(Created claim: summary (P836): The project addresses the construction of a gravitational sewerage system of 4 393.52 m in the central part of the municipality of Řepště. The sewerage system will be driven by local communications, along the II/477 road, the free terrain and the sewerage system to the WWTP, along the Datyňová river. There are around 139 family homes, primary schools, nurseries, municipal offices, TJ and centres. The construction of the wastewater treatment plan...) |
(Removed claim: co-financing rate (P837): 63.7500000035821 percent) |
||||||
Property / co-financing rate | |||||||
| |||||||
Property / co-financing rate: 63.7500000035821 percent / rank | |||||||
Revision as of 17:43, 19 March 2020
Project in Czech Republic financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Sewage system and WWTP, Stage 1 |
Project in Czech Republic financed by DG Regio |
Statements
31,144,879.45 Czech koruna
0 references
48,854,712.86 Czech koruna
0 references
3 September 2018
0 references
31 December 2020
0 references
Obec Řepiště
0 references
73932
0 references
Projekt řeší vybudování gravitační splaškové kanalizace v délce 4393.52 m v centrální části obce Řepiště. Kanalizace bude vedena místními komunikacemi, podél silnice II/477, volným terénem a před napojením kanalizace na ČOV je kanalizace vedena podél řeky Datyňka. Jedná se o odkanalizování cca 139 rodinných domů, základní školy, školky, obecního úřadu, budovy TJ Řepiště a společenského centra. Výstavba ČOV bude realizována na parcele číslo: 1531/3. Bude vybudováno 713.37 m gravitačních přípojek. (Czech)
0 references
The project addresses the construction of a gravitational sewerage system of 4 393.52 m in the central part of the municipality of Řepště. The sewerage system will be driven by local communications, along the II/477 road, the free terrain and the sewerage system to the WWTP, along the Datyňová river. There are around 139 family homes, primary schools, nurseries, municipal offices, TJ and centres. The construction of the wastewater treatment plant will be carried out on a plot of land: 1531/3. 713.37 m of gravitational connections will be built. (English)
0 references
Identifiers
CZ.05.1.30/0.0/0.0/16_042/0004724
0 references