(Changed an Item: modifying co-finance rate with the percentage) |
(Created claim: summary (P836): The aim of the project "Reducing the energy intensity of buildings: Kindergarten Hrnčiarska and Maternity School Fullu in Zvolen" is the reduction of energy consumption in the operation of the buildings of kindergartens by implementing the measures resulting from the energy audit. The applicant for the grant of a non-repayable financial contribution for the implementation of the submitted project is the City of Zvolen, as owner of the building a...) |
||||||||||||||
Property / summary | |||||||||||||||
The aim of the project "Reducing the energy intensity of buildings: Kindergarten Hrnčiarska and Maternity School Fullu in Zvolen" is the reduction of energy consumption in the operation of the buildings of kindergartens by implementing the measures resulting from the energy audit. The applicant for the grant of a non-repayable financial contribution for the implementation of the submitted project is the City of Zvolen, as owner of the building and land and the founder of the kindergarten. The target group are employees of kindergartens, children attending these pre-school facilities and their parents. The project will be implemented through two main activities and project support activities. The place of implementation of the project is the MŠ on Hrnčiarská Street No. 2063/2 MŠ and MŠ in Street Ľ. Fullu No. 1689/43.As a result of the implementation of the project, two public buildings will be renovated beyond the minimum requirements with a total floor area of 3333 m². The implementation of the project will reduce energy needs in buildings (difference between the total annual energy demand before and after the implementation of energy efficiency measures) by 276700 kWh/year, while the specific energy demand for heating will be reduced for the PO from 120 kWh/(m².a) to 21 kWh/(m².a), i.e. 82.5 % and for MS Ľ. Fullu from 112 kWh/(m².a) to 22 kWh/(m².a) or 80.4 %. After the completion of the project, both buildings will be classified in energy class A1. (English) | |||||||||||||||
Property / summary: The aim of the project "Reducing the energy intensity of buildings: Kindergarten Hrnčiarska and Maternity School Fullu in Zvolen" is the reduction of energy consumption in the operation of the buildings of kindergartens by implementing the measures resulting from the energy audit. The applicant for the grant of a non-repayable financial contribution for the implementation of the submitted project is the City of Zvolen, as owner of the building and land and the founder of the kindergarten. The target group are employees of kindergartens, children attending these pre-school facilities and their parents. The project will be implemented through two main activities and project support activities. The place of implementation of the project is the MŠ on Hrnčiarská Street No. 2063/2 MŠ and MŠ in Street Ľ. Fullu No. 1689/43.As a result of the implementation of the project, two public buildings will be renovated beyond the minimum requirements with a total floor area of 3333 m². The implementation of the project will reduce energy needs in buildings (difference between the total annual energy demand before and after the implementation of energy efficiency measures) by 276700 kWh/year, while the specific energy demand for heating will be reduced for the PO from 120 kWh/(m².a) to 21 kWh/(m².a), i.e. 82.5 % and for MS Ľ. Fullu from 112 kWh/(m².a) to 22 kWh/(m².a) or 80.4 %. After the completion of the project, both buildings will be classified in energy class A1. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The aim of the project "Reducing the energy intensity of buildings: Kindergarten Hrnčiarska and Maternity School Fullu in Zvolen" is the reduction of energy consumption in the operation of the buildings of kindergartens by implementing the measures resulting from the energy audit. The applicant for the grant of a non-repayable financial contribution for the implementation of the submitted project is the City of Zvolen, as owner of the building and land and the founder of the kindergarten. The target group are employees of kindergartens, children attending these pre-school facilities and their parents. The project will be