Modernisation of 110/15 kV Waszów station to increase security of electricity supply (Q86100): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed an Item: Fixing rounding issue)
(‎Removed claim: summary (P836): The project covers the modernisation of the electricity station Warzeszów and its associated infrastructure.The direct objective of the project is the improvement of the power supply of the city of Świnoujście and the western part of the municipality of Międzyzdroje, as well as the reliability of the energy supply and the increased energy security of the region through the modernisation of 110/15 kV stations., remove_old_english_translation)
Property / summary
The project covers the modernisation of the electricity station Warzeszów and its associated infrastructure.The direct objective of the project is the improvement of the power supply of the city of Świnoujście and the western part of the municipality of Międzyzdroje, as well as the reliability of the energy supply and the increased energy security of the region through the modernisation of 110/15 kV stations. (English)
 
Property / summary: The project covers the modernisation of the electricity station Warzeszów and its associated infrastructure.The direct objective of the project is the improvement of the power supply of the city of Świnoujście and the western part of the municipality of Międzyzdroje, as well as the reliability of the energy supply and the increased energy security of the region through the modernisation of 110/15 kV stations. (English) / rank
Normal rank
 

Revision as of 15:32, 14 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Modernisation of 110/15 kV Waszów station to increase security of electricity supply
Project in Poland financed by DG Regio

    Statements

    0 references
    8,006,620.47 zloty
    0 references
    1,921,588.91 Euro
    13 January 2020
    0 references
    13,200,000.0 zloty
    0 references
    3,168,000.0 Euro
    13 January 2020
    0 references
    60.66 percent
    0 references
    1 January 2020
    0 references
    31 December 2021
    0 references
    ENEA OPERATOR SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
    0 references
    0 references

    53°49'37.2"N, 14°20'8.5"E
    0 references
    Projekt obejmuje swoim zakresem modernizację stacji elektroenergetycznej Warszów wraz z infrastrukturą towarzyszącą. Celem bezpośrednim projektu jest poprawa zasilania miasta Świnoujście oraz zachodniej części gminy Międzyzdroje, a także niezawodności dostaw energii i zwiększenie bezpieczeństwa energetycznego regionu, poprzez modernizację stacji 110/15 kV Warszów. (Polish)
    0 references

    Identifiers

    POIS.07.01.00-00-0001/19