Construction of a sanitary sewerage network in Dobków Stage II. (Q2698549): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed label, description and/or aliases in en: translated_label)
(‎Changed an Item)
Property / programme
 
Property / programme: Dolno?l?skie Voivodeship - ERDF/ESF / rank
 
Normal rank

Revision as of 00:15, 26 July 2021

Project Q2698549 in Poland
Language Label Description Also known as
English
Construction of a sanitary sewerage network in Dobków Stage II.
Project Q2698549 in Poland

    Statements

    0 references
    3,364,153.8 zloty
    0 references
    747,851.39 Euro
    0.2223 Euro
    0 references
    3,957,828.0 zloty
    0 references
    879,825.16 Euro
    0.2223 Euro
    0 references
    85.0 percent
    0 references
    14 December 2020
    0 references
    30 November 2021
    0 references
    GMINA ŚWIERZAWA
    0 references

    51°0'52.9"N, 15°53'41.6"E
    0 references
    Przedmiotowy projekt dotyczy kontynuacji budowy sieci kanalizacji sanitarnej w miejscowości Dobków w aglomeracji Świerzawa (liczba RLM aglomeracji - 4790). Zarówno zakres prac planowanych do realizacji jak i sama aglomeracja (id aglomeracji PLDO084) została ujętej w KPOŚK i Master Planie dla wdrażania dyrektywy Rady 91/271/EWG w sprawie oczyszczania ścieków komunalnych. Celem główny projektu jest wzrost jakości życia mieszkańców poprzez zwiększenie odsetka osób korzystających z systemu oczyszczania ścieków w następstwie budowy systemu kanalizacji aglomeracji Świerzawa. W ramach projektu zrealizowane zostanie budowa sieci grawitacyjno - ciśnieniowej kanalizacji sanitarnej dla wsi Dobków składające się z: - grawitacyjnej sieci kanalizacji sanitarnej, O 200 L=3,5km, O 160 L=1,5km - sieciowych przepompowni ścieków - 8 szt. Dzięki realizacji przedmiotowego projektu do zbiorowego systemu oczyszczalni ścieków zostanie podłączonych 350 RLM na terenie aglomeracji Świerzawa, które do tej pory nie miały dostępu do sieci kanalizacyjnej. Z uwagi na ukształtowanie terenu przedmiotowy projekt dot. budowy kanalizacji sanitarnej grawitacyjnej oraz w niezbędnym zakresie kanalizacji tłocznej obejmującej osiem przepompowni ścieków sanitarnych. Przepompownie ścieków zlokalizowano w miejscach, gdzie transport grawitacyjny ścieków jest niemożliwy i wymusza to konieczność zastosowania rurociągów tłocznych. W związku z powyższym w ramach projektu przewidziano budowę sieci kanalizacji grawitacyjno-tłocznej. Wskazany w niniejszym wniosku zakres prac, był już przedmiotem projektu dofinansowanego w ramach RPO WD 2014-2020 w ramach umowy nr RPDS.04.02.03-02-0002/16-00. Ze względu na problemy w wykonawcą robót budowlanych Gmina Świerzawa zmuszona była rozwiązać umowę z wykonawcą robót i finalnie nie zrealizowała całości prac. (Polish)
    0 references
    The project in question concerns the continuation of the construction of a sanitary sewerage network in Dobków in the agglomeration of Świerzawa (the number of agglomerations p.e. – 4790). Both the scope of the work to be carried out and the agglomeration itself (i.e. the agglomeration PLDO084) are included in the NEPK and the Master Plan for the implementation of Council Directive 91/271/EEC on urban waste water treatment. The main objective of the project is to increase the quality of life of residents by increasing the percentage of people using the wastewater treatment system following the construction of the sewerage system of the Świerzawa agglomeration. As part of the project, the construction of a gravity-pressure sewerage network for the village of Dobków will be carried out, consisting of: — gravity sewage network, O 200 L=3,5km, O 160 L=1.5 km – network sewage pumping stations – 8 pcs. Thanks to the implementation of this project, 350 p.e. will be connected to the collective waste water treatment plant system in the area of Świerzawa agglomeration, which so far had no access to the sewerage network. Due to the terrain, the project in question concerning the construction of a gravity sewerage system and, to the extent necessary, a drainage system consisting of eight sewage pumping stations. Sewage pumping stations are located in places where gravity transport of waste water is impossible and this necessitates the use of pressure pipelines. In view of the above, the project envisaged the construction of a gravity-pressure sewerage network. The scope of work referred to in this application has already been the subject of a project co-financed under the ROP WD 2014-2020 under contract No RPDS.04.02.03-02-0002/16-00. Due to problems in the construction contractor, the municipality of Świerzawa was forced to terminate the contract with the contractor and ultimately failed to complete the works. (English)
    7 July 2021
    0 references

    Identifiers

    RPDS.04.02.03-02-0001/20
    0 references