(‎Removed claim: summary (P836): The aim of the project is to reduce the energy performance of HST technology by implementing comprehensive solutions. As part of the project, measures will be implemented to reduce the energy performance of the building, for example through the replacement of windows, insulation/insulation of the whole envelope of the building, reconstruction of electricity distribution and lighting, modernisation of the heating and cooling system and the conn...)
(‎Created claim: summary (P836): The aim of the project is to reduce the energy performance of the HST TechnoLogic building through the implementation of complex solutions. As part of the project, measures will be implemented that will reduce the energy performance of the building, e.g. through the exchange of windows, insulation/insulation of the whole building shell, reconstruction of electricity distributions and luminaires, modernisation of the heating and cooling system an...)
Property / summary
 
The aim of the project is to reduce the energy performance of the HST TechnoLogic building through the implementation of complex solutions. As part of the project, measures will be implemented that will reduce the energy performance of the building, e.g. through the exchange of windows, insulation/insulation of the whole building shell, reconstruction of electricity distributions and luminaires, modernisation of the heating and cooling system and connection to renewables. Through the above, there will be a significant reduction in final energy consumption in the premises of the company. a. (English)
Property / summary: The aim of the project is to reduce the energy performance of the HST TechnoLogic building through the implementation of complex solutions. As part of the project, measures will be implemented that will reduce the energy performance of the building, e.g. through the exchange of windows, insulation/insulation of the whole building shell, reconstruction of electricity distributions and luminaires, modernisation of the heating and cooling system and connection to renewables. Through the above, there will be a significant reduction in final energy consumption in the premises of the company. a. (English) / rank
 
Normal rank
Property / summary: The aim of the project is to reduce the energy performance of the HST TechnoLogic building through the implementation of complex solutions. As part of the project, measures will be implemented that will reduce the energy performance of the building, e.g. through the exchange of windows, insulation/insulation of the whole building shell, reconstruction of electricity distributions and luminaires, modernisation of the heating and cooling system and connection to renewables. Through the above, there will be a significant reduction in final energy consumption in the premises of the company. a. (English) / qualifier
 
point in time: 22 October 2020
Timestamp+2020-10-22T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 16:33, 22 October 2020

Project in Czech Republic financed by DG Regio
Language Label Description Also known as
English
Reducing energy performance of buildings HST TechnoLogic
Project in Czech Republic financed by DG Regio

    Statements

    0 references
    1,425,000.0 Czech koruna
    0 references
    57,000.0 Euro
    10 January 2020
    0 references
    2,850,000.0 Czech koruna
    0 references
    114,000.0 Euro
    10 January 2020
    0 references
    50 percent
    0 references
    21 December 2017
    0 references
    31 July 2018
    0 references
    HST TECHNOLOGIC s.r.o.
    0 references

    50°37'22.94"N, 15°36'38.74"E
    0 references
    54301
    0 references
    Cílem projektu je prostřednictvím realizace komplexních řešení snížit energetickou náročnost budovy společnosti HST TechnoLogic. V rámci projektu dojde k realizaci opatření, která sníží energetickou náročnost budovy, např. prostřednictvím výměny oken, izolací/zateplením celého pláště budovy, rekonstrukcí rozvodů elektřiny a svítidel, modernizací systému vytápění a chlazení a připojení na OZE. Prostřednictvím výše uvedeného dojde k významnému snížení konečné spotřeby energie v prostorách firmy. a. (Czech)
    0 references
    The aim of the project is to reduce the energy performance of the HST TechnoLogic building through the implementation of complex solutions. As part of the project, measures will be implemented that will reduce the energy performance of the building, e.g. through the exchange of windows, insulation/insulation of the whole building shell, reconstruction of electricity distributions and luminaires, modernisation of the heating and cooling system and connection to renewables. Through the above, there will be a significant reduction in final energy consumption in the premises of the company. a. (English)
    22 October 2020
    0 references

    Identifiers

    CZ.01.3.10/0.0/0.0/15_010/0003131
    0 references