Solar energy development of Coop Lőrinci Zrt. in Rózsaszentmárton (Q3933764): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Removed claims)
(‎Changed an Item: fix budget)
Property / co-financing rate
 
55.0 percent
Amount55.0 percent
Unitpercent
Property / co-financing rate: 55.0 percent / rank
 
Normal rank
Property / budget
 
8,331,000.0 forint
Amount8,331,000.0 forint
Unitforint
Property / budget: 8,331,000.0 forint / rank
 
Normal rank
Property / budget
 
23,551.74 Euro
Amount23,551.74 Euro
UnitEuro
Property / budget: 23,551.74 Euro / rank
 
Preferred rank
Property / budget: 23,551.74 Euro / qualifier
 
exchange rate to Euro: 0.002827 Euro
Amount0.002827 Euro
UnitEuro
Property / budget: 23,551.74 Euro / qualifier
 
point in time: 14 February 2022
Timestamp+2022-02-14T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0
Property / EU contribution
 
4,582,050.0 forint
Amount4,582,050.0 forint
Unitforint
Property / EU contribution: 4,582,050.0 forint / rank
 
Normal rank
Property / EU contribution
 
12,953.46 Euro
Amount12,953.46 Euro
UnitEuro
Property / EU contribution: 12,953.46 Euro / rank
 
Preferred rank
Property / EU contribution: 12,953.46 Euro / qualifier
 
exchange rate to Euro: 0.002827 Euro
Amount0.002827 Euro
UnitEuro
Property / EU contribution: 12,953.46 Euro / qualifier
 
point in time: 14 February 2022
Timestamp+2022-02-14T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 22:24, 14 February 2022

Project Q3933764 in Hungary
Language Label Description Also known as
English
Solar energy development of Coop Lőrinci Zrt. in Rózsaszentmárton
Project Q3933764 in Hungary

    Statements

    0 references
    0 references
    4,582,050.0 forint
    0 references
    12,953.46 Euro
    0.002827 Euro
    14 February 2022
    0 references
    8,331,000.0 forint
    0 references
    23,551.74 Euro
    0.002827 Euro
    14 February 2022
    0 references
    55.0 percent
    0 references
    26 June 2020
    0 references
    14 September 2020
    0 references
    COOP Lőrinci Kereskedelmi Zártkörűen Működő Részvénytársaság
    0 references
    0 references

