Development and reconstruction of the sewage treatment plant in Sulęcina, at the same time as the modernisation of the sanitary and water sewerage system in the agglomeration of Sulęcin agglomeration (Q85428): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Removed claim: summary (P836): The project includes the extension and reconstruction of the sewage treatment plant in Sulęcina, modernisation of the sewerage system, including the separation of combined sewerage system into sanitary and rainwater drainage, reconstruction and renovation of the water supply network and the development of the SUW in Sulęcina.The capacity of the plant is not changed and will remain at 14 234 p.e.In contrast, solutions will be put in place to en...)
(‎Created claim: summary (P836): The project includes the extension and reconstruction of the sewage treatment plant in Sulęcin, the modernisation of the sewerage system, including the distribution of general drainage into sanitary and rain drainage, the reconstruction and renovation of the water supply network and the extension of the SUW in Sulęcin. The capacity of the treatment plant is unchanged and will continue to be 14 234 RLM. On the other hand, solutions will be implem...)
Property / summary
 
The project includes the extension and reconstruction of the sewage treatment plant in Sulęcin, the modernisation of the sewerage system, including the distribution of general drainage into sanitary and rain drainage, the reconstruction and renovation of the water supply network and the extension of the SUW in Sulęcin. The capacity of the treatment plant is unchanged and will continue to be 14 234 RLM. On the other hand, solutions will be implemented to remove nitrogen and phosphorus to the parameters required by law. Standards in this area are now being exceeded. In addition, the use of sewage sludge for agricultural use will be improved. On the treatment plant will be made, among others: transport sewage sink, raw sewage pumping plant, blow and moss station. cleaning, chemical phosphorus precipitation station, 2 biological blocks, moss dehydration building, lime tank, dehydrated sediment warehouses, oxygen stabilisation tank, moss thickener. sediment. In view of the planned unbundling of the sewage system, the treatment plant will be rebuilt with a view to the acceptance of rainwater. The modernisation of the sewer system also includes the renovation of sections in poor technical condition and the exclusion from operation of worn sections. In the area of water supply, works will concern the construction of new sections of the network, renovation of sections in poor technical condition and extension of the SUW (2 techn. buildings and 2 clean water tanks). Output indicators will be implemented: Number of reconstructed waste water treatment plants – 1 units; Number of waste water treatment plants supported by the treatment/management of sewage sludge – 1 units; Length of the remodeled sanitary sanitary system – 2,05 km; Length of the refurbished sanitary sanitary system – 3,91 km; Length of the water network built.– 4,20 km; Length of the reconstructed water network – 1,27 km; Length of the refurbished water network – 1,26 km; Number of water treatment stations supported by 1 units; Results indicators will be implemented: Number of additives. persons benefiting from improved purification (English)
Property / summary: The project includes the extension and reconstruction of the sewage treatment plant in Sulęcin, the modernisation of the sewerage system, including the distribution of general drainage into sanitary and rain drainage, the reconstruction and renovation of the water supply network and the extension of the SUW in Sulęcin. The capacity of the treatment plant is unchanged and will continue to be 14 234 RLM. On the other hand, solutions will be implemented to remove nitrogen and phosphorus to the parameters required by law. Standards in this area are now being exceeded. In addition, the use of sewage sludge for agricultural use will be improved. On the treatment plant will be made, among others: transport sewage sink, raw sewage pumping plant, blow and moss station. cleaning, chemical phosphorus precipitation station, 2 biological blocks, moss dehydration building, lime tank, dehydrated sediment warehouses, oxygen stabilisation tank, moss thickener. sediment. In view of the planned unbundling of the sewage system, the treatment plant will be rebuilt with a view to the acceptance of rainwater. The modernisation of the sewer system also includes the renovation of sections in poor technical condition and the exclusion from operation of worn sections. In the area of water supply, works will concern the construction of new sections of the network, renovation of sections in poor technical condition and extension of the SUW (2 techn. buildings and 2 clean water tanks). Output indicators will be implemented: Number of reconstructed waste water treatment plants – 1 units; Number of waste water treatment plants supported by the treatment/management of sewage sludge – 1 units; Length of the remodeled sanitary sanitary system – 2,05 km; Length of the refurbished sanitary sanitary system – 3,91 km; Length of the water network built.– 4,20 km; Length of the reconstructed water network – 1,27 km; Length of the refurbished water network – 1,26 km; Number of water treatment stations supported by 1 units; Results indicators will be implemented: Number of additives. persons benefiting from improved purification (English) / rank
 
Normal rank
Property / summary: The project includes the extension and reconstruction of the sewage treatment plant in Sulęcin, the modernisation of the sewerage system, including the distribution of general drainage into sanitary and rain drainage, the reconstruction and renovation of the water supply network and the extension of the SUW in Sulęcin. The capacity of the treatment plant is unchanged and will continue to be 14 234 RLM. On the other hand, solutions will be implemented to remove nitrogen and phosphorus to the parameters required by law. Standards in this area are now being exceeded. In addition, the use of sewage sludge for agricultural use will be improved. On the treatment plant will be made, among others: transport sewage sink, raw sewage pumping plant, blow and moss station. cleaning, chemical phosphorus precipitation station, 2 biological blocks, moss dehydration building, lime tank, dehydrated sediment warehouses, oxygen stabilisation tank, moss thickener. sediment. In view of the planned unbundling of the sewage system, the treatment plant will be rebuilt with a view to the acceptance of rainwater. The modernisation of the sewer system also includes the renovation of sections in poor technical condition and the exclusion from operation of worn sections. In the area of water supply, works will concern the construction of new sections of the network, renovation of sections in poor technical condition and extension of the SUW (2 techn. buildings and 2 clean water tanks). Output indicators will be implemented: Number of reconstructed waste water treatment plants – 1 units; Number of waste water treatment plants supported by the treatment/management of sewage sludge – 1 units; Length of the remodeled sanitary sanitary system – 2,05 km; Length of the refurbished sanitary sanitary system – 3,91 km; Length of the water network built.– 4,20 km; Length of the reconstructed water network – 1,27 km; Length of the refurbished water network – 1,26 km; Number of water treatment stations supported by 1 units; Results indicators will be implemented: Number of additives. persons benefiting from improved purification (English) / qualifier
 