implemented through two main activities and project support activities. The place of implementation of the project is the MŠ on Hrnčiarská Street No. 2063/2 MŠ and MŠ in Street Ľ. Fullu No. 1689/43.As a result of the implementation of the project, two public buildings will be renovated beyond the minimum requirements with a total floor area of 3333 m². The implementation of the project will reduce energy needs in buildings (difference between the total annual energy demand before and after the implementation of energy efficiency measures) by 276700 kWh/year, while the specific energy demand for heating will be reduced for the PO from 120 kWh/(m².a) to 21 kWh/(m².a), i.e. 82.5 % and for MS Ľ. Fullu from 112 kWh/(m².a) to 22 kWh/(m².a) or 80.4 %. After the completion of the project, both buildings will be classified in energy class A1. (English) / qualifier | |||||||||||||||
point in time: 28 September 2021
|
Revision as of 13:53, 28 September 2021
Project Q3100692 in Slovakia
Language | Label | Description | Also known as |
---|---|---|---|
English | Reducing the energy intensity of buildings: Maternity rounds Hrnčiarska and Maternity rounds Fullu in Zvolen |
Project Q3100692 in Slovakia |
Statements
945,949.07 Euro
0 references
1,112,881.26 Euro
0 references
85.0 percent
0 references
1 April 2017
0 references
1 May 2018
0 references
Mesto Zvolen
0 references
Cieľom projektu s názvom „Zníženie energetickej náročnosti budov: Materská škola Hrnčiarska a Materská škola Fullu vo Zvolene“ je zníženie spotreby energie pri prevádzke budov materských škôl realizáciou opatrení, ktoré vyplývajú z energetického auditu. Žiadateľom o poskytnutie nenávratného finančného príspevku na realizáciu predkladaného projektu je Mesto Zvolen, ako majiteľ budovy a pozemku a zriaďovateľ materskej školy.Cieľovou skupinou sú zamestnanci materských škôl, deti navštevujúce tieto predškolské zariadenia a ich rodičia. Projekt bude realizovaný prostredníctvom dvoch hlavných aktivít a podporných aktivít projektu. Miestom realizácie projektu je MŠ na Hrnčiarskej ulici č. 2063/2 MŠ a MŠ na Ulici Ľ. Fullu č. 1689/43.V dôsledku realizácie projektu dôjde k obnove dvoch verejných budovy nad rámec minimálnych požiadaviek s celkovou podlahovou plochou 3333 m2. Realizáciou projektu dôjde ku zníženiu potreby energie v budovách (rozdiel medzi celkovou ročnou potrebou energie pred a po realizácii opatrení energetickej efektívnosti) o 276700 kWh/rok, pričom merná potreba energie na vykurovanie sa zníži pri MŠ Hrnčiarka zo 120 kWh/(m2.a) na 21 kWh/(m2.a), teda o 82,5 % a pri MŠ Ľ. Fullu z 112 kWh/(m2.a) na 22 kWh/(m2.a), teda o 80,4 %. Po ukončení realizácie projektu budú obidve budovy zaradené v energetickej triede A1. (Slovak)
0 references
The aim of the project "Reducing the energy intensity of buildings: Kindergarten Hrnčiarska and Maternity School Fullu in Zvolen" is the reduction of energy consumption in the operation of the buildings of kindergartens by implementing the measures resulting from the energy audit. The applicant for the grant of a non-repayable financial contribution for the implementation of the submitted project is the City of Zvolen, as owner of the building and land and the founder of the kindergarten. The target group are employees of kindergartens, children attending these pre-school facilities and their parents. The project will be implemented through two main activities and project support activities. The place of implementation of the project is the MŠ on Hrnčiarská Street No. 2063/2 MŠ and MŠ in Street Ľ. Fullu No. 1689/43.As a result of the implementation of the project, two public buildings will be renovated beyond the minimum requirements with a total floor area of 3333 m². The implementation of the project will reduce energy needs in buildings (difference between the total annual energy demand before and after the implementation of energy efficiency measures) by 276700 kWh/year, while the specific energy demand for heating will be reduced for the PO from 120 kWh/(m².a) to 21 kWh/(m².a), i.e. 82.5 % and for MS Ľ. Fullu from 112 kWh/(m².a) to 22 kWh/(m².a) or 80.4 %. After the completion of the project, both buildings will be classified in energy class A1. (English)
28 September 2021
0 references
Identifiers
310041A562
0 references