The subject of the project is the purchase and installation of photovoltaic sets. The installations will be installed on 354 private buildings in the Municipality of Germany with a total capacity of 1.269 MW. 169 units — installations with a power of 3.1 kW, 185 units of installations with a capacity of 4.03 kW, So far conventional electricity sources will be replaced by free solar energy. The achievement of the specific objectives will indirectly increase the attractiveness of the region’s tourism, improve the living conditions of its inhabitants and directly improve the natural environment.The target group will be residents of the municipality of Germany (private users), who expressed their willingness to join the project expressed in the form of a survey. Project indicators — additional renewable energy generation capacity — 1.269 MW. Electricity production -1205.97 MWe/year. Number of electricity generating units — 354 pcs. Reduction of CO2 emissions — 981.66 Mg/year.The air quality in the municipality is good; there is no obligation to draw up an air quality programme. The POP for the Lublin zone does not indicate any corrective or short-term measures for the municipality of Germany, which means that the levels of substances subject to air quality assessment have not been exceeded. photovoltaic installations will be installed on residential buildings (facade, roof), in the absence of the possibility to install the above-mentioned installations on the roof or facade, photovoltaic panels will be installed on commercial buildings such as a garage, a gazebo with the exclusive use of energy production for the residential needs of households. Photovoltaic panels will be on-grid installations, i.e. energy will be consumed on an ongoing basis, and potential surplus electricity goes to the power plant.The project concerns only residential buildings of private persons. The project will not be implemented on buildings protected by monuments or in areas covered by nature protection. The project will be implemented on private residential buildings. (English)
Property / summary: The subject of the project is the purchase and installation of photovoltaic sets. The installations will be installed on 354 private buildings in the Municipality of Germany with a total capacity of 1.269 MW. 169 units — installations with a power of 3.1 kW, 185 units of installations with a capacity of 4.03 kW, So far conventional electricity sources will be replaced by free solar energy. The achievement of the specific objectives will indirectly increase the attractiveness of the region’s tourism, improve the living conditions of its inhabitants and directly improve the natural environment.The target group will be residents of the municipality of Germany (private users), who expressed their willingness to join the project expressed in the form of a survey. Project indicators — additional renewable energy generation capacity — 1.269 MW. Electricity production -1205.97 MWe/year. Number of electricity generating units — 354 pcs. Reduction of CO2 emissions — 981.66 Mg/year.The air quality in the municipality is good; there is no obligation to draw up an air quality programme. The POP for the Lublin zone does not indicate any corrective or short-term measures for the municipality of Germany, which means that the levels of substances subject to air quality assessment have not been exceeded. photovoltaic installations will be installed on residential buildings (facade, roof), in the absence of the possibility to install the above-mentioned installations on the roof or facade, photovoltaic panels will be installed on commercial buildings such as a garage, a gazebo with the exclusive use of energy production for the residential needs of households. Photovoltaic panels will be on-grid installations, i.e. energy will be consumed on an ongoing basis, and potential surplus electricity goes to the power plant.The project concerns only residential buildings of private persons. The project will not be implemented on buildings protected by monuments or in areas covered by nature protection. The project will be implemented on private residential buildings. (English) / rank
 
Normal rank
Property / summary: The subject of the project is the purchase and installation of photovoltaic sets. The installations will be installed on 354 private buildings in the Municipality of Germany with a total capacity of 1.269 MW. 169 units — installations with a power of 3.1 kW, 185 units of installations with a capacity of 4.03 kW, So far conventional electricity sources will be replaced by free solar energy. The achievement of the specific objectives will indirectly increase the attractiveness of the region’s tourism, improve the living conditions of its inhabitants and directly improve the natural environment.The target group will be residents of the municipality of Germany (private users), who expressed their willingness to join the project expressed in the form of a survey. Project indicators — additional renewable energy generation capacity — 1.269 MW. Electricity production -1205.97 MWe/year. Number of electricity generating units — 354 pcs. Reduction of CO2 emissions — 981.66 Mg/year.The air quality in the municipality is good; there is no obligation to draw up an air quality programme. The POP for the Lublin zone does not indicate any corrective or short-term measures for the municipality of Germany, which means that the levels of substances subject to air quality assessment have not been exceeded. photovoltaic installations will be installed on residential buildings (facade, roof), in the absence of the possibility to install the above-mentioned installations on the roof or facade, photovoltaic panels will be installed on commercial buildings such as a garage, a gazebo with the exclusive use of energy production for the residential needs of households. Photovoltaic panels will be on-grid installations, i.e. energy will be consumed on an ongoing basis, and potential surplus electricity goes to the power plant.The project concerns only residential buildings of private persons. The project will not be implemented on buildings protected by monuments or in areas covered by nature protection. The project will be implemented on private residential buildings. (English) / qualifier
 
point in time: 21 October 2022
Timestamp+2022-10-21T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 13:21, 21 October 2022

