(‎Created claim: summary (P836): The project is aimed at expanding the capacity of the existing Maternity School on Hrebendova Street in Koice-MČ LUNÍK IX, with a high concentration of the presence of MRK. The main activity of the project is the reconstruction of the building of the maternal cola/should workplace in order to expand its capacity by extension, superstructure, reconstruction, change of disposition of objects. Project riei extension of a new single-floor pavilion f...)
Property / summary
 
The project is aimed at expanding the capacity of the existing Maternity School on Hrebendova Street in Koice-MČ LUNÍK IX, with a high concentration of the presence of MRK. The main activity of the project is the reconstruction of the building of the maternal cola/should workplace in order to expand its capacity by extension, superstructure, reconstruction, change of disposition of objects. Project riei extension of a new single-floor pavilion for two classes (44 iakov).The time of the project is the reconstruction of the existing connecting corridor and building modifications – insulation of the bolted construction. Overall, building modifications to existing buildings account for 26 % of the packaging construction, which means that it is a significant renovation from the demand for minimum requirements for the energy efficiency of buildings. At the time of building modifications and extensions are construction works to ensure the supply of energy, water as well as waste treatment, new fencing. By implementing the activities, we will ensure an increase in capacity in the existing maternity round by more than 30 % of the current capacity. The project is linked to the planned non-investment activities under Priority Axis 5, because Koice is planning to participate in the Take away NP. The project is in line with specific objective 6.1.2 Improve access to quality education, including early childhood education and care, under OP źZ and will contribute to the reconciliation of work and family life. (English)
Property / summary: The project is aimed at expanding the capacity of the existing Maternity School on Hrebendova Street in Koice-MČ LUNÍK IX, with a high concentration of the presence of MRK. The main activity of the project is the reconstruction of the building of the maternal cola/should workplace in order to expand its capacity by extension, superstructure, reconstruction, change of disposition of objects. Project riei extension of a new single-floor pavilion for two classes (44 iakov).The time of the project is the reconstruction of the existing connecting corridor and building modifications – insulation of the bolted construction. Overall, building modifications to existing buildings account for 26 % of the packaging construction, which means that it is a significant renovation from the demand for minimum requirements for the energy efficiency of buildings. At the time of building modifications and extensions are construction works to ensure the supply of energy, water as well as waste treatment, new fencing. By implementing the activities, we will ensure an increase in capacity in the existing maternity round by more than 30 % of the current capacity. The project is linked to the planned non-investment activities under Priority Axis 5, because Koice is planning to participate in the Take away NP. The project is in line with specific objective 6.1.2 Improve access to quality education, including early childhood education and care, under OP źZ and will contribute to the reconciliation of work and family life. (English) / rank
 
Normal rank
Property / summary: The project is aimed at expanding the capacity of the existing Maternity School on Hrebendova Street in Koice-MČ LUNÍK IX, with a high concentration of the presence of MRK. The main activity of the project is the reconstruction of the building of the maternal cola/should workplace in order to expand its capacity by extension, superstructure, reconstruction, change of disposition of objects. Project riei extension of a new single-floor pavilion for two classes (44 iakov).The time of the project is the reconstruction of the existing connecting corridor and building modifications – insulation of the bolted construction. Overall, building modifications to existing buildings account for 26 % of the packaging construction, which means that it is a significant renovation from the demand for minimum requirements for the energy efficiency of buildings. At the time of building modifications and extensions are construction works to ensure the supply of energy, water as well as waste treatment, new fencing. By implementing the activities, we will ensure an increase in capacity in the existing maternity round by more than 30 % of the current capacity. The project is linked to the planned non-investment activities under Priority Axis 5, because Koice is planning to participate in the Take away NP. The project is in line with specific objective 6.1.2 Improve access to quality education, including early childhood education and care, under OP źZ and will contribute to the reconciliation of work and family life. (English) / qualifier
 
point in time: 15 September 2021
Timestamp+2021-09-15T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 13:10, 15 September 2021

Project Q3100635 in Slovakia
Language Label Description Also known as
English
No label defined
Project Q3100635 in Slovakia

    Statements

    0 references
    469,540.0 Euro
    0 references
    552,400.0 Euro
    0 references
    0.85 percent
    0 references
    1 February 2016
    0 references
    1 December 2019
    0 references
    Mesto Košice
    0 references

    48°42'51.52"N, 21°14'4.52"E
    0 references
    Projekt je zameraný na rozšírenie kapacity existujúcej materskej školy na Hrebendovej ulici v Košiciach-MČ LUNÍK IX,s vysokou koncentráciou prítomnosti MRK. Hlavnou aktivitou projektu je Rekonštrukcia budovy materskej školy/elokovaného pracoviska za účelom rozšírenia jej kapacity prístavbou, nadstavbou, rekonštrukciou, zmenou dispozície objektov. Projekt rieši prístavbu nového jednopodlažného pavilónu pre dve triedy(44 žiakov).Súčasou projektu je prestavba existujúcej spojovacej chodby a stavebné úpravy - zateplenia strešnej konštrukcie. Celkovo predstavujú stavebné úpravy existujúcich budov 26% obalovej konštrukcie,čo znamená,že sa jedná o významnú obnovu z hžadiska minimálnych požiadaviek na energetickú hospodárnos budov.Súčasou stavebných úprav a prístavby sú stavebné práce pre zabezpečenie dodávok energií, vody ako aj riešenia odpadov, nové oplotenie.Realizovaním aktivít zabezpečíme nárast kapacity v existujúcej materskej škole viac ako o 30% súčasnej kapacity. Projekt je previazaný na plánované neinvestičné aktivity v rámci prioritnej osi 5, pretože sa mesto Košice plánuje zapoji do NP Take away. Projekt je v súlade so Špecifickým ciežom 6.1.2 Zlepši prístup ku kvalitnému vzdelávaniu vrátane vzdelávania a starostlivosti v rannom detstve v rámci OP źZ a prispeje k zosúladeniu pracovného a rodinného života u žien. (Slovak)
    0 references
    The project is aimed at expanding the capacity of the existing Maternity School on Hrebendova Street in Koice-MČ LUNÍK IX, with a high concentration of the presence of MRK. The main activity of the project is the reconstruction of the building of the maternal cola/should workplace in order to expand its capacity by extension, superstructure, reconstruction, change of disposition of objects. Project riei extension of a new single-floor pavilion for two classes (44 iakov).The time of the project is the reconstruction of the existing connecting corridor and building modifications – insulation of the bolted construction. Overall, building modifications to existing buildings account for 26 % of the packaging construction, which means that it is a significant renovation from the demand for minimum requirements for the energy efficiency of buildings. At the time of building modifications and extensions are construction works to ensure the supply of energy, water as well as waste treatment, new fencing. By implementing the activities, we will ensure an increase in capacity in the existing maternity round by more than 30 % of the current capacity. The project is linked to the planned non-investment activities under Priority Axis 5, because Koice is planning to participate in the Take away NP. The project is in line with specific objective 6.1.2 Improve access to quality education, including early childhood education and care, under OP źZ and will contribute to the reconciliation of work and family life. (English)
    15 September 2021
    0 references

    Identifiers

    312061B446
    0 references