Q3079336 (Q3079336): Difference between revisions
Jump to navigation
Jump to search
(Changed an Item: Edited by the infer coords bot - inferring coordiantes from postal codes) |
(Created claim: summary (P836): The project will include the construction of one 34,5 m long wooden staircase with a single handrail and a terrace with borders on the top of the cobblestones. For the construction of stairs and terraces, a construction project has been prepared by OÜ Minnol in 2011, which includes the reconstruction of the entire hiking trail. Building a staircase is part of it. In 2012, a pedestrian arc bridge was built on the hiking trail (between lakes) acco...) |
||||||||||||||
Property / summary | |||||||||||||||
The project will include the construction of one 34,5 m long wooden staircase with a single handrail and a terrace with borders on the top of the cobblestones. For the construction of stairs and terraces, a construction project has been prepared by OÜ Minnol in 2011, which includes the reconstruction of the entire hiking trail. Building a staircase is part of it. In 2012, a pedestrian arc bridge was built on the hiking trail (between lakes) according to the above-mentioned project. The self-financing of the project is co-financed by the Environmental Programme of EIC. (English) | |||||||||||||||
Property / summary: The project will include the construction of one 34,5 m long wooden staircase with a single handrail and a terrace with borders on the top of the cobblestones. For the construction of stairs and terraces, a construction project has been prepared by OÜ Minnol in 2011, which includes the reconstruction of the entire hiking trail. Building a staircase is part of it. In 2012, a pedestrian arc bridge was built on the hiking trail (between lakes) according to the above-mentioned project. The self-financing of the project is co-financed by the Environmental Programme of EIC. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The project will include the construction of one 34,5 m long wooden staircase with a single handrail and a terrace with borders on the top of the cobblestones. For the construction of stairs and terraces, a construction project has been prepared by OÜ Minnol in 2011, which includes the reconstruction of the entire hiking trail. Building a staircase is part of it. In 2012, a pedestrian arc bridge was built on the hiking trail (between lakes) according to the above-mentioned project. The self-financing of the project is co-financed by the Environmental Programme of EIC. (English) / qualifier | |||||||||||||||
point in time: 16 August 2021
|
Revision as of 14:20, 16 August 2021
Project Q3079336 in Estonia
Language | Label | Description | Also known as |
---|---|---|---|
English | No label defined |
Project Q3079336 in Estonia |
Statements
20,528.11 Euro
0 references
24,150.72 Euro
0 references
85.0 percent
0 references
1 April 2015
0 references
31 October 2015
0 references
Alatskivi Vallavalitsus
0 references
60201
0 references
Projekti raames ehitatakse üks 34,5 meetri pikkune ühepoolse käsipuuga puutrepp ja ülemisel osale munakividest terrass koos piiretega. Trepi ja terrassi ehituseks on koostatud 2011.aastal OÜ Minnoli poolt ehitusprojekt, mis hõlmab kogu matkaraja rekonstrueerimist. Trepi ehitamine on üks osa sellest. 2012.aastal ehitati eelpoolnimetatud projekti järgi matkarajale (järvede vahele) jalakäijate kaarsild. Projekti omafinantseering kaasfinantseeritakse KIKi Keskkonnaprogrammist. (Estonian)
0 references
The project will include the construction of one 34,5 m long wooden staircase with a single handrail and a terrace with borders on the top of the cobblestones. For the construction of stairs and terraces, a construction project has been prepared by OÜ Minnol in 2011, which includes the reconstruction of the entire hiking trail. Building a staircase is part of it. In 2012, a pedestrian arc bridge was built on the hiking trail (between lakes) according to the above-mentioned project. The self-financing of the project is co-financed by the Environmental Programme of EIC. (English)
16 August 2021
0 references
Identifiers
2014-2020.8.01.004.01.15-0010
0 references