Project Q4420993 in Poland
Language Label Description Also known as
English
ECO-EFFECTIVE COMMUNE OF GERMANY STAGE V
Project Q4420993 in Poland

    Statements

    0 references
    2,595,650.0 zloty
    0 references
    577,012.99 Euro
    0 references
    5,191,300.0 zloty
    0 references
    1,154,025.99 Euro
    0 references
    50.0 percent
    0 references
    21 August 2019
    0 references
    31 October 2022
    0 references
    GMINA NIEMCE
    0 references
    Przedmiotem projektu jest zakup i instalacja zestawów fotowoltaicznych. Instalacje zostaną zamontowane na 354 obiektach prywatnych w Gminie Niemce o łącznej mocy 1,269 MW. 169 sztuk - instalacji o mocy 3,1 kW, 185 sztuk instalacji o mocy 4,03 kW, Dotychczasowe konwencjonalne źródła energii elektrycznej zostaną zastąpione darmową energią słoneczną. Realizacja celów szczegółowych wpłynie pośrednio na wzrost atrakcyjności turystycznej regionu, poprawę warunków życia jego mieszkańców oraz bezpośrednio na poprawę stanu środowiska naturalnego.Grupą docelową będą mieszkańcy gminy Niemce (użytkownicy prywatni), którzy wyrazili chęć przystąpienia do projektu wyrażoną w formie ankiety. Wskaźniki projektu- dodatkowa moc wytwarzania energii odnawialnej - 1,269 MW. Produkcja energii elektrycznej -1205,97 MWe/rok. Liczba jednostek wytwarzania energii elektrycznej - 354 szt. Spadek emisji CO 2 - 981,66 Mg/rok.Jakość powietrza w gminie jest dobra; nie ma obowiązku opracowania programu ochrony powietrza. W POP dla strefy lubelskiej nie wskazano działań naprawczych ani krótkoterminowych dla gminy Niemce, co oznacza że na jej terenie nie odnotowano przekroczenia poziomów substancji podlegających ocenie jakości powietrza. instalacje fotowoltaiczne montowane będą na budynkach mieszkalnych (elewacja, dach), w przypadku braku możliwości montażu ww. instalacji na dachu bądź elewacji, panele fotowoltaiczne zostaną zamontowane na budynkach gospodarczych typu garaż, altana z wyłącznym przeznaczeniem produkcji energii na potrzeby mieszkalne gospodarstw domowych. Panele fotowoltaiczne będą instalacjami typu on -grid, czyli energia zużywana będzie na bieżąco, a ewentualne nadwyżki prądu trafiają do zakładu energetycznego.Projekt dotyczy wyłącznie budynków mieszkalnych osób prywatnych. Projekt nie będzie realizowany na budynkach objętych ochroną zabytków a także na obszarach objętych ochroną przyrody. Projekt będzie realizowany na prywatnych budynkach mieszkalnych. (Polish)
    0 references
    The subject of the project is the purchase and installation of photovoltaic sets. The installations will be installed on 354 private buildings in the Municipality of Germany with a total capacity of 1.269 MW. 169 units — installations with a power of 3.1 kW, 185 units of installations with a capacity of 4.03 kW, So far conventional electricity sources will be replaced by free solar energy. The achievement of the specific objectives will indirectly increase the attractiveness of the region’s tourism, improve the living conditions of its inhabitants and directly improve the natural environment.The target group will be residents of the municipality of Germany (private users), who expressed their willingness to join the project expressed in the form of a survey. Project indicators — additional renewable energy generation capacity — 1.269 MW. Electricity production -1205.97 MWe/year. Number of electricity generating units — 354 pcs. Reduction of CO2 emissions — 981.66 Mg/year.The air quality in the municipality is good; there is no obligation to draw up an air quality programme. The POP for the Lublin zone does not indicate any corrective or short-term measures for the municipality of Germany, which means that the levels of substances subject to air quality assessment have not been exceeded. photovoltaic installations will be installed on residential buildings (facade, roof), in the absence of the possibility to install the above-mentioned installations on the roof or facade, photovoltaic panels will be installed on commercial buildings such as a garage, a gazebo with the exclusive use of energy production for the residential needs of households. Photovoltaic panels will be on-grid installations, i.e. energy will be consumed on an ongoing basis, and potential surplus electricity goes to the power plant.The project concerns only residential buildings of private persons. The project will not be implemented on buildings protected by monuments or in areas covered by nature protection. The project will be implemented on private residential buildings. (English)
    21 October 2022
    0 references
    WOJ.: LUBELSKIE, POW.: lubelski
    0 references

    Identifiers

    RPLU.04.01.00-06-0133/19
    0 references