RATIONALISATION OF ENERGY CONSUMPTION IN THE MUNICIPALITY OF GRABICA BY MEANS OF THERMO-MODERNISATION OF PUBLIC BUILDINGS IN THE OLD AND KAMEVENTS (Q101924): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Created claim: summary (P836): The investment in question consists of the preparation of a project (preparatory work), the completion of the comprehensive thermal modernisation works in two public buildings, i.e. the building of a library subsidiary in Krzewowo Old and the building of a library of branches in Kamina, and the provision of investment supervision and promotion activities. The scope of the project includes: — the development of a project documentation for the lib...)
(‎Changed claim: summary (P836): The investment consists in preparation of the project (preparatory works), carrying out comprehensive thermomodernization works in two public buildings, i.e. the building of the Library Branch in Krzepczów Stary and the building of the Library Branch in Kamocin, as well as the provision of investor supervision services and promotional activities. The material scope of the project includes: - development of project documentation for the library b...)
Property / summaryProperty / summary
The investment in question consists of the preparation of a project (preparatory work), the completion of the comprehensive thermal modernisation works in two public buildings, i.e. the building of a library subsidiary in Krzewowo Old and the building of a library of branches in Kamina, and the provision of investment supervision and promotion activities. The scope of the project includes: — the development of a project documentation for the library building in Krimicia Old, — the development of an energy audit for the library building in Khamicie Old, — the development of an energy audit for the library building in Kammolicie, — the development of a project feasibility study for the building of the building in Kammolicie, — the replacement of the building’s floor inside the building in Kammolicie, — the replacement of the building’s floor inside the building in Kammolicie, — the replacement of the building’s heating system in the building in Kammolicie, — modernisation of the wall of the building in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie, — modernisation of the heating system in the building in Kammolicie Energy audit carried out in the second quarter of 2015, project documentation was started in the fourth quarter of 2015, completed in the 4th quarter of the year. 2015. In the first quarter of 2016 the applicant commissioned a feasibility study. The planned date of the invitation to tender for the works and the selection pursuant to Article 4(8) of the Public Procurement Act of investment and promotion contractors is planned for the fourth quarter of 2016. The tangible and financial end is the second quarter of 2017. (English)
The investment consists in preparation of the project (preparatory works), carrying out comprehensive thermomodernization works in two public buildings, i.e. the building of the Library Branch in Krzepczów Stary and the building of the Library Branch in Kamocin, as well as the provision of investor supervision services and promotional activities. The material scope of the project includes: - development of project documentation for the library building in Krzepczów Stary, - development of project documentation for the library building in Kamocin, - development of the energy audit for the library building in Krzepczów Stary, - development of the energy audit for the library building in Kamocin, - development of the study feasibility of the project, - insulation of the top floor of the building in Krzepczów Stary, - insulation of the top floor of the building in Kamocin, - replacement of window woodwork in the building in Krzepczów Stary, - replacement of window woodwork in the building in Kamocin, - replacement of door woodwork in the building in Krzepczów Stary , - floor insulation on the ground in a building in Krzepczów Stary, floor insulation on the ground in a building in Kamocin, insulation of the external wall in a building in Krzepczów Stary, insulation of the external wall in a building in Kamocin, - modernization of the heating system in the building in Krzepczów Stary, - modernize heating system in a building in Kamocin, - modernization of the domestic hot water system in the building in Krzepczów Stary, - investor's supervision, - promotion of the project. In the second quarter of 2015, an energy audit was carried out, in the fourth quarter of 2015. preparation of project documentation began, completed in Q4 2015. In the first quarter of 2016, the Applicant commissioned the development of a feasibility study. Planned date of announcement of the tender for construction works and selection pursuant to art. 4 section 8 of the PPL Act, investors' supervision and promotion contractors are planned for the fourth quarter of 2016. Material and financial completion is the second quarter of 2017. (English)

Revision as of 13:22, 10 March 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
RATIONALISATION OF ENERGY CONSUMPTION IN THE MUNICIPALITY OF GRABICA BY MEANS OF THERMO-MODERNISATION OF PUBLIC BUILDINGS IN THE OLD AND KAMEVENTS
Project in Poland financed by DG Regio

    Statements

    0 references
    648,127.84 zloty
    0 references
    155,550.68159999998 Euro
    13 January 2020
    0 references
    951,867.98 zloty
    0 references
    228,448.31519999998 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    29 June 2015
    0 references
    30 June 2017
    0 references
    GMINA GRABICA
    0 references