    47°47'1.00"N, 19°44'24.11"E
    0 references
    A projekt keretében 31,92 kWp névleges teljesítményű napelemes rendszer beszerzése és telepítése valósul meg (nem engedélyköteles) 2020.05.04 és 2021.05.03 között. A projekt előkészítése során az alábbi lépések valósultak meg: - Telephelyek és fióktelepek felmérése, a pályázatra alkalmas helyszínek szűrése - Előzetes ellenőrzés a pályázat elvárásainak való megfelelés érdekében - Leendő kivitelező kiválasztása árajánlatok, fajlagos költségek alapján - Egyeztetések a kivitelezővel, a Coop üzletlánc energetikai szakértőjével, a bevonandó műszaki ellenőrrel Projektünk illeszkedik stratégiánkhoz és missziónkhoz, a pályázati felhívás elvárásaihoz, továbbá a Coop üzletlánc és tagjai által 2016-ban megkezdett boltmegújítási elképzelésekhez. Az elmúlt években saját forrásból is folyamatosan hajtottunk végre fejlesztéseket, ami által üzleteink energetikai hatékonysága is nőtt. Mivel a jelen projekttel párhuzamosan egy kisebb napelemes fejlesztést is végrehajtunk, amihez szintén pályázati forrást vontunk be (GINOP-4.1.3-19-2019-00833), a pályázat témája, a megvalósítás lépései nem idegenek számunkra. Ennek megfelelően a szükséges menedzsment- és megvalósítási szakértelemmel is rendelkezünk, ezt azonban a siker érdekében kiegészítjük hozzáértő és tapasztalt kivitelező, műszaki ellenőr és energetikai szakreferens bevonásával. A projekt céljai: költségcsökkentés (rezsi), ÜHG-gázok kibocsátásának csökkentése, primer energiafelhasználás csökkentése, a technológiai fejlettség és a versenyképesség növelése. A projekt végső eredménye és hatása a környezetterhelés jelentős mértékű csökkentése, és a költségek lehető legmagasabb mértékű megtakarítása, amelyek ily módon újabb projektekre, fejlesztésekre, befektetésekre fordíthatók (ami tovább növeli a cég stabilitását és versenyképességét). Ennek érdekében a projekt az alábbi legfontosabb megvalósítási lépésekből, szakaszokból épül fel: - Napelemes rendszer és tartószerkezet kiszállítása, telepítése inverterrel - Érintésvédelmi felülvizsgálat és próbaüzem - Monitoring rendszer beüzemelése a naprakész adatok biztosítása érdekében - Áramszolgáltatói ügyintézés - Áramtermelés megkezdése, a projekt hasznosítása A tervezett napelemes rendszer és a kapcsolódó szolgáltatások rövid bemutatása: 31,92 kWp teljesítményű, komplett napelemes rendszer paraméterei, komponensei: - 114 db, egyenként 280 Wp teljesítményű polykristályos napelem panel (VTSZ: 85414090). - 1 db ABB TRIO 27.6-TL-OUTD-S2 3 fázisú napelemes inverter modul (VTSZ: 85044084). - Időjárásálló ferde tető tartószerkezet rendszer (VTSZ: 76042100). - AC/DC oldali védelmi berendezések. - Solar kábel (4 mm2). - Csatlakozók, szerelvények, csavarok, kábeltálcák, egyéb segédanyagok. A kivitelezés lépései: - Kiszállítás, kiszállás - Tartószerkezet rögzítése ferde tetőre - Rendszer telepítése, kivitelezése - Inverter csatlakoztatása, felprogramozása, beállítása - Érintésvédelmi vizsgálat és jegyzőkönyvezése - Próbaüzem, átadás/átvétel - Garanciális helytállás Egyéb, a kivitelező által vállalt szolgáltatások: - Kiszállás, felmérés, árajánlat, megtérülési kalkuláció - Műszaki dokumentáció - Villamos tervezés - Egyvonalas rajz - Teljes áramszolgáltatói ügyintézés (Hungarian)
    0 references
    The project will purchase and install a solar system with a rated power of 31.92 kWp between 04.05.2020 and 03.05.2021 (not subject to authorisation). The following steps were taken in the preparation of the project: — Assessment of sites and branches, screening of sites suitable for the tender — Preliminary verification to meet the requirements of the tender — Selection of a prospective contractor based on quotations, unit costs — Conciliations with the contractor, the energy expert of the Coop business chain, the technical inspector to be involved Our project fits with our strategy and mission, the requirements of the call for applications, and the business renewal ideas started by Coop and its members in 2016. In recent years, we have been continuously developing from our own resources, which has also increased the energy efficiency of our businesses. Since we are implementing a small solar-powered development in parallel with this project, for which we have also involved a grant source (GINOP-4.1.3-19-2019-00833), the subject of the application, the steps of implementation are not alien to us. Accordingly, we also have the necessary management and implementation expertise, but for the sake of success, we complement this with the involvement of competent and experienced contractors, technical inspectors and energy policy officers. Objectives of the project: reducing costs (overhead), reducing GHG emissions, reducing primary energy use, increasing technological development and competitiveness. The final result and impact of the project is a significant reduction of the environmental burden and the highest possible cost savings, which can thus be spent on newer projects, developments and investments (which further enhances the firm’s stability and competitiveness). To this end, the project consists of the following key