Reconstruction of the 110/15 kV substation in order to enable the development of renewable energy (Q84416): Difference between revisions
Jump to navigation
Jump to search
(Changed an Item: Label in wikidata changed) |
(Created claim: summary (P836): The scope of the project involves the reconstruction of the GPZ 110/15 kV Kleczew electricity station in order to enable the development of renewable energy.The station is part of the 110 kV distribution network where the 15 kV electricity transition is performed., Adding English summary) |
||
Property / summary | |||
The scope of the project involves the reconstruction of the GPZ 110/15 kV Kleczew electricity station in order to enable the development of renewable energy.The station is part of the 110 kV distribution network where the 15 kV electricity transition is performed. (English) | |||
Property / summary: The scope of the project involves the reconstruction of the GPZ 110/15 kV Kleczew electricity station in order to enable the development of renewable energy.The station is part of the 110 kV distribution network where the 15 kV electricity transition is performed. (English) / rank | |||
Normal rank |
Revision as of 09:39, 4 March 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Reconstruction of the 110/15 kV substation in order to enable the development of renewable energy |
Project in Poland financed by DG Regio |
Statements
2,648,488.37 zloty
0 references
4,489,500.0 zloty
0 references
72.66 percent
0 references
28 December 2018
0 references
30 September 2020
0 references
ENERGA-OPERATOR SPÓŁKA AKCYJNA
0 references
Zakres Projektu obejmuje przebudowę stacji elektroenergetycznej GPZ 110/15 kV Kleczew celem umożliwienia rozwoju energetyki odnawialnej. Stacja stanowi element sieci dystrybucyjnej na napięciu 110 kV, na której odbywa się transformacja energii elektrycznej na napięcie 15 kV. (Polish)
0 references
The scope of the project involves the reconstruction of the GPZ 110/15 kV Kleczew electricity station in order to enable the development of renewable energy.The station is part of the 110 kV distribution network where the 15 kV electricity transition is performed. (English)
0 references
Identifiers
POIS.01.01.02-00-0004/18
0 references