Reconstruction of the 110/15 kV substation in order to enable the development of renewable energy (Q84416): Difference between revisions
Jump to navigation
Jump to search
(Removed claim: summary (P836): The scope of the project involves the reconstruction of the GPZ 110/15 kV Kleczew electricity station in order to enable the development of renewable energy.The station is part of the 110 kV distribution network where the 15 kV electricity transition is performed., remove_old_english_translation) |
(Created claim: summary (P836): The scope of the project includes the reconstruction of the power station GPZ 110/15 kV Kleczew in order to enable the development of renewable energy. The station is part of a distribution network at a voltage of 110 kV, where electricity is transformed to a voltage of 15 kV., translated_summary) |
||||||||||||||
Property / summary | |||||||||||||||
The scope of the project includes the reconstruction of the power station GPZ 110/15 kV Kleczew in order to enable the development of renewable energy. The station is part of a distribution network at a voltage of 110 kV, where electricity is transformed to a voltage of 15 kV. (English) | |||||||||||||||
Property / summary: The scope of the project includes the reconstruction of the power station GPZ 110/15 kV Kleczew in order to enable the development of renewable energy. The station is part of a distribution network at a voltage of 110 kV, where electricity is transformed to a voltage of 15 kV. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The scope of the project includes the reconstruction of the power station GPZ 110/15 kV Kleczew in order to enable the development of renewable energy. The station is part of a distribution network at a voltage of 110 kV, where electricity is transformed to a voltage of 15 kV. (English) / qualifier | |||||||||||||||
point in time: 14 October 2020
|
Revision as of 13:01, 14 October 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Reconstruction of the 110/15 kV substation in order to enable the development of renewable energy |
Project in Poland financed by DG Regio |
Statements
2,648,488.37 zloty
0 references
3,645,000.0 zloty
0 references
72.66 percent
0 references
28 December 2018
0 references
30 September 2020
0 references
ENERGA-OPERATOR SPÓŁKA AKCYJNA
0 references
Zakres Projektu obejmuje przebudowę stacji elektroenergetycznej GPZ 110/15 kV Kleczew celem umożliwienia rozwoju energetyki odnawialnej. Stacja stanowi element sieci dystrybucyjnej na napięciu 110 kV, na której odbywa się transformacja energii elektrycznej na napięcie 15 kV. (Polish)
0 references
The scope of the project includes the reconstruction of the power station GPZ 110/15 kV Kleczew in order to enable the development of renewable energy. The station is part of a distribution network at a voltage of 110 kV, where electricity is transformed to a voltage of 15 kV. (English)
14 October 2020
0 references
Identifiers
POIS.01.01.02-00-0004/18
0 references