Requalification of the Largo de São Marcos das Gaeiras (Q2878189): Difference between revisions
Jump to navigation
Jump to search
(Changed an Item: modifying budgets in portugal one item from slovenia) |
(Changed label, description and/or aliases in fr, and other parts: Adding French translations) |
||||||||||||||
label / fr | label / fr | ||||||||||||||
Requalification de Largo de São Marcos das Gaeiras | |||||||||||||||
Property / summary | |||||||||||||||
Le premier amendement proposé par le promoteur est de nature temporelle. L’objectif est de modifier la date de fin de l’opération du 31.5.2018 au 31.12.2018, à la suite de la prolongation du délai d’exécution du contrat jusqu’au 31.10.2018. La date de début est maintenue au 24.7.2015. (French) | |||||||||||||||
Property / summary: Le premier amendement proposé par le promoteur est de nature temporelle. L’objectif est de modifier la date de fin de l’opération du 31.5.2018 au 31.12.2018, à la suite de la prolongation du délai d’exécution du contrat jusqu’au 31.10.2018. La date de début est maintenue au 24.7.2015. (French) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: Le premier amendement proposé par le promoteur est de nature temporelle. L’objectif est de modifier la date de fin de l’opération du 31.5.2018 au 31.12.2018, à la suite de la prolongation du délai d’exécution du contrat jusqu’au 31.10.2018. La date de début est maintenue au 24.7.2015. (French) / qualifier | |||||||||||||||
point in time: 4 December 2021
|
Revision as of 22:56, 4 December 2021
Project Q2878189 in Portugal
Language | Label | Description | Also known as |
---|---|---|---|
English | Requalification of the Largo de São Marcos das Gaeiras |
Project Q2878189 in Portugal |
Statements
1,140,972.0 Euro
0 references
1,342,320.0 Euro
0 references
85.0 percent
0 references
24 July 2015
0 references
30 July 2019
0 references
MUNICÍPIO DE ÓBIDOS
0 references
A primeira alteração proposta pelo promotor é de natureza temporal. Pretende-se alterar a data de fim da operação, de 31.05.2018, para 31.12.2018, na sequência da prorrogação do prazo de execução da empreitada até 31.10.2018. A data de início mantém-se em 24.07.2015. (Portuguese)
0 references
The first amendment proposed by the promoter is of a temporal nature. It is intended to change the end date of the operation from 31.05.2018 to 31.12.2018 following the lengthening of the deadline for the execution of the contract to 31.10.2018. The start date remains 24.07.2015. (English)
7 July 2021
0 references
Le premier amendement proposé par le promoteur est de nature temporelle. L’objectif est de modifier la date de fin de l’opération du 31.5.2018 au 31.12.2018, à la suite de la prolongation du délai d’exécution du contrat jusqu’au 31.10.2018. La date de début est maintenue au 24.7.2015. (French)
4 December 2021
0 references
Óbidos, Gaeiras
0 references
Identifiers
CENTRO-09-2316-FEDER-000006
0 references