(Removed claim: summary (P836): The extension of the wastewater treatment plant in the ECR will include the extension and reconstruction of the plant, including the construction of two new biological reactors working in a system close to A2/O with secondary settling tanks, the extension of the mechanical cleaning plant, the expansion of the equipment of the sludge management system.The development and modernisation of the wastewater treatment plant in the ECR will be part of...) |
(Created claim: summary (P836): The extension of the sewage treatment plant in Zblewo together with the infrastructure accompanying the plant will include the extension and reconstruction of the treatment plant, including the construction of two new biological reactors operating in a system similar to A2/O with secondary settlers, expansion of mechanical treatment node, expansion of equipment for the economy with excessive sludge. The planned extension and modernisation of the...) |
||||||||||||||
Property / summary | |||||||||||||||
The extension of the sewage treatment plant in Zblewo together with the infrastructure accompanying the plant will include the extension and reconstruction of the treatment plant, including the construction of two new biological reactors operating in a system similar to A2/O with secondary settlers, expansion of mechanical treatment node, expansion of equipment for the economy with excessive sludge. The planned extension and modernisation of the sewage treatment plant in Zblew is in line with the criteria of the competition, as it results from the need to adapt it to the quality requirements of discharged waste water (for biogenic compounds – nitrogen; the limit value is 15 mg N/l and currently in the samples tested is 63,4 mg N/l) and increased throughput. The construction of RES installations up to 40 kW will consist of the construction of batteries of photovoltaic cells producing electricity for the sewage treatment plant, “Construction of a water retention tank with a capacity of 150 m³ in the hydroforne in Zblewo” The scope of the water intake in Zblewo will consist of the construction of a vertical tank with a capacity of 150 m³ at the water intake area. It will be used to store drinking water, which will allow for the correction of periodic water deficits. “Reconstruction of the water supply network in Jezierce” Includes network infrastructure along the road running through Jezierce and a section of the road connecting Jezeerce and Kleszczewo Kościerskie. Material scope: Reconstruction of the water supply system with a length of approx. It’s 2,345 miles. “Reconstruction of the treatment station and extension of water intake in Jezerka” The task will consist of the installation in the existing technical building of water treatment station equipment, i.e. aerators, one-stage filter kits with mineral and catalytic bed, as well as construction of two storage tanks with a capacity of 75 m³ each and a second-degree pumping station. (English) | |||||||||||||||
Property / summary: The extension of the sewage treatment plant in Zblewo together with the infrastructure accompanying the plant will include the extension and reconstruction of the treatment plant, including the construction of two new biological reactors operating in a system similar to A2/O with secondary settlers, expansion of mechanical treatment node, expansion of equipment for the economy with excessive sludge. The planned extension and modernisation of the sewage treatment plant in Zblew is in line with the criteria of the competition, as it results from the need to adapt it to the quality requirements of discharged waste water (for biogenic compounds – nitrogen; the limit value is 15 mg N/l and currently in the samples tested is 63,4 mg N/l) and increased throughput. The construction of RES installations up to 40 kW will consist of the construction of batteries of photovoltaic cells producing electricity for the sewage treatment plant, “Construction of a water retention tank with a capacity of 150 m³ in the hydroforne in Zblewo” The scope of the water intake in Zblewo will consist of the construction of a vertical tank with a capacity of 150 m³ at the water intake area. It will be used to store drinking water, which will allow for the correction of periodic water deficits. “Reconstruction of the water supply network in Jezierce” Includes network infrastructure along the road running through Jezierce and a section of the road connecting Jezeerce and Kleszczewo Kościerskie. Material scope: Reconstruction of the water supply system with a length of approx. It’s 2,345 miles. “Reconstruction of the treatment station and extension of water intake in Jezerka” The task will consist of the installation in the existing technical building of water treatment station equipment, i.e. aerators, one-stage filter kits with mineral and catalytic bed, as well as construction of two storage tanks with a capacity of 75 m³ each and a second-degree pumping station. