(‎Created claim: summary (P836): The project is part of the construction of the New Route du Littoral and more particularly on the viaduct at sea part of which each block requires several circular ducts to pass prestressed cables when the concrete is poured., translated_summary)
Property / summary
 
The project is part of the construction of the New Route du Littoral and more particularly on the viaduct at sea part of which each block requires several circular ducts to pass prestressed cables when the concrete is poured. (English)
Property / summary: The project is part of the construction of the New Route du Littoral and more particularly on the viaduct at sea part of which each block requires several circular ducts to pass prestressed cables when the concrete is poured. (English) / rank
 
Normal rank
Property / summary: The project is part of the construction of the New Route du Littoral and more particularly on the viaduct at sea part of which each block requires several circular ducts to pass prestressed cables when the concrete is poured. (English) / qualifier
 
point in time: 22 November 2021
Timestamp+2021-11-22T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 14:06, 22 November 2021

Project Q3712755 in France
Language Label Description Also known as
English
No label defined
Project Q3712755 in France

    Statements

    0 references
    9,324.17 Euro
    0 references
    58,276.07 Euro
    0 references
    16.0 percent
    0 references
    1 March 2016
    0 references
    31 May 2016
    0 references
    SAS ALDES REUNION
    0 references
    Le projet s'inscrit dans le cadre de la construction de la Nouvelle Route du Littoral et plus particulièrement sur la partie viaduc en mer dont chaque bloc requiert plusieurs gaines circulaires pour faire passer des câbles de précontraintes lorsque le béton est coulé. (French)
    0 references
    The project is part of the construction of the New Route du Littoral and more particularly on the viaduct at sea part of which each block requires several circular ducts to pass prestressed cables when the concrete is poured. (English)
    22 November 2021
    0 references

    Identifiers

    RE0002861