(Removed claim: summary (P836): THE PROJECT CONCERNS THE THERMO-MODERNISATION OF THE 2 PUBLIC BUILDINGS IN THE VICINITY OF A SWIMMING POOL AND A SPORTS HALL. THE PLANNED SCOPE OF WORK INCLUDES A SWIMMING POOL FOR THE MODERNISATION OF THE HOT WATER HEATING SYSTEM FOR THE SWIMMING POOL. THE PROJECT WILL CONTRIBUTE TO THE COST SAVINGS OF THE THERMAL ENERGY IN THE POOL, THE COST SAVINGS OF THE HEAT IN THE ARENA, ANNUAL SAVINGS OF DEMAND FOR NON-RENEWABLE PRIMARY ENERGY IN THE BA...) |
||
Property / summary | |||
Property / summary: THE PROJECT CONCERNS THE THERMO-MODERNISATION OF THE 2 PUBLIC BUILDINGS IN THE VICINITY OF A SWIMMING POOL AND A SPORTS HALL. THE PLANNED SCOPE OF WORK INCLUDES A SWIMMING POOL FOR THE MODERNISATION OF THE HOT WATER HEATING SYSTEM FOR THE SWIMMING POOL. THE PROJECT WILL CONTRIBUTE TO THE COST SAVINGS OF THE THERMAL ENERGY IN THE POOL, THE COST SAVINGS OF THE HEAT IN THE ARENA, ANNUAL SAVINGS OF DEMAND FOR NON-RENEWABLE PRIMARY ENERGY IN THE BASIN OF MORE THAN 25 %, ANNUAL SAVINGS OF DEMAND FOR NON-RENEWABLE PRIMARY ENERGY IN A MULTIARENA FACILITY OF MORE THAN 25 %. A SPORTS HALL UPGRADING THE HEATING SYSTEM, MODERNISATION OF THE SYSTEM FOR COOKING HOT WATER, MECHANICAL VENTILATION WITH RECUPERATIVE SYSTEM, REPLACEMENT OF ROOF STRUCTURES INCLUDING THERMAL INSULATION, INSULATION OF EXTERNAL WALLS, MODERNISATION OF THE INTERNAL ELECTRICAL SYSTEM, INSTALLATION OF LIGHTNING, INSTALLATION OF PHOTOVOLTAIC PANELS, TRANSPORTATION AND DISPOSAL OF ASBESTOS PANELS FROM THE ROOF OF THE BUILDING. THE TASKS TO BE CARRIED OUT ARE AS FOLLOWS: 1 PROJECT PREPARATION 2 CONSTRUCTION WORK 3 PROJECT MANAGEMENT AND USER SERVICE IS MAINLY LOCATED IN THE INHABITANTS OF THE TOWN OF TONGUES, THE MUNICIPALITIES OF OZORKÓW. THE MAIN OBJECTIVE OF THE PROJECT IS TO IMPROVE ENERGY EFFICIENCY IN THE TERRITORY OF THE MUNICIPALITY BY MEANS OF ENERGY EFFICIENCY MEASURES DESIGNED TO PROTECT, REDUCE GREENHOUSE GAS EMISSIONS, INCREASE THE USE OF RENEWABLE ENERGY SOURCES BY IMPLEMENTING INDICATORS IN THE NUMBER OF ENERGY MODERNISED BUILDINGS 2. USEFUL FLOOR AREA OF BUILDINGS UNDERGOING THERMOMODERNISATION 2 782,40 M2 REDUCTION OF ANNUAL PRIMARY ENERGY CONSUMPTION IN PUBLIC BUILDINGS (CO32) 743 734.09 KWH/YEAR ESTIMATED DECREASE OF GREENHOUSE GAS (GHG) EMISSIONS PER YEAR (CO34) 101.28 T CO2/ROK OF SAVED HEAT ENERGY OF 703,19 GJ/YEAR REDUCTION OF FINAL ENERGY CONSUMPTION DUE TO THE 1029,27 GJ/YEAR (English) / rank | |||
