(‎Removed claim: summary (P836): The project consists of the construction of a 0.99 MW photovoltaic power plant and a 10 kW energy storage facility. The installation will be located on plots Nos 224, 225 and 231/3, which are situated within the land area of Prague, the municipality of Dobre Miasto, Warmińsko-Mazurskie Province. As part of the project, the applicant will construct a photovoltaic installation with the necessary infrastructure. Under the planned investment an ar...)
(‎Created claim: summary (P836): The project consists of the construction of a 0.99 MW photovoltaic installation and a 10 kW energy storage facility. The installation will be located on plots no. 224, 225 and 231/3, located within the geodesic area of Praslity, gmina Dobre Miasto, Warmińsko-Mazurskie voivodship. As part of the project, the applicant will build a photovoltaic installation together with the necessary infrastructure. The planned investment includes an area not exc...)
Property / summary
 
The project consists of the construction of a 0.99 MW photovoltaic installation and a 10 kW energy storage facility. The installation will be located on plots no. 224, 225 and 231/3, located within the geodesic area of Praslity, gmina Dobre Miasto, Warmińsko-Mazurskie voivodship. As part of the project, the applicant will build a photovoltaic installation together with the necessary infrastructure. The planned investment includes an area not exceeding 2 hectares. The applicant has a signed lease of real estate for a period of 25 years. Currently, the area under the planned project is unbuilt, mainly covered with meadow vegetation. The applicant shall have a building permit. After signing the grant agreement, the applicant will select the contractor who will build the installation. The project fits into the assumptions set out in the SzOOP RPO WiM 2014-2020 i.e. thanks to the implementation of the investment, the share of RES in the overall energy balance of the region will be increased. Electricity will be produced from newly built RES installations and lower greenhouse gas emissions. The installation shall not exceed 2MWe/MWth. Energy will be sold to the grid. The beneficiary is an entrepreneur. (English)
Property / summary: The project consists of the construction of a 0.99 MW photovoltaic installation and a 10 kW energy storage facility. The installation will be located on plots no. 224, 225 and 231/3, located within the geodesic area of Praslity, gmina Dobre Miasto, Warmińsko-Mazurskie voivodship. As part of the project, the applicant will build a photovoltaic installation together with the necessary infrastructure. The planned investment includes an area not exceeding 2 hectares. The applicant has a signed lease of real estate for a period of 25 years. Currently, the area under the planned project is unbuilt, mainly covered with meadow vegetation. The applicant shall have a building permit. After signing the grant agreement, the applicant will select the contractor who will build the installation. The project fits into the assumptions set out in the SzOOP RPO WiM 2014-2020 i.e. thanks to the implementation of the investment, the share of RES in the overall energy balance of the region will be increased. Electricity will be produced from newly built RES installations and lower greenhouse gas emissions. The installation shall not exceed 2MWe/MWth. Energy will be sold to the grid. The beneficiary is an entrepreneur. (English) / rank
 
Normal rank
Property / summary: The project consists of the construction of a 0.99 MW photovoltaic installation and a 10 kW energy storage facility. The installation will be located on plots no. 224, 225 and 231/3, located within the geodesic area of Praslity, gmina Dobre Miasto, Warmińsko-Mazurskie voivodship. As part of the project, the applicant will build a photovoltaic installation together with the necessary infrastructure. The planned investment includes an area not exceeding 2 hectares. The applicant has a signed lease of real estate for a period of 25 years. Currently, the area under the planned project is unbuilt, mainly covered with meadow vegetation. The applicant shall have a building permit. After signing the grant agreement, the applicant will select the contractor who will build the installation. The project fits into the assumptions set out in the SzOOP RPO WiM 2014-2020 i.e. thanks to the implementation of the investment, the share of RES in the overall energy balance of the region will be increased. Electricity will be produced from newly built RES installations and lower greenhouse gas emissions. The installation shall not exceed 2MWe/MWth. Energy will be sold to the grid. The beneficiary is an entrepreneur. (English) / qualifier
 
point in time: 21 October 2020
Timestamp+2020-10-21T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 16:36, 21 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of a 0.99 MW photovoltaic power plant in Prauslii
Project in Poland financed by DG Regio

    Statements

    0 references
    3,885,230.86 zloty
    0 references
    932,455.41 Euro
    13 January 2020
    0 references
    4,856,538.58 zloty
    0 references
    1,165,569.26 Euro
    13 January 2020
    0 references
    80.0 percent
    0 references
    1 February 2018
    0 references
    28 September 2018
    0 references
    AUTO - HANDEL IMPORT - EXPORT SŁAWOMIR WASIK
    0 references
    0 references

    53°59'12.8"N, 20°23'50.3"E
    0 references
    Projekt polega na budowie instalacji fotowoltaicznej o mocy 0,99 MW oraz magazynu energii o mocy 10kW. Instalacja zostanie zlokalizowana na działkach nr 224, 225 oraz 231/3, położonych w obrębie geodezyjnym Praslity, gmina Dobre Miasto, województwo warmińsko-mazurskie. W ramach realizacji projektu Wnioskodawca wybuduje instalację fotowoltaiczną wraz z niezbędną infrastrukturą. Pod planowaną inwestycję przeznaczony jest obszar nie przekraczający 2 ha. Wnioskodawca posiada podpisaną umowę dzierżawy nieruchomości na okres 25 lat. Aktualnie teren pod planowane przedsięwzięcie jest niezabudowany, porośnięty w głównej mierze roślinnością łąkową. Wnioskodawca posiada pozwolenie na budowę. Po podpisaniu umowy o dofinansowanie Wnioskodawca wyłoni wykonawcę, który wybuduje instalację. Projekt wpisuje się w założenia określone w SzOOP RPO WiM 2014-2020 tj. dzięki realizacji inwestycji nastąpi zwiększenie udziału OZE w ogólnym bilansie energetycznym regionu. Nastąpi produkcja energii elektrycznej z nowo wybudowanych instalacji wykorzystujących OZE i spadek emisji gazów cieplarnianych. Instalacja nie przekracza 2MWe/MWth. Energia będzie sprzedawana do sieci. Beneficjentem jest przedsiębiorca. (Polish)
    0 references
    The project consists of the construction of a 0.99 MW photovoltaic installation and a 10 kW energy storage facility. The installation will be located on plots no. 224, 225 and 231/3, located within the geodesic area of Praslity, gmina Dobre Miasto, Warmińsko-Mazurskie voivodship. As part of the project, the applicant will build a photovoltaic installation together with the necessary infrastructure. The planned investment includes an area not exceeding 2 hectares. The applicant has a signed lease of real estate for a period of 25 years. Currently, the area under the planned project is unbuilt, mainly covered with meadow vegetation. The applicant shall have a building permit. After signing the grant agreement, the applicant will select the contractor who will build the installation. The project fits into the assumptions set out in the SzOOP RPO WiM 2014-2020 i.e. thanks to the implementation of the investment, the share of RES in the overall energy balance of the region will be increased. Electricity will be produced from newly built RES installations and lower greenhouse gas emissions. The installation shall not exceed 2MWe/MWth. Energy will be sold to the grid. The beneficiary is an entrepreneur. (English)
    21 October 2020
    0 references

    Identifiers

    RPWM.04.01.00-28-0428/16