“Revitalisation of railway line No 59 along the section border of the State — Chrysanthemums (S)” (Q116738): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Removed claim: summary (P836): The project involves design work and the renovation of one gauge, non-electrified, wide gauge (1 520 mm) of railway line number 59 from km 0,000 to km 20,132 with traffic control units, electric power, telecommunication, road junctions at one road and railway line level and engineering structures. The Skupowo — Chrysanthemums segment in km 20,132-27,155 is currently not in charge of PKP PLK S.A., the category of line 59 — secondary. The whole...)
(‎Created claim: summary (P836): The subject of the project are design works and revitalisation of single track, non-electrified wide track (1520 mm) railway line No. 59 in the section from km 0.000 to km 20.132, together with traffic control devices, electric power engineering, telecommunications, intersections in one level of roads and railway lines and engineering facilities. The section Skupowo – Chryzanów in km 20.132-27.155 is currently not included in the management of P...)
Property / summary
 
The subject of the project are design works and revitalisation of single track, non-electrified wide track (1520 mm) railway line No. 59 in the section from km 0.000 to km 20.132, together with traffic control devices, electric power engineering, telecommunications, intersections in one level of roads and railway lines and engineering facilities. The section Skupowo – Chryzanów in km 20.132-27.155 is currently not included in the management of PKP PLK S.A. The category of line No.59 – secondary. The whole subject-matter of the contract includes the performance of: 1) Design documentation necessary for the proper execution of all construction works and obtaining all the required opinions, arrangements, approvals, conditions, decisions and permits necessary for the performance of the subject matter of the contract; 2) All construction works according to the scope of the contract on the basis of the design documentation referred to in point 1, as well as all preparatory works necessary for the performance of the scope of the Agreement and any activities required by Law, prepared by the Contractor and approved by the Employer; 3) Conformity assessment of each structural subsystem covered by the contract at each stage (design, construction and final testing of the subsystem). The contract includes the design and execution of the track range, engineering and traffic control, as well as all sectors necessary for the proper performance of the task. The awarding entity shall pay particular attention to the fact that the whole subject of the contract should be performed in accordance with the Technical Standards. (English)
Property / summary: The subject of the project are design works and revitalisation of single track, non-electrified wide track (1520 mm) railway line No. 59 in the section from km 0.000 to km 20.132, together with traffic control devices, electric power engineering, telecommunications, intersections in one level of roads and railway lines and engineering facilities. The section Skupowo – Chryzanów in km 20.132-27.155 is currently not included in the management of PKP PLK S.A. The category of line No.59 – secondary. The whole subject-matter of the contract includes the performance of: 1) Design documentation necessary for the proper execution of all construction works and obtaining all the required opinions, arrangements, approvals, conditions, decisions and permits necessary for the performance of the subject matter of the contract; 2) All construction works according to the scope of the contract on the basis of the design documentation referred to in point 1, as well as all preparatory works necessary for the performance of the scope of the Agreement and any activities required by Law, prepared by the Contractor and approved by the Employer; 3) Conformity assessment of each structural subsystem covered by the contract at each stage (design, construction and final testing of the subsystem). The contract includes the design and execution of the track range, engineering and traffic control, as well as all sectors necessary for the proper performance of the task. The awarding entity shall pay particular attention to the fact that the whole subject of the contract should be performed in accordance with the Technical Standards. (English) / rank
 
Normal rank
Property / summary: The subject of the project are design works and revitalisation of single track, non-electrified wide track (1520 mm) railway line No. 59 in the section from km 0.000 to km 20.132, together with traffic control devices, electric power engineering, telecommunications, intersections in one level of roads and railway lines and engineering facilities. The section Skupowo – Chryzanów in km 20.132-27.155 is currently not included in the management of PKP PLK S.A. The category of line No.59 – secondary. The whole subject-matter of the contract includes the performance of: 1) Design documentation necessary for the proper execution of all construction works and obtaining all the required opinions, arrangements, approvals, conditions, decisions and permits necessary for the performance of the subject matter of the contract; 2) All construction works according to the scope of the contract on the basis of the design documentation referred to in point 1, as well as all preparatory works necessary for the performance of the scope of the Agreement and any activities required by Law, prepared by the Contractor and approved by the Employer; 3) Conformity assessment of each structural subsystem covered by the contract at each stage (design, construction and final testing of the subsystem). The contract includes the design and execution of the track range, engineering and traffic control, as well as all sectors necessary for the proper performance of the task. The awarding entity shall pay particular attention to the fact that the whole subject of the contract should be performed in accordance with the Technical Standards. (English) / qualifier
 
point in time: 20 October 2020
Timestamp+2020-10-20T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 15:40, 20 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
“Revitalisation of railway line No 59 along the section border of the State — Chrysanthemums (S)”
Project in Poland financed by DG Regio

