(‎Created claim: summary (P836): The main objective of the project is to reduce the demand for heat and to reduce the operating costs of buildings No 5 and No 2 at ul. Slovak 85 in Przemyśl. The objective will be achieved through implementation: — in Building 5: the warming of external walls; the warming of the core walls of Part A; the warming of the floors on the ground of part A of the low ground floor; the warming of the part A under the low ground floor (basement); replace...)
Property / summary
 
The main objective of the project is to reduce the demand for heat and to reduce the operating costs of buildings No 5 and No 2 at ul. Slovak 85 in Przemyśl. The objective will be achieved through implementation: — in Building 5: the warming of external walls; the warming of the core walls of Part A; the warming of the floors on the ground of part A of the low ground floor; the warming of the part A under the low ground floor (basement); replacement of window frames — high and low ground floor fasteners; replacement of carpenter — ground floor, section A, modernisation of the central heating system of high and low ground floor space heating and modernisation of domestic hot water — in Building No 2: the wall warming of fundamental walls (on the ground), the replacement of doors, insulation of floors on the ground floor, floor insulation of façade floors, insulation of outdoor walls, insulation of terrace (flat roof), insulation of ceilings for non-heated attainments, modernisation of the hot water service and modernisation of the central heating system, replacement of door joinery in both buildings. As part of the project, energy audits, technical documentation have been carried out. The investor’s supervision and post-audit audit will be carried out where the thermal insulation test of the building insulation layers will be tested for the thermal insulation of the building as well as the air leak testing of the building. In view of the lack of consent from the Voivodeship Office for the Preservation of Monuments on the insulation of the façade walls of the building using warming materials (polystyrene, wool and tp), and the possibility of renewing, renovating the façade of the outer wall, the warming plaster is designed to reach the U-value max. [W/m² * K]. (English)
Property / summary: The main objective of the project is to reduce the demand for heat and to reduce the operating costs of buildings No 5 and No 2 at ul. Slovak 85 in Przemyśl. The objective will be achieved through implementation: — in Building 5: the warming of external walls; the warming of the core walls of Part A; the warming of the floors on the ground of part A of the low ground floor; the warming of the part A under the low ground floor (basement); replacement of window frames — high and low ground floor fasteners; replacement of carpenter — ground floor, section A, modernisation of the central heating system of high and low ground floor space heating and modernisation of domestic hot water — in Building No 2: the wall warming of fundamental walls (on the ground), the replacement of doors, insulation of floors on the ground floor, floor insulation of façade floors, insulation of outdoor walls, insulation of terrace (flat roof), insulation of ceilings for non-heated attainments, modernisation of the hot water service and modernisation of the central heating system, replacement of door joinery in both buildings. As part of the project, energy audits, technical documentation have been carried out. The investor’s supervision and post-audit audit will be carried out where the thermal insulation test of the building insulation layers will be tested for the thermal insulation of the building as well as the air leak testing of the building. In view of the lack of consent from the Voivodeship Office for the Preservation of Monuments on the insulation of the façade walls of the building using warming materials (polystyrene, wool and tp), and the possibility of renewing, renovating the façade of the outer wall, the warming plaster is designed to reach the U-value max. [W/m² * K]. (English) / rank
 
Normal rank

Revision as of 08:50, 10 March 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Thermo-modernisation of the buildings of the nursing/Hospice Department in Przemyśl
Project in Poland financed by DG Regio

    Statements

    0 references
    2,944,043.3 zloty
    0 references
    706,570.3919999999 Euro
    13 January 2020
    0 references
    3,651,599.73 zloty
    0 references
    876,383.9352 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    21 September 2018
    0 references
    31 January 2020
    0 references
    CARITAS ARCHIDIECEZJI PRZEMYSKIEJ
    0 references
    Cel główny projektu to zmniejszenie zapotrzebowania na energie cieplną oraz obniżenie kosztów eksploatacyjnych budynków nr 5 oraz nr 2 Zakładu Opiekuńczo-Leczniczego/Hospicjum przy ul. Słowackiego 85 w Przemyślu. Cel zostanie osiągnięty poprzez realizację:- w budynku 5: ocieplenia ścian zewnętrznych; ocieplenia ścian fundamentowych części A; ocieplenia podłóg na gruncie część A niskiego parteru; ocieplenia stropów część A pod niskim parterem (piwnicą); wymianę stolarki okiennej- wysokiego i niskiego parteru cz.A; wymianę stolarki drzwiowej- wysokiego parteru cz.A, modernizację instalacji centralnego ogrzewania wysokiego i niskiego parteru część A oraz modernizację ciepłej wody.- w budynku nr 2: ocieplenia ścian fundamentowych (przy gruncie), wymianę stolarki drzwiowej, docieplenie podłogi na gruncie-niskiego parteru, docieplenie ścian zewnętrznych elewacyjnych, docieplenie tarasu(dach płaski), docieplenie stropów pod nieogrzewanym poddaszem, modernizację instalacji c.w.u oraz modernizację instalacji centralnego ogrzewania, wymiana stolarki drzwiowej.- wymianę opraw świetlówek na oprawy led'owe w obu budynkach. W ramach realizacji projektu wykonano audyty energetyczne, dokumentację techniczną. Przeprowadzony zostanie nadzór inwestorski oraz audyt powykonawczy, w ramach którego przeprowadzone zostanie termowizyjne badanie ciągłości warstw izolacji termicznej budynku oraz powietrzne badanie szczelności budynku. Z uwagi na brak zgody Wojewódzkiego Urzędu Konserwacji Zabytków na ocieplenie ścian elewacyjnych budynku z użyciem materiałów ocieplających (styropianu, wełny i tp), oraz możliwością odnowienia, renowacji elewacji ścian zewnętrznych tynkiem ocieplającym zaprojektowano grubość tynku ocieplającego zapewniając uzyskanię max wartości współczynnika przenikania U [W/m2*K]. (Polish)
    0 references
    The main objective of the project is to reduce the demand for heat and to reduce the operating costs of buildings No 5 and No 2 at ul. Slovak 85 in Przemyśl. The objective will be achieved through implementation: — in Building 5: the warming of external walls; the warming of the core walls of Part A; the warming of the floors on the ground of part A of the low ground floor; the warming of the part A under the low ground floor (basement); replacement of window frames — high and low ground floor fasteners; replacement of carpenter — ground floor, section A, modernisation of the central heating system of high and low ground floor space heating and modernisation of domestic hot water — in Building No 2: the wall warming of fundamental walls (on the ground), the replacement of doors, insulation of floors on the ground floor, floor insulation of façade floors, insulation of outdoor walls, insulation of terrace (flat roof), insulation of ceilings for non-heated attainments, modernisation of the hot water service and modernisation of the central heating system, replacement of door joinery in both buildings. As part of the project, energy audits, technical documentation have been carried out. The investor’s supervision and post-audit audit will be carried out where the thermal insulation test of the building insulation layers will be tested for the thermal insulation of the building as well as the air leak testing of the building. In view of the lack of consent from the Voivodeship Office for the Preservation of Monuments on the insulation of the façade walls of the building using warming materials (polystyrene, wool and tp), and the possibility of renewing, renovating the façade of the outer wall, the warming plaster is designed to reach the U-value max. [W/m² * K]. (English)
    0 references

    Identifiers

    RPPK.03.02.00-18-0031/18
    0 references