Construction of a 110/15 kV station in order to enable the development of renewable energy (Q84414): Difference between revisions
Jump to navigation
Jump to search
(Changed an Item: Label in wikidata changed) |
(Created claim: summary (P836): The aim of the project is to increase the capacity to connect sources of electricity generation to RES without reducing the parameters of the energy supplied and minimise the risk of failure and power cuts (the significant barriers to the development of renewable energy will be removed).The project will increase the capacity to connect electricity generators from RES.In addition, the power supply conditions for the target audience will be improv...) |
||
Property / summary | |||
The aim of the project is to increase the capacity to connect sources of electricity generation to RES without reducing the parameters of the energy supplied and minimise the risk of failure and power cuts (the significant barriers to the development of renewable energy will be removed).The project will increase the capacity to connect electricity generators from RES.In addition, the power supply conditions for the target audience will be improved.The direct objective and therefore the project are in line with the objectives of the Operational Programme, the priority axis and the activities and sub-actions of the OPI & E 1.1.2.The project covers the construction of a new electricity station GPZ Skwierina II 110/15 kV consisting of a 110 kV switchgear and a 15 kV switchgear.The station is part of the 110 kV distribution network where the 15 kV electricity transition is performed along with a 110 kV line and 15 kV lines. (English) | |||
Property / summary: The aim of the project is to increase the capacity to connect sources of electricity generation to RES without reducing the parameters of the energy supplied and minimise the risk of failure and power cuts (the significant barriers to the development of renewable energy will be removed).The project will increase the capacity to connect electricity generators from RES.In addition, the power supply conditions for the target audience will be improved.The direct objective and therefore the project are in line with the objectives of the Operational Programme, the priority axis and the activities and sub-actions of the OPI & E 1.1.2.The project covers the construction of a new electricity station GPZ Skwierina II 110/15 kV consisting of a 110 kV switchgear and a 15 kV switchgear.The station is part of the 110 kV distribution network where the 15 kV electricity transition is performed along with a 110 kV line and 15 kV lines. (English) / rank | |||
Normal rank |
Revision as of 09:39, 4 March 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of a 110/15 kV station in order to enable the development of renewable energy |
Project in Poland financed by DG Regio |
Statements
16,448,895.5 zloty
0 references
35,834,438.7 zloty
0 references
62.54 percent
0 references
22 March 2019
0 references
30 September 2021
0 references
ENEA OPERATOR SP. Z O.O.
0 references
Celem projektu jest zwiększenie możliwości przyłączenia źródeł wytwarzania energii elektrycznej OZE bez jednoczesnego obniżania parametrów dostarczanej energii oraz przy minimalizowaniu ryzyka wystąpienia awarii i przerw w dostawie energii (zniesione zostaną istotne bariery dla rozwoju energetyki odnawialnej). W wyniku realizacji projektu zwiększy się możliwość przyłączenia wytwórców energii elektrycznej z OZE. Ponadto, poprawie ulegną warunki zasilania odbiorców objętych zasięgiem oddziaływania stacji. Cel bezpośredni, a tym samym projekt, jest zgodny z celami Programu Operacyjnego, osi priorytetowej oraz działania i poddziałania 1.1.2 POIiŚ. Projekt obejmuje swoim zakresem budowę nowej stacji elektroenergetycznej GPZ Skwierzyna II 110/15 kV składającej się z rozdzielni 110 kV i rozdzielnicy 15 kV. Stacja stanowi element sieci dystrybucyjnej na napięciu 110 kV, na której odbywa się transformacja energii elektrycznej na napięcie 15 kV wraz z linią zasilającą 110 kV oraz wyprowadzeniami 15 kV. (Polish)
0 references
The aim of the project is to increase the capacity to connect sources of electricity generation to RES without reducing the parameters of the energy supplied and minimise the risk of failure and power cuts (the significant barriers to the development of renewable energy will be removed).The project will increase the capacity to connect electricity generators from RES.In addition, the power supply conditions for the target audience will be improved.The direct objective and therefore the project are in line with the objectives of the Operational Programme, the priority axis and the activities and sub-actions of the OPI & E 1.1.2.The project covers the construction of a new electricity station GPZ Skwierina II 110/15 kV consisting of a 110 kV switchgear and a 15 kV switchgear.The station is part of the 110 kV distribution network where the 15 kV electricity transition is performed along with a 110 kV line and 15 kV lines. (English)
0 references
Identifiers
POIS.01.01.02-00-0003/19
0 references