Construction of Ostrołęka – Stanisławów line with the construction of Wyszków station and extension of the station in this line (Q86104): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Removed claim: contained in NUTS (P1845): Warszawski wschodni (Q2577124), Removing duplicate contained in NUTS)
(‎Removed claim: contained in NUTS (P1845): Ostrołęcki (Q2577175), Removing duplicate contained in NUTS)
Property / contained in NUTS
 
Property / contained in NUTS: Ostrołęcki / rank
Normal rank
 

Revision as of 10:16, 3 December 2021

Project Q86104 in Poland
Language Label Description Also known as
English
Construction of Ostrołęka – Stanisławów line with the construction of Wyszków station and extension of the station in this line
Project Q86104 in Poland

    Statements

    0 references
    0 references
    0 references
    0 references
    39,870,000.0 zloty
    0 references
    9,568,800.0 Euro
    13 January 2020
    0 references
    134,661,763.77 zloty
    0 references
    32,318,823.3 Euro
    13 January 2020
    0 references
    29.61 percent
    0 references
    1 January 2014
    0 references
    31 December 2023
    0 references
    POLSKIE SIECI ELEKTROENERGETYCZNE S.A
    0 references

    52°9'25.2"N, 21°37'36.5"E
    0 references

    52°56'55.7"N, 21°45'31.3"E
    0 references

    53°4'40.8"N, 21°34'29.6"E
    0 references

    52°47'26.2"N, 19°51'23.0"E
    0 references

    52°29'13.9"N, 21°33'49.7"E
    0 references

    52°36'16.6"N, 21°28'5.9"E
    0 references
    Przedmiotem projektu jest budowa dwutorowej linii elektroenergetycznej wysokiego napięcia 400kV o długości 110 km (220 km sieci prądowej) na odcinku Ostrołęka - Stanisławów. W tym odcinku zostanie wybudowana jedna stacja 400 (220)/110 kV Wyszków i rozbudowane dwie stacje: 400/220/110 kV Ostrołęka oraz 400 kV Stanisławów. Celem Projektu jest poprawa pewności i bezpieczeństwa pracy Krajowego Systemu Elektroenergetycznego w północno-wschodniej części Polski, poprawa pewności zasilania aglomeracji warszawskiej oraz sieci 110 kV Pośrednim celem Projektu jest: a) stworzenie warunków do zwiększenia możliwości wymiany energii elektrycznej z litewskim systemem elektroenergetycznym przy zapewnieniu bezpiecznej pracy tego połączenia b) stworzenie warunków do wyprowadzenia mocy z konwencjonalnych i odnawialnych źródeł energii (Polish)
    0 references
    The subject of the project is the construction of a two-track high voltage power line of 400 kV with a length of 110 km (220 km of electricity network) on the Ostrołęka-Stanisławów section. In this section, one station 400 (220)/110 kV Wyszków will be built and two stations will be expanded: 400/220/110 kV Ostrołęka and 400 kV Stanisławów. The aim of the project is to improve the safety and safety of the National Power System in the north-eastern part of Poland, to improve the power supply of the Warsaw agglomeration and the 110 kV network The indirect objective of the project is: a) creating the conditions for increasing the possibility of electricity exchanges with the Lithuanian electricity system while ensuring the safe operation of this connection (b) creating the conditions for power decommissioning from conventional and renewable energy sources (English)
    14 October 2020
    0 references
    L’objet du projet est la construction d’une ligne électrique à haute tension à double voie de 400 kV d’une longueur de 110 km (220 km du réseau actuel) sur le tronçon Ostrołęka — Stanisławów. Dans cette section, une station de 400 (220)/110 kV de Wyszków sera construite et deux stations seront agrandies: 400/220/110 kV Ostrołęka et 400 kV Stanisławów. L’objectif du projet est d’améliorer la fiabilité et la sécurité de l’exploitation du réseau électrique national dans la partie nord-est de la Pologne, d’améliorer la fiabilité de l’alimentation électrique de l’agglomération de Varsovie et du réseau de 110 kV. L’objectif indirect du projet est: a) créer les conditions permettant d’accroître la possibilité d’échanger de l’électricité avec le réseau électrique lituanien tout en assurant le fonctionnement sûr de cette connexion b) créer les conditions d’extraction d’électricité à partir de sources d’énergie conventionnelles et renouvelables (French)
    30 November 2021
    0 references

    Identifiers

    POIS.07.01.00-00-0002/18
    0 references