implementation steps and phases: — Delivery and installation of solar system and support structure with inverter — Touch protection inspection and trial operation — Installation of a monitoring system to ensure up-to-date data — Power supply administration — Start of electricity production, utilisation of the project Short presentation of the planned solar system and related services: Parameters and components of a complete solar system with a power of 31.92 kWp: — 114 polycrystalline solar panels with a capacity of 280 Wp (VTSZ: 85414090). — 1 pcs ABB TRIO 27.6-TL-OUTD-S2 3-phase solar inverter module (VTSZ: 85044084). — Weatherproof inclined roof support structure system (VTSZ: 76042100). — AC/DC side defence equipment. — Solar cable (4 mm²). — Connectors, fittings, screws, cable trays, other auxiliary materials. The steps of the construction: — Delivery, disembarkation — Fixing of the holding structure on an inclined roof — Installation and implementation of the system — Connection, programming and adjustment of the Inverter — Touch protection inspection and recording — Proof plant, handover/receipt — Guaranteed liability Other services undertaken by the contractor: — Disembarkation, survey, quotation, calculation of return — Technical documentation — Electrical design — Single-line drawing — Full power supply administration (English)
    8 February 2022
    0 references
    Le projet permettra d’acheter et d’installer un système solaire d’une puissance nominale de 31,92 kWc entre le 04.05.2020 et le 03.05.2021 (non soumis à autorisation). Les mesures suivantes ont été prises dans le cadre de la préparation du projet: — Évaluation des sites et des succursales, examen des sites adaptés à l’offre — Vérification préliminaire pour répondre aux exigences de l’offre — Sélection d’un contractant potentiel sur la base des devis, coûts unitaires — Conciliations avec le contractant, l’expert en énergie de la chaîne d’affaires Coop, l’inspecteur technique à impliquer Notre projet s’inscrit dans notre stratégie et notre mission, les exigences de l’appel à candidatures et les idées de renouvellement d’entreprise lancées par Coop et ses membres en 2016. Ces dernières années, nous n’avons cessé de développer nos propres ressources, ce qui a également accru l’efficacité énergétique de nos activités. Comme nous mettons en œuvre un petit développement solaire en parallèle avec ce projet, pour lequel nous avons également impliqué une source de subvention (GINOP-4.1.3-19-2019-00833), le sujet de la demande, les étapes de mise en œuvre ne nous sont pas étrangères. En conséquence, nous disposons également de l’expertise nécessaire en matière de gestion et de mise en œuvre, mais, par souci de succès, nous le complétons avec la participation d’entrepreneurs compétents et expérimentés, d’inspecteurs techniques et de responsables de la politique énergétique. Objectifs du projet: réduire les coûts (frais généraux), réduire les émissions de GES, réduire la consommation d’énergie primaire, accroître le développement technologique et la compétitivité. Le résultat final et l’impact du projet sont une réduction significative de la charge environnementale et les économies de coûts les plus élevées possibles, qui peuvent donc être dépensées pour des projets, des développements et des investissements plus récents (ce qui renforce encore la stabilité et la compétitivité de l’entreprise). À cette fin, le projet comprend les étapes et phases clés de mise en œuvre suivantes: — Fourniture et installation d’un système solaire et d’une structure de support avec onduleur — Inspection de la protection tactile et opération d’essai — Installation d’un système de surveillance pour assurer la mise à jour des données — Administration de l’alimentation électrique — Début de la production d’électricité, utilisation du projet Présentation succincte du système solaire prévu et services connexes: Paramètres et composants d’un système solaire complet d’une puissance de 31,92 kWc: — 114 panneaux solaires polycristallins d’une capacité de 280 Wp (VTSZ: 85414090). — 1 pcs ABB TRIO 27.6-TL-OUTD-S2 Module d’onduleur solaire 3 phases (VTSZ: 85044084). — Système de structure de support inclinée inclinée résistant aux intempéries (VTSZ: 76042100). — Matériel de défense latérale AC/DC. — Câble solaire (4 mm²). — Connecteurs, raccords, vis, chemins de câbles, autres matériaux auxiliaires. Les étapes de la construction: — Livraison, débarquement — Fixation de la structure d’exploitation sur un toit incliné — Installation et mise en œuvre du système — Connexion, programmation et réglage de l’onduleur — Contrôle et enregistrement de la protection tactile — Installation de démonstration, remise/réception — Responsabilité garantie Autres prestations effectuées par le contractant: Débarquement, levé, devis, calcul du retour — Documentation technique — Conception électrique — Dessin à ligne unique — Administration de l’alimentation électrique (French)
    10 February 2022
    0 references
    Rózsaszentmárton, Heves
    0 references

    Identifiers

    GINOP-4.1.4-19-2019-00205
    0 references