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The extension of the sewage treatment plant in Zblewo together with the infrastructure accompanying the plant will include the extension and reconstruction of the treatment plant, including the construction of two new biological reactors operating in a system similar to A2/O with secondary settlers, expansion of mechanical treatment node, expansion of equipment for the economy with excessive sludge. The planned extension and modernisation of the sewage treatment plant in Zblew is in line with the criteria of the competition, as it results from the need to adapt it to the quality requirements of discharged waste water (for biogenic compounds – nitrogen; the limit value is 15 mg N/l and currently in the samples tested is 63,4 mg N/l) and increased throughput. The construction of RES installations up to 40 kW will consist of the construction of batteries of photovoltaic cells producing electricity for the sewage treatment plant, “Construction of a water retention tank with a capacity of 150 m³ in the hydroforne in Zblewo” The scope of the water intake in Zblewo will consist of the construction of a vertical tank with a capacity of 150 m³ at the water intake area. It will be used to store drinking water, which will allow for the correction of periodic water deficits. “Reconstruction of the water supply network in Jezierce” Includes network infrastructure along the road running through Jezierce and a section of the road connecting Jezeerce and Kleszczewo Kościerskie. Material scope: Reconstruction of the water supply system with a length of approx. It’s 2,345 miles. “Reconstruction of the treatment station and extension of water intake in Jezerka” The task will consist of the installation in the existing technical building of water treatment station equipment, i.e. aerators, one-stage filter kits with mineral and catalytic bed, as well as construction of two storage tanks with a capacity of 75 m³ each and a second-degree pumping station. (English) / qualifier | |||||||||||||||
point in time: 14 October 2020
|
Revision as of 15:35, 14 October 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | MODERNISATION AND EXTENSION OF THE WATER AND WASTEWATER SYSTEM IN ZBLEWC AGGLOMERATION |
Project in Poland financed by DG Regio |
Statements
7,255,439.3 zloty
0 references
8,535,810.95 zloty
0 references
85.0 percent
0 references
2 January 2018
0 references
31 January 2022
0 references
GMINA ZBLEWO
0 references
Rozbudowa oczyszczalni ścieków w Zblewie wraz z infrastrukturą towarzyszącą obejmie rozbudowę i przebudowę oczyszczalni, w tym budowę dwóch nowych reaktorów biologicznych pracujących w układzie zbliżonym do A2/O z osadnikami wtórnymi, rozbudowę węzła oczyszczania mechanicznego, rozbudowę urządzeń gospodarki osadem nadmiernym. Planowana do realizacji rozbudowa i modernizacja oczyszczalni ścieków w Zblewie wpisuje się kryteria konkursu, gdyż wynika z konieczności jej dostosowania do wymogów dotyczących jakości odprowadzanych ścieków (w zakresie związków biogennych - azotu; wartość dopuszczalna to 15 mg N/l, a obecnie w badanych próbkach wynosi ona 63,4 mg N/l) i zwiększenia przepustowości. Budowa instalacji OZE o mocy do 40 kW polegać będzie na budowie baterii ogniw fotowoltaicznych produkujących energię elektryczną na potrzeby oczyszczalni ścieków, "Budowa zbiornika retencyjnego na wodę o pojemności 150 m3 w hydroforni w Zblewie” Zakres realizowany na terenie ujęcia wody w Zblewie polegać będzie na wykonaniu zbiornika pionowego, jednokomorowego o pojemności 150 m3 na terenie ujęcia wody. Służyć będzie magazynowaniu wody pitnej, co pozwoli na wyrównanie okresowych deficytów wody. „Przebudowa sieci wodociągowej w m. Jezierce” Obejmuje infrastrukturę sieci wzdłuż drogi przebiegającej przez m. Jezierce oraz odcinku drogi łączącej Jezierce i Kleszczewo Kościerskie. Zakres rzeczowy: Przebudowa sieci wodociągowej o długości ok. 2,345 km. „Przebudowa stacji uzdatniania i rozbudowa ujęcia wody w m. Jezierce” Zadanie polegać będzie na montażu w istniejącym budynku technicznym urządzeń stacji uzdatniania wody, tj. aeratorów, zestawów filtracyjnych jednostopniowych ze złożem mineralnym i katalitycznym a także na budowie dwóch zbiorników retencyjnych o pojemności 75 m3 każdy oraz pompowni II stopnia. (Polish)
0 references
The extension of the sewage treatment plant in Zblewo together with the infrastructure accompanying the plant will include the extension and reconstruction of the treatment plant, including the construction of two new biological reactors operating in a system similar to A2/O with secondary settlers, expansion of mechanical treatment node, expansion of equipment for the economy with excessive sludge. The planned extension and modernisation of the sewage treatment plant in Zblew is in line with the criteria of the competition, as it results from the need to adapt it to the quality requirements of discharged waste water (for biogenic compounds – nitrogen; the limit value is 15 mg N/l and currently in the samples tested is 63,4 mg N/l) and increased throughput. The construction of RES installations up to 40 kW will consist of the construction of batteries of photovoltaic cells producing electricity for the sewage treatment plant, “Construction of a water retention tank with a capacity of 150 m³ in the hydroforne in Zblewo” The scope of the water intake in Zblewo will consist of the construction of a vertical tank with a capacity of 150 m³ at the water intake area. It will be used to store drinking water, which will allow for the correction of periodic water deficits. “Reconstruction of the water supply network in Jezierce” Includes network infrastructure along the road running through Jezierce and a section of the road connecting Jezeerce and Kleszczewo Kościerskie. Material scope: Reconstruction of the water supply system with a length of approx. It’s 2,345 miles. “Reconstruction of the treatment station and extension of water intake in Jezerka” The task will consist of the installation in the existing technical building of water treatment station equipment, i.e. aerators, one-stage filter kits with mineral and catalytic bed, as well as construction of two storage tanks with a capacity of 75 m³ each and a second-degree pumping station. (English)
14 October 2020
0 references
Identifiers
POIS.02.03.00-00-0094/17
0 references