(‎Created claim: summary (P836): The aim of the project is reconstruction of the national regional road P73 Vecumnieki – Nereta – Subate km 57.56-65.10, which includes the construction of a duvet and the purchase of land. The total planned duration of the project is 51 months. The planned total cost of the project is EUR 7287607,38, including the planned European Regional Development Fund funding – EUR 6194466.27 and the state budget funding – EUR 1093141.11. As a result of the...)
Property / summary
 
The aim of the project is reconstruction of the national regional road P73 Vecumnieki – Nereta – Subate km 57.56-65.10, which includes the construction of a duvet and the purchase of land. The total planned duration of the project is 51 months. The planned total cost of the project is EUR 7287607,38, including the planned European Regional Development Fund funding – EUR 6194466.27 and the state budget funding – EUR 1093141.11. As a result of the project, the national regional road P73 Vecumnieki – Nereta – Subate will be arranged in the length of 57.56-65.10-7.54 km. The maximum driven axle load of road sections covered by the project will be 11.5 tonnes after the implementation of the project and the maximum uncontrolled vehicle mass will be 44 tonnes. The road is state-owned. If necessary, the necessary plots will be purchased. (English)
Property / summary: The aim of the project is reconstruction of the national regional road P73 Vecumnieki – Nereta – Subate km 57.56-65.10, which includes the construction of a duvet and the purchase of land. The total planned duration of the project is 51 months. The planned total cost of the project is EUR 7287607,38, including the planned European Regional Development Fund funding – EUR 6194466.27 and the state budget funding – EUR 1093141.11. As a result of the project, the national regional road P73 Vecumnieki – Nereta – Subate will be arranged in the length of 57.56-65.10-7.54 km. The maximum driven axle load of road sections covered by the project will be 11.5 tonnes after the implementation of the project and the maximum uncontrolled vehicle mass will be 44 tonnes. The road is state-owned. If necessary, the necessary plots will be purchased. (English) / rank
 
Normal rank
Property / summary: The aim of the project is reconstruction of the national regional road P73 Vecumnieki – Nereta – Subate km 57.56-65.10, which includes the construction of a duvet and the purchase of land. The total planned duration of the project is 51 months. The planned total cost of the project is EUR 7287607,38, including the planned European Regional Development Fund funding – EUR 6194466.27 and the state budget funding – EUR 1093141.11. As a result of the project, the national regional road P73 Vecumnieki – Nereta – Subate will be arranged in the length of 57.56-65.10-7.54 km. The maximum driven axle load of road sections covered by the project will be 11.5 tonnes after the implementation of the project and the maximum uncontrolled vehicle mass will be 44 tonnes. The road is state-owned. If necessary, the necessary plots will be purchased. (English) / qualifier
 
point in time: 15 July 2021
Timestamp+2021-07-15T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 12:47, 15 July 2021

Project Q3057649 in Latvia
Language Label Description Also known as
English
No label defined
Project Q3057649 in Latvia

    Statements

    0 references
    0 references
    6,194,466.27 Euro
    0 references
    7,287,607.38 Euro
    0 references
    23 September 2016
    0 references
    22 December 2020
    0 references
    Satiksmes ministrija
    0 references
    0 references

    56°12'21.31"N, 25°18'36.90"E
    0 references
    Projekta mērķis ir valsts reģionālā autoceļa P73 Vecumnieki – Nereta – Subate posma km 57,56 – 65,10 pārbūve, kas ietver segas izbūvi un zemju iegādi. Plānotais kopējais projekta īstenošanas ilgums 51 mēneši. Projekta plānotās kopējās izmaksas 7 287 607,38 euro, t.sk. plānotais Eiropas Reģionālās attīstības fonda finansējums – 6 194 466,27 euro un valsts budžeta finansējums – 1 093 141,11 euro. Projekta īstenošanas rezultātā tiks sakārtots valsts reģionālā autoceļa P73 Vecumnieki – Nereta – Subate posma km 57,56 – 65,10 – 7,54 km garumā. Projektā ietvertā autoceļa posmu maksimālā autotransporta dzenošās ass slodze pēc projekta īstenošanas būs 11,5 tonnas un maksimālā nekontrolētā transportlīdzekļa pilnā masa būs 44 tonnas. Autoceļš atrodas valsts īpašumā. Nepieciešamības gadījumā vajadzīgie zemes gabali tiks iegādāti. (Latvian)
    0 references
    The aim of the project is reconstruction of the national regional road P73 Vecumnieki – Nereta – Subate km 57.56-65.10, which includes the construction of a duvet and the purchase of land. The total planned duration of the project is 51 months. The planned total cost of the project is EUR 7287607,38, including the planned European Regional Development Fund funding – EUR 6194466.27 and the state budget funding – EUR 1093141.11. As a result of the project, the national regional road P73 Vecumnieki – Nereta – Subate will be arranged in the length of 57.56-65.10-7.54 km. The maximum driven axle load of road sections covered by the project will be 11.5 tonnes after the implementation of the project and the maximum uncontrolled vehicle mass will be 44 tonnes. The road is state-owned. If necessary, the necessary plots will be purchased. (English)
    15 July 2021
    0 references
    Neretas pag., Aizkraukles nov.
    0 references
    Neretas pag., Aizkraukles nov.