Construction of the storm water drainage network in the municipality of Myślisbórz (Q137844): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed an Item)
(‎Created claim: summary (P836): The project shall comprise the following tasks and expenses: Task No 1: Preparatory work — including: development of a feasibility study and a functioning utility programme. Task 2. Construction of section No 1 of the storm water collection system in Myślisborzu — covering the earth works and the sewerage system on the site: Dz. 32, 33/5, 35, 110, 112, 116, 136, 144, 146, Myślisbórz 2. Description: The design and construction of rainwater draina...)
Property / summary
 
The project shall comprise the following tasks and expenses: Task No 1: Preparatory work — including: development of a feasibility study and a functioning utility programme. Task 2. Construction of section No 1 of the storm water collection system in Myślisborzu — covering the earth works and the sewerage system on the site: Dz. 32, 33/5, 35, 110, 112, 116, 136, 144, 146, Myślisbórz 2. Description: The design and construction of rainwater drainage from storm water into the river are no 32. The storm water collection network will be carried out on the premises of road parcels No 146, 144, 136, 116, 112, 110, 35, at the roadside and/or the road and by municipal parcel No 33/5 and will be transferred to the river on the river. 32 in Mlisbórz. The project is intended to be implemented in the “Design and Explosion” system. Task 3. Construction of section No 2 of the storm water sewage system in Myślisborzu — consisting of: OJ No 72, 145, 101, 102/1, 102/2, 81/1, 81/4, 746, 748,745,760/15. Description: Design and construction of rainwater drainage with drainage ditches on plot No 101. The storm water collection network will be carried out in road parcels No 81/1, 81/4, 72, 746, 745, 747, 748, 760/15, 145, 102/1 and 102/2. 101 in the town of Myślibórz. The project is planned to be carried out in a ‘projection and demolition’ system. For each of the sections, the following steps are planned: (a) drawing up a comprehensive project documentation based on the enclosed concept of the storm water system b) the sanitary sector — rainwater drainage, c) the road sector — restoring the pavement, renovation of the road pass, etc. d) obtaining a construction permit, (d) building a storm water sewerage on the basis of documentation prepared and permits (f) obtaining collection for the use of storm water drainage from 11.01.2016 to 31.12.2016. (English)
Property / summary: The project shall comprise the following tasks and expenses: Task No 1: Preparatory work — including: development of a feasibility study and a functioning utility programme. Task 2. Construction of section No 1 of the storm water collection system in Myślisborzu — covering the earth works and the sewerage system on the site: Dz. 32, 33/5, 35, 110, 112, 116, 136, 144, 146, Myślisbórz 2. Description: The design and construction of rainwater drainage from storm water into the river are no 32. The storm water collection network will be carried out on the premises of road parcels No 146, 144, 136, 116, 112, 110, 35, at the roadside and/or the road and by municipal parcel No 33/5 and will be transferred to the river on the river. 32 in Mlisbórz. The project is intended to be implemented in the “Design and Explosion” system. Task 3. Construction of section No 2 of the storm water sewage system in Myślisborzu — consisting of: OJ No 72, 145, 101, 102/1, 102/2, 81/1, 81/4, 746, 748,745,760/15. Description: Design and construction of rainwater drainage with drainage ditches on plot No 101. The storm water collection network will be carried out in road parcels No 81/1, 81/4, 72, 746, 745, 747, 748, 760/15, 145, 102/1 and 102/2. 101 in the town of Myślibórz. The project is planned to be carried out in a ‘projection and demolition’ system. For each of the sections, the following steps are planned: (a) drawing up a comprehensive project documentation based on the enclosed concept of the storm water system b) the sanitary sector — rainwater drainage, c) the road sector — restoring the pavement, renovation of the road pass, etc. d) obtaining a construction permit, (d) building a storm water sewerage on the basis of documentation prepared and permits (f) obtaining collection for the use of storm water drainage from 11.01.2016 to 31.12.2016. (English) / rank
 
Normal rank

Revision as of 10:14, 11 March 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of the storm water drainage network in the municipality of Myślisbórz
Project in Poland financed by DG Regio

