(Removed claim: summary (P836): The purpose of the project is the construction of the I/37 road in category S 9,5/80 in category S, of the overall length of the main route of 2.082 km, which is dealt with as the south-west bypass of the Municipality of Skal nad Oslavou. Implementation of the project will lead to the payment of transit traffic away from the built-up area of the municipality in order to reduce the burden of the population by noise and exile. There will also be...) |
(Created claim: summary (P836): The object of the project is the construction of the relocation of road I/37 in category S 9,5/80 in the total length of the main route 2.082 km, which is designed as a southwest bypass of the municipality of Sklené nad Oslavou. The implementation of the project will lead to the transfer of transit transport outside the municipality and thus reduce the burden of the population by noise and exhalations. There will also be an increase in traffic f...) |
||||||||||||||
Property / summary | |||||||||||||||
The object of the project is the construction of the relocation of road I/37 in category S 9,5/80 in the total length of the main route 2.082 km, which is designed as a southwest bypass of the municipality of Sklené nad Oslavou. The implementation of the project will lead to the transfer of transit transport outside the municipality and thus reduce the burden of the population by noise and exhalations. There will also be an increase in traffic flow on the I/37 road, shortened driving time and increased road safety in the municipality of Sklené nad Oslavou, including pedestrian safety. (English) | |||||||||||||||
Property / summary: The object of the project is the construction of the relocation of road I/37 in category S 9,5/80 in the total length of the main route 2.082 km, which is designed as a southwest bypass of the municipality of Sklené nad Oslavou. The implementation of the project will lead to the transfer of transit transport outside the municipality and thus reduce the burden of the population by noise and exhalations. There will also be an increase in traffic flow on the I/37 road, shortened driving time and increased road safety in the municipality of Sklené nad Oslavou, including pedestrian safety. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The object of the project is the construction of the relocation of road I/37 in category S 9,5/80 in the total length of the main route 2.082 km, which is designed as a southwest bypass of the municipality of Sklené nad Oslavou. The implementation of the project will lead to the transfer of transit transport outside the municipality and thus reduce the burden of the population by noise and exhalations. There will also be an increase in traffic flow on the I/37 road, shortened driving time and increased road safety in the municipality of Sklené nad Oslavou, including pedestrian safety. (English) / qualifier | |||||||||||||||
point in time: 23 October 2020
|
Revision as of 10:40, 23 October 2020
Project in Czech Republic financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | I/37 road Glass above Oslavou bypass |
Project in Czech Republic financed by DG Regio |
Statements
153,500,318.5 Czech koruna
0 references
180,588,610.0 Czech koruna
0 references
85 percent
0 references
22 March 2017
0 references
21 March 2019
0 references
31 May 2019
0 references
Ředitelství silnic a dálnic ČR
0 references
14000
0 references
Předmětem projektu je výstavba přeložky silnice I/37 v kategorii S 9,5/80 v celkové délce hlavní trasy 2,082 km, která je řešena jako jihozápadní obchvat obce Sklené nad Oslavou. Realizací projektu dojde k odvedení tranzitní dopravy mimo zástavbu obce a sníží se tak zátěž obyvatelstva hlukem a exhalacemi. Dojde rovněž ke zvýšení plynulosti dopravy na silnici I/37, zkrácení jízdní doby a zvýšení bezpečnosti silničního provozu v obci Sklené nad Oslavou včetně bezpečnosti chodců. (Czech)
0 references
The object of the project is the construction of the relocation of road I/37 in category S 9,5/80 in the total length of the main route 2.082 km, which is designed as a southwest bypass of the municipality of Sklené nad Oslavou. The implementation of the project will lead to the transfer of transit transport outside the municipality and thus reduce the burden of the population by noise and exhalations. There will also be an increase in traffic flow on the I/37 road, shortened driving time and increased road safety in the municipality of Sklené nad Oslavou, including pedestrian safety. (English)
23 October 2020
0 references
Identifiers
CZ.04.3.42/0.0/0.0/15_004/0000105