    51°28'41.9"N, 19°32'4.9"E
    0 references
    Przedmiotowa inwestycja polega na przygotowaniu projektu (prace przygotowawcze), przeprowadzeniu kompleksowych prac termomodernizacyjnych w dwóch budynkach użyteczności publicznej tj. budynku Filii Bibliotecznej w Krzepczowie Starym oraz budynku Filii Bibliotecznej w Kamocinie oraz świadczeniu usługi nadzoru inwestorskiego i działań promocyjnych. Zakres rzeczowy projektu obejmuje: - opracowanie dokumentacji projektowej dla budynku biblioteki w Krzepczowie Starym, - opracowanie dokumentacji projektowej dla budynku biblioteki w Kamocinie, - opracowanie audytu energetycznego dla budynku biblioteki w Krzepczowie Starym, - opracowanie audytu energetycznego dla budynku biblioteki w Kamocinie, - opracowanie studium wykonalności projektu, - ocieplenie stropu ostatniej kondygnacji budynku w Krzepczowie Starym, - ocieplenie stropu ostatniej kondygnacji budynku w Kamocinie, - wymiana stolarki okiennej w budynku w Krzepczowie Starym, - wymiana stolarki okiennej w budynku w Kamocinie, - wymiana stolarki drzwiowej w budynku w Krzepczowie Starym, - ocieplenie podłogi na gruncie w budynku w Krzepczowie Starym, ocieplenie podłogi na gruncie w budynku w Kamocinie, ocieplenie ściany zew. w budynku w Krzepczowie Starym, ocieplenie ściany zew. w budynku w Kamocinie, - modernizacja systemu grzewczego w budynku w Krzepczowie Starym, - modernizacja systemu grzewczego w budynku w Kamocinie, - modernizacja systemu c.w.u. w budynku w Krzepczowie Starym, - nadzór inwestorski,– promocja projektu. W II kwartale 2015 roku wykonano audytu energetyczny, w IV kwartale 2015r. rozpoczęto opracowanie dokumentacji projektowej, zakończono w IV kw. 2015. W I kwartale 2016 roku Wnioskodawca zlecił opracowanie studium wykonalności. Planowany termin ogłoszenia przetargu na roboty budowlane oraz wybranie w trybie art. 4 ust 8 ustawy Pzp wykonawców nadzoru inwestorskiego oraz promocji planuje się na IV kwartał 2016 roku. Zakończenie rzeczowe i finansowe to II kwartał 2017r. (Polish)
    0 references
    The investment consists in preparation of the project (preparatory works), carrying out comprehensive thermomodernization works in two public buildings, i.e. the building of the Library Branch in Krzepczów Stary and the building of the Library Branch in Kamocin, as well as the provision of investor supervision services and promotional activities. The material scope of the project includes: - development of project documentation for the library building in Krzepczów Stary, - development of project documentation for the library building in Kamocin, - development of the energy audit for the library building in Krzepczów Stary, - development of the energy audit for the library building in Kamocin, - development of the study feasibility of the project, - insulation of the top floor of the building in Krzepczów Stary, - insulation of the top floor of the building in Kamocin, - replacement of window woodwork in the building in Krzepczów Stary, - replacement of window woodwork in the building in Kamocin, - replacement of door woodwork in the building in Krzepczów Stary , - floor insulation on the ground in a building in Krzepczów Stary, floor insulation on the ground in a building in Kamocin, insulation of the external wall in a building in Krzepczów Stary, insulation of the external wall in a building in Kamocin, - modernization of the heating system in the building in Krzepczów Stary, - modernize heating system in a building in Kamocin, - modernization of the domestic hot water system in the building in Krzepczów Stary, - investor's supervision, - promotion of the project. In the second quarter of 2015, an energy audit was carried out, in the fourth quarter of 2015. preparation of project documentation began, completed in Q4 2015. In the first quarter of 2016, the Applicant commissioned the development of a feasibility study. Planned date of announcement of the tender for construction works and selection pursuant to art. 4 section 8 of the PPL Act, investors' supervision and promotion contractors are planned for the fourth quarter of 2016. Material and financial completion is the second quarter of 2017. (English)
    0 references

    Identifiers

    RPLD.04.02.02-10-0023/16
    0 references