    Statements

    0 references
    2,116,217.28 zloty
    0 references
    507,892.14719999995 Euro
    13 January 2020
    0 references
    2,489,667.41 zloty
    0 references
    597,520.1784 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    11 January 2016
    0 references
    30 November 2019
    0 references
    GMINA MYŚLIBÓRZ
    0 references
    Projekt obejmuje następujące zadania i wydatki: Zadanie nr 1: Prace przygotowawcze - obejmujące: opracowanie Studium wykonalności oraz Programu Funkcjonalno-Użytkowego. Zadanie nr 2. Budowa odcinka nr 1 kanalizacji deszczowej w Myśliborzu – obejmująca roboty ziemne i sieć kanalizacyjną na terenie: dz. nr : 32, 33/5, 35, 110, 112, 116, 136, 144, 146 obręb Myślibórz 2. Opis: Zaprojektowanie i wykonanie kanalizacji deszczowej odprowadzenia wód opadowych do rzeki Myśla dz. nr 32. Sieć kanalizacji deszczowej prowadzona będzie na terenie działek drogowych nr 146, 144, 136, 116, 112, 110, 35, poboczem lub jezdnią i przez działkę gminną nr 33/5 z odprowadzeniem do rzeki Myśla dz. 32 w miejscowości Myślibórz. Projekt przewidziany jest do realizacji w systemie „zaprojektuj i wybuduj”. Zadanie nr 3. Budowa odcinka nr 2 kanalizacji deszczowej w Myśliborzu – obejmująca : dz. nr 72, 145, 101, 102/1, 102/2, 81/1, 81/4, 746, 748,745,760/15 obręb 3 Myślibórz. Opis: Zaprojektowanie i wykonanie kanalizacji deszczowej odprowadzenia wód opadowych do rowu melioracyjnego na działce nr 101. Sieć kanalizacji deszczowej prowadzona będzie na terenie działek drogowych nr 81/1, 81/4, 72, 746, 745, 747, 748, 760/15, 145, 102/1, 102/2 z odprowadzeniem do rowu dz. 101 w Miejscowości Myślibórz. Projekt planowany jest do realizacji w systemie „zaprojektuj i wybuduj”. Dla każdego z odcinków planowane są następujące etapy: a) sporządzenie kompleksowej dokumentacji projektowej na podstawie załączonej koncepcji przebiegu trasy kanalizacji deszczowej b) branża sanitarna – kanalizacja deszczowa, c) branża drogowa – odtworzenia nawierzchni, remont przepustu drogowego itp. d) uzyskanie pozwolenia na budowę e) wybudowanie kanalizacji deszczowej na podstawie sporządzonej dokumentacji i uzyskanych pozwoleniach f) uzyskanie odbioru do użytkowania kanalizacji deszczowej Realizacja projektu będzie od 11.01.2016 r. do 31.12.2016 r. (Polish)
    0 references
    The project shall comprise the following tasks and expenses: Task No 1: Preparatory work — including: development of a feasibility study and a functioning utility programme. Task 2. Construction of section No 1 of the storm water collection system in Myślisborzu — covering the earth works and the sewerage system on the site: Dz. 32, 33/5, 35, 110, 112, 116, 136, 144, 146, Myślisbórz 2. Description: The design and construction of rainwater drainage from storm water into the river are no 32. The storm water collection network will be carried out on the premises of road parcels No 146, 144, 136, 116, 112, 110, 35, at the roadside and/or the road and by municipal parcel No 33/5 and will be transferred to the river on the river. 32 in Mlisbórz. The project is intended to be implemented in the “Design and Explosion” system. Task 3. Construction of section No 2 of the storm water sewage system in Myślisborzu — consisting of: OJ No 72, 145, 101, 102/1, 102/2, 81/1, 81/4, 746, 748,745,760/15. Description: Design and construction of rainwater drainage with drainage ditches on plot No 101. The storm water collection network will be carried out in road parcels No 81/1, 81/4, 72, 746, 745, 747, 748, 760/15, 145, 102/1 and 102/2. 101 in the town of Myślibórz. The project is planned to be carried out in a ‘projection and demolition’ system. For each of the sections, the following steps are planned: (a) drawing up a comprehensive project documentation based on the enclosed concept of the storm water system b) the sanitary sector — rainwater drainage, c) the road sector — restoring the pavement, renovation of the road pass, etc. d) obtaining a construction permit, (d) building a storm water sewerage on the basis of documentation prepared and permits (f) obtaining collection for the use of storm water drainage from 11.01.2016 to 31.12.2016. (English)
    0 references

    Identifiers

    RPZP.03.03.00-32-A011/16
    0 references