Construction of a photovoltaic installation with a capacity of about 1 MWp at the Regional Waste Management Plant in Słajsin on plot No 66/8 with an area of 2,8318 ha, the area of Słajsino, Nowogard. (Q2718695): Difference between revisions
Jump to navigation
Jump to search
(Changed claim: EU contribution (P835): 433,815.63 euro) |
(Changed claim: budget (P474): 723,026.05 euro) |
||
Property / budget: 723,026.05 Euro / rank | Property / budget: 723,026.05 Euro / rank | ||
Preferred rank |
Revision as of 01:41, 22 September 2021
Project Q2718695 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of a photovoltaic installation with a capacity of about 1 MWp at the Regional Waste Management Plant in Słajsin on plot No 66/8 with an area of 2,8318 ha, the area of Słajsino, Nowogard. |
Project Q2718695 in Poland |
Statements
1,951,487.3 zloty
0 references
3,252,478.85 zloty
0 references
60.0 percent
0 references
30 November 2020
0 references
31 December 2022
0 references
CELOWY ZWIAZEK GMIN R - XXI
0 references
Projekt ma charakter stacjonarny. Realizacja projektu zostanie zlokalizowana w Słajsinie na działce nr 66/8 o powierzchni 2,8318 ha, obręb Słajsino, gm. Nowogard. Realizacja projektu będzie polegała na budowie instalacji fotowoltaicznej o mocy około 1 MWp na terenie Regionalnego Zakładu Gospodarowania Odpadami. W celu prawidłowej realizacji projektu, na etapie aplikacyjnym i w trakcie wdrażania powołany został zespół zadaniowy dla projektu. Do zadań zespołu projektu będzie należała weryfikacja postępu rzeczowego, poprawność realizacji projektu, nadzór i kontrola. Aby zapewnić bezpieczeństwo związane z prawidłowym rozliczeniem projektu Wnioskodawca bierze pod uwagę skorzystanie z usług wyspecjalizowanej firmy doradczej. Usługa obejmie pomoc w zakresie prawidłowej realizacji projektu (przeprowadzenie procedury wyboru wykonawcy, realizacja projektu, rozliczenie projektu). Głównymi etapami projektu są: opracowanie koncepcji projektu, przygotowanie wniosku aplikacyjnego wraz z załącznikami, przygotowanie i przeprowadzenie procedury przetargowej na wykonawców, realizacja robót budowlanych i montaż instalacji fotowoltaicznych, uruchomienie instalacji, nadzór nad realizacją projektu. (Polish)
0 references
The project is stationary. The implementation of the project will be located in Słajsino on plot No 66/8 with an area of 2,8318 ha, the area of Słajsino, Nowogard. The implementation of the project will consist of the construction of a photovoltaic installation with a capacity of about 1 MWp at the Regional Waste Management Plant. In order to implement the project correctly, at the application stage and during implementation, a task force for the project was set up. The tasks of the project team will include verification of factual progress, correctness of project implementation, supervision and control. In order to ensure the safety associated with the correct settlement of the project, the Applicant shall take into account the use of a specialised consultancy firm. The service will include assistance in the correct implementation of the project (performance of the procedure for selecting the contractor, implementation of the project, settlement of the project). The main stages of the project are: development of the design concept, preparation of the application and annexes, preparation and conduct of tendering procedure for contractors, execution of construction works and installation of photovoltaic installations, installation of installations, supervision of project implementation. (English)
8 July 2021
0 references
Identifiers
RPZP.02.10.00-32-C073/20
0 references