Upgrading of moving stairs in Palmovka, East: 311, 312 and 313 (Q67891): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Removed claim: summary (P836): Project "Modernisation of moving stairs in Palmovka, East: 311, 312 and 313 "consists of achieving energy savings through the modernisation of existing obsolete and highly energy-intensive escalators in modern energy efficient escalators and lower operating costs. the project will be carried out at Palmovka’s metro station., remove_old_english_translation)
(‎Created claim: summary (P836): Project "Modernisation of Moving Steps at Palmovka Station, East: 311, 312 and 313" consists of achieving energy savings through the modernisation of existing outdated and energy-intensive escalators for modern energy-efficient escalators with higher operational safety and lower operating costs.The project will be realised at Palmovka metro station., translated_summary)
Property / summary
 
Project "Modernisation of Moving Steps at Palmovka Station, East: 311, 312 and 313" consists of achieving energy savings through the modernisation of existing outdated and energy-intensive escalators for modern energy-efficient escalators with higher operational safety and lower operating costs.The project will be realised at Palmovka metro station. (English)
Property / summary: Project "Modernisation of Moving Steps at Palmovka Station, East: 311, 312 and 313" consists of achieving energy savings through the modernisation of existing outdated and energy-intensive escalators for modern energy-efficient escalators with higher operational safety and lower operating costs.The project will be realised at Palmovka metro station. (English) / rank
 
Normal rank
Property / summary: Project "Modernisation of Moving Steps at Palmovka Station, East: 311, 312 and 313" consists of achieving energy savings through the modernisation of existing outdated and energy-intensive escalators for modern energy-efficient escalators with higher operational safety and lower operating costs.The project will be realised at Palmovka metro station. (English) / qualifier
 
point in time: 23 October 2020
Timestamp+2020-10-23T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 18:53, 23 October 2020

Project in Czech Republic financed by DG Regio
Language Label Description Also known as
English
Upgrading of moving stairs in Palmovka, East: 311, 312 and 313
Project in Czech Republic financed by DG Regio

    Statements

    0 references
    0 references
    12,881,701.03 Czech koruna
    0 references
    515,268.04 Euro
    1 October 2020
    0 references
    25,763,402.07 Czech koruna
    0 references
    1,030,536.08 Euro
    1 October 2020
    0 references
    50.0 percent
    0 references
    1 November 2017
    0 references
    31 August 2018
    0 references
    31 August 2018
    0 references
    Dopravní podnik hl. m. Prahy, akciová společnost
    0 references
    0 references

    50°6'45.7"N, 14°29'53.2"E
    0 references
    19000
    0 references
    Projekt "Modernizace pohyblivých schodů ve stanici Palmovka, východ: 311, 312 a 313" spočívá v dosažení energetické úspory prostřednictvím modernizace stávajících zastaralých a energeticky vysoce náročných eskalátorů za moderní energeticky efektivní eskalátory s vyšší bezpečností provozu a nižšími provozními náklady.Projekt bude realizován ve stanici metra Palmovka. (Czech)
    0 references
    Project "Modernisation of Moving Steps at Palmovka Station, East: 311, 312 and 313" consists of achieving energy savings through the modernisation of existing outdated and energy-intensive escalators for modern energy-efficient escalators with higher operational safety and lower operating costs.The project will be realised at Palmovka metro station. (English)
    23 October 2020
    0 references

    Identifiers

    CZ.07.2.11/0.0/0.0/17_048/0000640
    0 references