Introduction of a new generation of steel flangs on the market as a result of the expansion of the ‘MALMS’ facility in Choszczno (Q137409): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed an Item)
(‎Changed an Item)
Property / fund
 
Property / fund: European Regional Development Fund / rank
 
Normal rank

Revision as of 13:14, 7 June 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Introduction of a new generation of steel flangs on the market as a result of the expansion of the ‘MALMS’ facility in Choszczno
Project in Poland financed by DG Regio

    Statements

    0 references
    1,755,966.28 zloty
    0 references
    421,431.9072 Euro
    13 January 2020
    0 references
    3,926,979.16 zloty
    0 references
    942,474.9984 Euro
    13 January 2020
    0 references
    55.0 percent
    0 references
    27 July 2018
    0 references
    31 December 2019
    0 references
    LETKOMILLER MARIUSZ "MALMS"
    0 references
    Realizacja projektu obejmuje rozbudowę i przebudowę istniejącego budynku produkcyjno-magazynowego o pomieszczenia produkcyjne oraz zakup niezbędnych środków trwałych. W ramach projektu planuje się zrealizować następujące wydatki: 1. Roboty budowlane w zakresie obiektów budowlanych 2. Zakup suwnicy - 2 szt. 3. Zakup suwnicy z obrotnicą - 2 szt. 4. Zakup komory śrutowniczej - 1 szt. 5. Zakup filtrowentylatorów - 3 szt. 6. Zakup specjalizowanej wiertarki do trasowania - 1 szt. 7. Zakup regałów magazynowych oraz stołu z krzesłami. Realizacja projektu planowana jest na okres od stycznia 2018 r. do grudnia 2019 r. (Polish)
    0 references
    The implementation of the project involves the extension and reconstruction of the existing building and storage building with a production area and the purchase of the necessary fixed assets. In the framework of the project, the following expenditure is to be realised: 1. Construction work for construction works 2. The purchase of cranes — 2 3. Purchase of a crane with a revolution — 2 4. Purchase of the screw chamber — 1. 5. The purchase of the filtifers — 3. 6. Purchase of a specialised drilling drill — 1 7. Purchase of storage racks and a table with chairs. The project is planned to run from January 2018 to December 2019. (English)
    0 references

    Identifiers

    RPZP.01.06.00-32-0013/17
    0 references