(Created claim: summary (P836): The aim of dredging the beach is to enable a better control of the channel gauge. The work consists of creating a marine sediment pit between the South Spike and the South Port West Pier by excavation on the foreshore., translated_summary) |
||||||||||||||
Property / summary | |||||||||||||||
The aim of dredging the beach is to enable a better control of the channel gauge. The work consists of creating a marine sediment pit between the South Spike and the South Port West Pier by excavation on the foreshore. (English) | |||||||||||||||
Property / summary: The aim of dredging the beach is to enable a better control of the channel gauge. The work consists of creating a marine sediment pit between the South Spike and the South Port West Pier by excavation on the foreshore. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The aim of dredging the beach is to enable a better control of the channel gauge. The work consists of creating a marine sediment pit between the South Spike and the South Port West Pier by excavation on the foreshore. (English) / qualifier | |||||||||||||||
point in time: 22 November 2021
|
Revision as of 14:13, 22 November 2021
Project Q3713428 in France
Language | Label | Description | Also known as |
---|---|---|---|
English | No label defined |
Project Q3713428 in France |
Statements
1,320,000.0 Euro
0 references
2,200,000.0 Euro
0 references
60.0 percent
0 references
1 January 2017
0 references
31 December 2019
0 references
GRAND PORT MARITIME DE LA REUNION
0 references
La réalisation du dragage de la plage vise à permettre une meilleure maîtrise du gabarit du chenal. Les travaux consistent à créer une fosse à sédiments marins entre l’épi Sud et la jetée Sud du Port-Ouest, par excavation sur l’estran. (French)
0 references
The aim of dredging the beach is to enable a better control of the channel gauge. The work consists of creating a marine sediment pit between the South Spike and the South Port West Pier by excavation on the foreshore. (English)
22 November 2021
0 references
Identifiers
RE0018922
0 references