Revision as of 15:53, 17 October 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | COMPREHENSIVE RENOVATION OF PUBLIC BUILDINGS FOR SPORT INFRASTRUCTURE |
Project in Poland financed by DG Regio |
Statements
1,424,975.09 zloty
0 references
1,697,611.5 zloty
0 references
83.94 percent
0 references
14 June 2017
0 references
31 December 2020
0 references
GMINA MIASTO OZORKÓW
0 references
PROJEKT DOTYCZY TERMOMODERNIZACJI 2 BUDYNKÓW UŻYTECZNOŚCI PUBLICZNEJ NA TERENIE OZORKOWA BASENU I HALI SPORTOWEJ. PLANOWANY ZAKRES PRAC OBEJMUJE BASEN MODERNIZACJA SYSTEMU PRZYGOTOWANIA C.W.U. PODGRZEWU WODY BASENOWEJ WYMIANĘ STOLARKI ZEWNĘTRZNEJ. PROJEKT PRZYCZYNI SIĘ DO OSIĄGNIĘCIA OSZCZĘDNOŚCI KOSZTÓW ENERGII CIEPLNEJ W OBIEKCIE BASENU, OSZCZĘDNOŚCI KOSZTÓW ENERGII CIEPLNEJ W OBIEKCIE HALI, ROCZNE OSZCZĘDNOŚCI ZAPOTRZEBOWANIA NA NIEODNAWIALNĄ ENERGIĘ PIERWOTNĄ W OBIEKCIE BASENU POWYŻEJ 25%, ROCZNE OSZCZĘDNOŚCI ZAPOTRZEBOWANIA NA NIEODNAWIALNĄ ENERGIĘ PIERWOTNĄ W OBIEKCIE HALI POWYŻEJ 25%. HALA SPORTOWA MODERNIZACJA SYSTEMU GRZEWCZEGO, MODERNIZACJI SYSTEMU PRZYGOTOWANIA C.W.U., SYSTEM WENTYLACJI MECHANICZNEJ Z REKUPERACJĄ, WYMIANA KONSTRUKCJI DACHU WRAZ Z MONTAŻEM IZOLACJI TERMICZNEJ, DOCIEPLENIE ŚCIAN ZEWNĘTRZNYCH, MODERNIZACJĘ INSTALACJI ELEKTRYCZNEJ WEWNĘTRZNEJ, INSTALACJĘ ODGROMOWĄ, MONTAŻ PANELI FOTOWOLTAICZNYCH, TRANSPORT I UTYLIZACJA PŁYT AZBESTOWYCH Z DACHU BUDYNKU. PRZEWIDZIANE ZADANIA: 1 PRZYGOTOWANIE PROJEKTU 2 ROBOTY BUDOWLANE 3 ZARZĄDZANIE PROJEKTEM I JEGO OBSŁUGA UŻYTKOWNIKAMI SĄ GŁOWNIE MIESZKAŃCY MIASTA OZORÓW, GMINY OZORKÓW. GŁÓWNYM CELEM PROJEKTU JEST POPRAWA EFEKTYWNOŚCI ENERGETYCZNEJ NA TERENIE GMINY POPRZEZ DZIAŁANIA TERMOMODERNIZACYJNE ZMIERZAJĄCE DO OCHRONY, OGRANICZENIA EMISJI GAZÓW CIEPLARNIANYCH, WZROSTU WYKORZYSTANIA ODNAWIALNYCH ŹRÓDEŁ ENERGII DZIĘKI JEGO REALIZACJI ZOSTANĄ OSIĄGNIĘTE WSKAŹNIKI LICZBA ZMODERNIZOWANYCH ENERGETYCZNIE BUDYNKÓW 2 SZT. POWIERZCHNIA UŻYTKOWA BUDYNKÓW PODDANYCH TERMOMODERNIZACJI 2 782,40 M2 ZMNIEJSZENIE ROCZNEGO ZUŻYCIA ENERGII PIERWOTNEJ W BUDYNKACH PUBLICZNYCH (CO32) 743 734,09 KWH/ROK SZACOWANY ROCZNY SPADEK EMISJI GAZÓW CIEPLARNIANYCH (CO34) 101,28 T RÓWNOWAŻNIKA CO2/ROK ILOŚĆ ZAOSZCZĘDZONEJ ENERGII CIEPLNEJ 703,19 GJ/ROK ZMNIEJSZENIE ZUŻYCIA ENERGII KOŃCOWEJ W WYNIKU REALIZACJI PROJEKTÓW 1029,27 GJ/ROK (Polish)
0 references
Identifiers
RPLD.04.02.01-10-0020/17
0 references