(‎Removed claim: summary (P836): The purpose of the planned investment is to expand the composting plant in the area of municipal waste processing. The extension of the phase is assumed. At this stage, it is envisaged to build: — 3 bioreactors and 1 empty reactors with process air cleaning systems, i.e. a biofilter and a ventilation system, i.e. 3 ventilation fans built in a container fan in a container; compost/stabilisation square; surfaced area between bioreactors and a ri...)
(‎Created claim: summary (P836): The object of the planned investment is the expansion of the composting plant in the Regional Municipal Waste Processing Plant. A phased expansion is planned. At this stage, the construction of: —3 bioreactors and 1 without armament with process air purification system i.e. biofilter and ventilation system i.e. 3 aeration fans built in a container fan room; compost/stabilisation maturation site; a paved area between the bioreactors and the matur...)
Property / summary
 
The object of the planned investment is the expansion of the composting plant in the Regional Municipal Waste Processing Plant. A phased expansion is planned. At this stage, the construction of: —3 bioreactors and 1 without armament with process air purification system i.e. biofilter and ventilation system i.e. 3 aeration fans built in a container fan room; compost/stabilisation maturation site; a paved area between the bioreactors and the maturation area – the manoeuvring area/technological area; an airtight underground leaching tank, delivery of a shredder. The purpose of the composting installation is to: — biostabilisation of waste fraction 0-80 mm containing biodegradable waste and the production of compost from green and kitchen waste from selective collection, as well as sewage sludge. Reactor capacity is approx. 9500 Mg/year. The aim of the project is to reduce the landfill of waste, increase recycling and improve the quality of treatment. (English)
Property / summary: The object of the planned investment is the expansion of the composting plant in the Regional Municipal Waste Processing Plant. A phased expansion is planned. At this stage, the construction of: —3 bioreactors and 1 without armament with process air purification system i.e. biofilter and ventilation system i.e. 3 aeration fans built in a container fan room; compost/stabilisation maturation site; a paved area between the bioreactors and the maturation area – the manoeuvring area/technological area; an airtight underground leaching tank, delivery of a shredder. The purpose of the composting installation is to: — biostabilisation of waste fraction 0-80 mm containing biodegradable waste and the production of compost from green and kitchen waste from selective collection, as well as sewage sludge. Reactor capacity is approx. 9500 Mg/year. The aim of the project is to reduce the landfill of waste, increase recycling and improve the quality of treatment. (English) / rank
 
Normal rank
Property / summary: The object of the planned investment is the expansion of the composting plant in the Regional Municipal Waste Processing Plant. A phased expansion is planned. At this stage, the construction of: —3 bioreactors and 1 without armament with process air purification system i.e. biofilter and ventilation system i.e. 3 aeration fans built in a container fan room; compost/stabilisation maturation site; a paved area between the bioreactors and the maturation area – the manoeuvring area/technological area; an airtight underground leaching tank, delivery of a shredder. The purpose of the composting installation is to: — biostabilisation of waste fraction 0-80 mm containing biodegradable waste and the production of compost from green and kitchen waste from selective collection, as well as sewage sludge. Reactor capacity is approx. 9500 Mg/year. The aim of the project is to reduce the landfill of waste, increase recycling and improve the quality of treatment. (English) / qualifier
 
point in time: 21 October 2020
Timestamp+2020-10-21T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 09:52, 21 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
“Expansion of the composting plant at RIPOK Czarnówko”
Project in Poland financed by DG Regio

    Statements

    0 references
    6,133,131.74 zloty
    0 references
    1,471,951.62 Euro
    13 January 2020
    0 references
    7,215,449.11 zloty
    0 references
    1,731,707.79 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 October 2018
    0 references
    31 December 2019
    0 references
    ZAKŁAD ZAGOSPODAROWANIA ODPADÓW „CZYSTA BŁĘKITNA KRAINA” SP. Z O.O. W CZARNÓWKU
    0 references
    0 references
    Przedmiotem planowanej inwestycji jest rozbudowa kompostowni na terenie Regionalnej Instalacji Przetwarzania Odpadów Komunalnych. Zakłada się rozbudowę etapową. Na obecnym etapie zakłada się budowę : -3 bioreaktorów oraz 1 bez uzbrojenia z instalacją do oczyszczania powietrza procesowego tj. biofiltrem oraz system wentylacji tj. 3 wentylatorów napowietrzających zabudowanych w kontenerowej wentylatorowni; placu dojrzewania kompostu/stabilizatu; utwardzonego plac pomiędzy bioreaktorami a placem dojrzewania – teren manewrowy/plac technologiczny; szczelnego, podziemnego zbiornika na odcieki, dostawę rozdrabniarki. Celem instalacji kompostowania jest: - stabilizacja biologiczna odpadów frakcji 0-80 mm zawierającej odpady biodegradowalne oraz produkcja kompostu z odpadów zielonych i kuchennych z selektywnej zbiórki, a także osadów ściekowych. Przepustowość reaktorów to ok. 9500 Mg/rok. Celem projektu jest redukcja składowania odpadów, zwiększenie recyklingu i poprawa jakości przetwarzania. (Polish)
    0 references
    The object of the planned investment is the expansion of the composting plant in the Regional Municipal Waste Processing Plant. A phased expansion is planned. At this stage, the construction of: —3 bioreactors and 1 without armament with process air purification system i.e. biofilter and ventilation system i.e. 3 aeration fans built in a container fan room; compost/stabilisation maturation site; a paved area between the bioreactors and the maturation area – the manoeuvring area/technological area; an airtight underground leaching tank, delivery of a shredder. The purpose of the composting installation is to: — biostabilisation of waste fraction 0-80 mm containing biodegradable waste and the production of compost from green and kitchen waste from selective collection, as well as sewage sludge. Reactor capacity is approx. 9500 Mg/year. The aim of the project is to reduce the landfill of waste, increase recycling and improve the quality of treatment. (English)
    21 October 2020
    0 references

    Identifiers

    RPPM.11.02.00-22-0014/17
    0 references