Purchase of equipment for Natura Plan Bt. (Q3919768): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed an Item: add summary)
(‎Changed an Item: Adding English translations)
Property / summary
 
If the level of groundwater at the time of earthwork or foundation is higher than the level of the lower plane of the bases, we must take care of dewatering. The working pit is dewatered by vacuum pumps. The investment generates additional production and service added value, because it makes our company suitable for effective work even in the case of construction work requiring special expertise, environmental remediation, pile sweeping, even anti-docking and waterproofing work, dehumidification of building, mine deepening, sinking, underground work or the construction of an outdoor swimming pool. The Doka flexible slab system adapts easily to almost every floor plan, can be applied quickly and easily up to 30 cm slab thickness, the joints are made within the system — so it is easy to fit the walls and supports, the support height can be up to 5.50 m and the formwork shell can be selected as you like. Among the advantages of the purchased formwork system, the most important thing is that the formwork and scaffolding work is a mechanic, so it is more productive and its quality reaches the level of the factory production. There is no loss of material in its assembly, the formwork can be used up to 100 times, they have high size accuracy. It is important that surfaces that do not require plastering can be made, allowing additional added value. (English)
Property / summary: If the level of groundwater at the time of earthwork or foundation is higher than the level of the lower plane of the bases, we must take care of dewatering. The working pit is dewatered by vacuum pumps. The investment generates additional production and service added value, because it makes our company suitable for effective work even in the case of construction work requiring special expertise, environmental remediation, pile sweeping, even anti-docking and waterproofing work, dehumidification of building, mine deepening, sinking, underground work or the construction of an outdoor swimming pool. The Doka flexible slab system adapts easily to almost every floor plan, can be applied quickly and easily up to 30 cm slab thickness, the joints are made within the system — so it is easy to fit the walls and supports, the support height can be up to 5.50 m and the formwork shell can be selected as you like. Among the advantages of the purchased formwork system, the most important thing is that the formwork and scaffolding work is a mechanic, so it is more productive and its quality reaches the level of the factory production. There is no loss of material in its assembly, the formwork can be used up to 100 times, they have high size accuracy. It is important that surfaces that do not require plastering can be made, allowing additional added value. (English) / rank
 
Normal rank
Property / summary: If the level of groundwater at the time of earthwork or foundation is higher than the level of the lower plane of the bases, we must take care of dewatering. The working pit is dewatered by vacuum pumps. The investment generates additional production and service added value, because it makes our company suitable for effective work even in the case of construction work requiring special expertise, environmental remediation, pile sweeping, even anti-docking and waterproofing work, dehumidification of building, mine deepening, sinking, underground work or the construction of an outdoor swimming pool. The Doka flexible slab system adapts easily to almost every floor plan, can be applied quickly and easily up to 30 cm slab thickness, the joints are made within the system — so it is easy to fit the walls and supports, the support height can be up to 5.50 m and the formwork shell can be selected as you like. Among the advantages of the purchased formwork system, the most important thing is that the formwork and scaffolding work is a mechanic, so it is more productive and its quality reaches the level of the factory production. There is no loss of material in its assembly, the formwork can be used up to 100 times, they have high size accuracy. It is important that surfaces that do not require plastering can be made, allowing additional added value. (English) / qualifier
 
point in time: 8 February 2022
Timestamp+2022-02-08T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 17:15, 8 February 2022

Project Q3919768 in Hungary
Language Label Description Also known as
English
Purchase of equipment for Natura Plan Bt.
Project Q3919768 in Hungary

    Statements

    0 references
    20,200,000 forint
    0 references
    55,857.24 Euro
    0.00276521 Euro
    3 December 2021
    0 references
    111,554.014 Euro
    0.0027336256 Euro
    14 December 2021
    0 references
    40,808,080.808 forint
    0 references
    49.5 percent
    0 references
    14 March 2016
    0 references
    14 June 2016
    0 references
    NATURA-PLAN Mérnökiroda Kereskedelmi és Szolgáltató Betéti Társaság
    0 references
    0 references

    48°0'21.71"N, 19°47'5.64"E
    0 references
    Ha a földmunka, illetve az alapozás készítésének időpontjában a talajvíz szintje magasabb az alapok alsó síkjának szintjénél, gondoskodnunk kell a víztelenítésről. A munkagödör víztelenítése vákuumpszivattyúkkal történik meg. A beruházással további termelési-szolgáltatási hozzáadott- érték növekedés jön létre, mert speciális szakértelmet igénylő építési munkánál, környezetvédelmi kármentesítésnél, cölöpverésnél, akár dohosság elleni és vízszigetelési munka, épület páramentesítése, aknamélyítés, -süllyesztés, föld felszíne alatti munka illetve a szabadtéri úszómedence építése esetén is alkalmassá teszi cégünket az eredményes munkavállalásra. A Doka rugalmas födémrendszer egyszerűen alkalmazkodik szinte minden alaprajzhoz, 30 cm födémvastagságig gyorsan és egyszerűen alkalmazható, az illesztések a rendszeren belül történnek – így egyszerűen illeszthető a falakhoz és támaszokhoz, az alátámasztási magasság 5,50 m-ig terjedhet és a zsaluhéj kiválasztható tetszés szerint. A beszerzett zsaluzati rendszer előnyei között a legfontosabb, hogy a zsaluzási és állványozási munka szerelő jellegű, így termelékenyebb és színvonala eléri az üzemi gyártás színvonalát. Szerelésénél nincs anyagveszteség, a zsaluzatok akár 100-szor is felhasználhatóak, nagy méretpontosságúak. Fontos, hogy vakolást nem igénylő felületek készíthetőek, amely további hozzáadott-értéknövekedést tesz lehetővé. (Hungarian)
    0 references
    If the level of groundwater at the time of earthwork or foundation is higher than the level of the lower plane of the bases, we must take care of dewatering. The working pit is dewatered by vacuum pumps. The investment generates additional production and service added value, because it makes our company suitable for effective work even in the case of construction work requiring special expertise, environmental remediation, pile sweeping, even anti-docking and waterproofing work, dehumidification of building, mine deepening, sinking, underground work or the construction of an outdoor swimming pool. The Doka flexible slab system adapts easily to almost every floor plan, can be applied quickly and easily up to 30 cm slab thickness, the joints are made within the system — so it is easy to fit the walls and supports, the support height can be up to 5.50 m and the formwork shell can be selected as you like. Among the advantages of the purchased formwork system, the most important thing is that the formwork and scaffolding work is a mechanic, so it is more productive and its quality reaches the level of the factory production. There is no loss of material in its assembly, the formwork can be used up to 100 times, they have high size accuracy. It is important that surfaces that do not require plastering can be made, allowing additional added value. (English)
    8 February 2022
    0 references
    Bátonyterenye, Nógrád
    0 references

    Identifiers

    GINOP-1.2.2-15-2015-01897
    0 references