on the northern, southern and eastern façades, exchange of locksmith elements, replacement of timber products and repair by construction of damaged reinforced surfaces. After the construction work is completed, the existing heating system will be regulated. (English) | |||||||||||||||
Property / summary: The object of the project are building modifications to house No. 197 within the second stage leading to energy savings of the existing building and ensuring repairs of unsatisfactory parts of the façades. These include insulated façades, insulation of soils, exchange of window and door openings on the northern, southern and eastern façades, exchange of locksmith elements, replacement of timber products and repair by construction of damaged reinforced surfaces. After the construction work is completed, the existing heating system will be regulated. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The object of the project are building modifications to house No. 197 within the second stage leading to energy savings of the existing building and ensuring repairs of unsatisfactory parts of the façades. These include insulated façades, insulation of soils, exchange of window and door openings on the northern, southern and eastern façades, exchange of locksmith elements, replacement of timber products and repair by construction of damaged reinforced surfaces. After the construction work is completed, the existing heating system will be regulated. (English) / qualifier | |||||||||||||||
point in time: 23 October 2020
|
Revision as of 22:17, 23 October 2020
Project in Czech Republic financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Insulation and replacement of building blocks No 197, Hradec nad Moravskoi |
Project in Czech Republic financed by DG Regio |
Statements
1,664,953.86 Czech koruna
0 references
5,549,846.23 Czech koruna
0 references
30.0 percent
0 references
1 May 2016
0 references
17 October 2018
0 references
30 November 2018
0 references
Město Hradec nad Moravicí
0 references
74741
0 references
Předmětem projektu jsou stavebních úprav na domě č. p. 197 v rámci II. etapy vedoucí k dosažení energetických úspor stávajícího objektu a zajištění oprav nevyhovujících části fasád. Jedná se o zateplení průčelí, zateplení půd, výměnu okenních a dveřních otvorů na severní, jižní a východní fasádě, výměnu zámečnických prvků, výměnu klempířských výrobků a opravu stavbou poškozených zpevněných ploch. Po ukončení stavebních prací dojde k vyregulování stávající otopné soustavy. (Czech)
0 references
The object of the project are building modifications to house No. 197 within the second stage leading to energy savings of the existing building and ensuring repairs of unsatisfactory parts of the façades. These include insulated façades, insulation of soils, exchange of window and door openings on the northern, southern and eastern façades, exchange of locksmith elements, replacement of timber products and repair by construction of damaged reinforced surfaces. After the construction work is completed, the existing heating system will be regulated. (English)
23 October 2020
0 references
Identifiers
CZ.06.2.11/0.0/0.0/16_098/0001937
0 references