point in time: 14 October 2020
Timestamp+2020-10-14T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 15:59, 14 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Development and reconstruction of the sewage treatment plant in Sulęcina, at the same time as the modernisation of the sanitary and water sewerage system in the agglomeration of Sulęcin agglomeration
Project in Poland financed by DG Regio

    Statements

    0 references
    22,753,294.91 zloty
    0 references
    5,460,790.78 Euro
    13 January 2020
    0 references
    26,768,582.25 zloty
    0 references
    6,424,459.74 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 February 2015
    0 references
    31 December 2020
    0 references
    GMINA SULĘCIN
    0 references
    0 references

    52°26'29.0"N, 15°6'58.3"E
    0 references
    Projekt obejmuje rozbudowę i przebudowę oczyszczalni ścieków w Sulęcinie, modernizację systemu kanalizacji, w tym rozdział kanalizacji ogólnospławnej na kanalizację sanitarną i deszczową, przebudowę i remont sieci wodociągowej oraz rozbudowę SUW w Sulęcinie. Przepustowość oczyszczalni nie ulega zmianie i wynosić będzie nadal 14 234 RLM. Natomiast wdrażane będą rozwiązania, umożliwiające usuwanie azotu i fosforu do parametrów wymaganych prawem. Obecnie normy w tym zakresie są przekraczane. Ponadto nastąpi poprawa zagospodarowania osadów ściekowych w celu rolniczego wykorzystania. Na oczyszczalni wykonane zostaną m.in. obiekty: zlewnia ścieków dowożonych, pompownia ścieków surowych, stacja dmuchaw i mech. podczyszczania, stacja chemicznego strącania fosforu, 2 bloki biologiczne, budynek mech. odwodniania osadów, zbiornik wapna, magazyny osadu odwodnionego, zbiornik tlenowej stabilizacji, zagęszczacz mech. osadów. W związku z planowanym rozdziałem kanalizacji ogólnospławnej oczyszczalnia zostanie przebudowana pod kątem przyjęcia ścieków deszczowych. Modernizacja systemu kanalizacji obejmuje ponadto renowację odcinków w złym stanie techn. i wyłączenie z eksploatacji odcinków zużytych. W zakresie zaopatrzenia w wodę prace dotyczyć będą budowy nowych odcinków sieci, renowacji odcinków w złym stanie techn. i rozbudowy SUW (2 budynki techn. i 2 zbiorniki na wodę czystą). Realizowane będą wskaźniki produktu: Liczba przebudowanych oczyszczalni ścieków kom.– 1 szt.; Liczba oczyszczalni ścieków kom. wspartych w zakresie przeróbki / zagospodarowania osadów ściekowych – 1 szt.; Długość przebudowanej kanalizacji san.– 2,05 km; Długość wyremontowanej kanalizacji san.– 3,91 km; Długość wybudowanej sieci wodoc.– 4,20 km; Długość przebudowanej sieci wodoc.– 1,27 km; Długość wyremontowanej sieci wodoc.– 1,26 km; Liczba wspartych stacji uzdatniania wody – 1 szt.; Realizowane będą wskaźniki rezultatu: Liczba dodatk. osób korzystających z ulepszonego oczyszczania (Polish)
    0 references
    The project includes the extension and reconstruction of the sewage treatment plant in Sulęcin, the modernisation of the sewerage system, including the distribution of general drainage into sanitary and rain drainage, the reconstruction and renovation of the water supply network and the extension of the SUW in Sulęcin. The capacity of the treatment plant is unchanged and will continue to be 14 234 RLM. On the other hand, solutions will be implemented to remove nitrogen and phosphorus to the parameters required by law. Standards in this area are now being exceeded. In addition, the use of sewage sludge for agricultural use will be improved. On the treatment plant will be made, among others: transport sewage sink, raw sewage pumping plant, blow and moss station. cleaning, chemical phosphorus precipitation station, 2 biological blocks, moss dehydration building, lime tank, dehydrated sediment warehouses, oxygen stabilisation tank, moss thickener. sediment. In view of the planned unbundling of the sewage system, the treatment plant will be rebuilt with a view to the acceptance of rainwater. The modernisation of the sewer system also includes the renovation of sections in poor technical condition and the exclusion from operation of worn sections. In the area of water supply, works will concern the construction of new sections of the network, renovation of sections in poor technical condition and extension of the SUW (2 techn. buildings and 2 clean water tanks). Output indicators will be implemented: Number of reconstructed waste water treatment plants – 1 units; Number of waste water treatment plants supported by the treatment/management of sewage sludge – 1 units; Length of the remodeled sanitary sanitary system – 2,05 km; Length of the refurbished sanitary sanitary system – 3,91 km; Length of the water network built.– 4,20 km; Length of the reconstructed water network – 1,27 km; Length of the refurbished water network – 1,26 km; Number of water treatment stations supported by 1 units; Results indicators will be implemented: Number of additives. persons benefiting from improved purification (English)
    14 October 2020
    0 references

    Identifiers

    POIS.02.03.00-00-0183/16
    0 references