    Statements

    0 references
    0 references
    0 references
    62,204,811.9 zloty
    0 references
    14,929,154.86 Euro
    13 January 2020
    0 references
    73,182,131.65 zloty
    0 references
    17,563,711.6 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    28 June 2018
    0 references
    9 April 2021
    0 references
    PKP POLSKIE LINIE KOLEJOWE SPÓŁKA AKCYJNA
    0 references

    53°1'58.4"N, 23°36'24.1"E
    0 references

    52°50'9.2"N, 23°45'25.2"E
    0 references
    Przedmiotem projektu są prace projektowe oraz rewitalizacja jednotorowej, niezelektryfikowanej, szerokotorowej (1520 mm) linii kolejowej nr 59 na odcinku od km 0,000 do km 20,132 wraz z urządzeniami sterowania ruchem kolejowym, elektroenergetyką, telekomunikacją, skrzyżowaniami w jednym poziomie dróg kołowych i linii kolejowej oraz obiektami inżynieryjnymi. Odcinek Skupowo - Chryzanów w km 20,132 – 27,155 obecnie nie znajduje się w zarzadzaniu PKP PLK S.A. Kategoria linii nr 59– drugorzędna. Całość przedmiotu zamówienia obejmuje wykonanie: 1) Dokumentacji projektowej niezbędnej do prawidłowego wykonania wszystkich robót budowlanych i uzyskania dla niej wszystkich wymaganych opinii, uzgodnień, dopuszczeń, warunków, decyzji i pozwoleń niezbędnych do realizacji przedmiotu zamówienia; 2) Wszystkich robót budowlanych zgodnie z zakresem zamówienia na podstawie opracowanej przez Wykonawcę i zatwierdzonej przez Zamawiającego dokumentacji projektowej, o której mowa w ppkt 1, oraz wszystkich robót przygotowawczych niezbędnych do wykonania zakresu Umowy oraz wszelkich czynności wymaganych Prawem; 3) Przeprowadzenie oceny zgodności każdego podsystemu strukturalnego objętego zakresem zamówienia na każdym etapie (projektowania, budowy i końcowych prób podsystemu). Zamówienie obejmuje zaprojektowanie i wykonanie zakresu torowego, inżynieryjnego i sterowania ruchem kolejowym oraz wszystkich branż niezbędnych do prawidłowego wykonania zadania. Zamawiający zwraca szczególną uwagę, iż całość przedmiotu Zamówienia powinna być wykonana zgodnie z Standardami Technicznymi. (Polish)
    0 references
    The subject of the project are design works and revitalisation of single track, non-electrified wide track (1520 mm) railway line No. 59 in the section from km 0.000 to km 20.132, together with traffic control devices, electric power engineering, telecommunications, intersections in one level of roads and railway lines and engineering facilities. The section Skupowo – Chryzanów in km 20.132-27.155 is currently not included in the management of PKP PLK S.A. The category of line No.59 – secondary. The whole subject-matter of the contract includes the performance of: 1) Design documentation necessary for the proper execution of all construction works and obtaining all the required opinions, arrangements, approvals, conditions, decisions and permits necessary for the performance of the subject matter of the contract; 2) All construction works according to the scope of the contract on the basis of the design documentation referred to in point 1, as well as all preparatory works necessary for the performance of the scope of the Agreement and any activities required by Law, prepared by the Contractor and approved by the Employer; 3) Conformity assessment of each structural subsystem covered by the contract at each stage (design, construction and final testing of the subsystem). The contract includes the design and execution of the track range, engineering and traffic control, as well as all sectors necessary for the proper performance of the task. The awarding entity shall pay particular attention to the fact that the whole subject of the contract should be performed in accordance with the Technical Standards. (English)
    20 October 2020
    0 references

    Identifiers

    RPPD.04.02.00-20-0003/18