(‎Created claim: summary (P836): The project involves the construction of a cliff from which a 2 ton rock detached in 2008 resulting in the destruction of a building. The work consists of the laying of a concrete wall nailed on the retaining walls, a fence plated on the rock front, the reinforcement by nailing to the rock, the purge and the roosting of unstable masses on cliffs., translated_summary)
(‎Changed label, description and/or aliases in en: translated_label)
label / enlabel / en
 
Reinforcement works of the cliff of Rue Marcel Dolhem

Revision as of 19:16, 18 November 2021

Project Q3683886 in France
Language Label Description Also known as
English
Reinforcement works of the cliff of Rue Marcel Dolhem
Project Q3683886 in France

    Statements

    0 references
    63,622.45 Euro
    0 references
    212,074.85 Euro
    0 references
    30.0 percent
    0 references
    1 October 2016
    0 references
    30 June 2017
    0 references
    MONT-SAINT-PERE
    0 references
    Le projet consiste à effectuer des travaux de confortement d'une falaise dont un rocher de 2 tonnes s'est détaché en 2008 occasionnant la destruction d'un bâtiment. Les travaux consistent en la pose de paroi béton clouée sur les murs de soutènement, d'un grillage plaqué sur le front rocheux, le confortement par clouage au rocher, la purge et le déroctage des masses instables en falaise. (French)
    0 references
    The project involves the construction of a cliff from which a 2 ton rock detached in 2008 resulting in the destruction of a building. The work consists of the laying of a concrete wall nailed on the retaining walls, a fence plated on the rock front, the reinforcement by nailing to the rock, the purge and the roosting of unstable masses on cliffs. (English)