(Created claim: summary (P836): The assistance covered by this application corresponds to the 2nd phase of modernisation of the Ovar-Gaia section, including the construction of level crossings, the complete renewal of the track between the PK 296+ 600 and the PK 332+ 780, the installation of electronic signalling systems, telecommunications and automatic speed control between the PK 299+ 885 and the PK 332+ 760 and the carrying out of studies and projects., translated_summary) |
||||||||||||||
Property / summary | |||||||||||||||
The assistance covered by this application corresponds to the 2nd phase of modernisation of the Ovar-Gaia section, including the construction of level crossings, the complete renewal of the track between the PK 296+ 600 and the PK 332+ 780, the installation of electronic signalling systems, telecommunications and automatic speed control between the PK 299+ 885 and the PK 332+ 760 and the carrying out of studies and projects. (English) | |||||||||||||||
Property / summary: The assistance covered by this application corresponds to the 2nd phase of modernisation of the Ovar-Gaia section, including the construction of level crossings, the complete renewal of the track between the PK 296+ 600 and the PK 332+ 780, the installation of electronic signalling systems, telecommunications and automatic speed control between the PK 299+ 885 and the PK 332+ 760 and the carrying out of studies and projects. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The assistance covered by this application corresponds to the 2nd phase of modernisation of the Ovar-Gaia section, including the construction of level crossings, the complete renewal of the track between the PK 296+ 600 and the PK 332+ 780, the installation of electronic signalling systems, telecommunications and automatic speed control between the PK 299+ 885 and the PK 332+ 760 and the carrying out of studies and projects. (English) / qualifier | |||||||||||||||
point in time: 8 July 2021
|
Revision as of 13:06, 8 July 2021
Project Q2913358 in Portugal
Language | Label | Description | Also known as |
---|---|---|---|
English | No label defined |
Project Q2913358 in Portugal |
Statements
118,738,326.73 Euro
0 references
85.0 percent
0 references
30 April 2014
0 references
31 December 2022
0 references
INFRAESTRUTURAS DE PORTUGAL, S.A.
0 references
A intervenção objeto da presente candidatura corresponde à 2.ª fase de modernização do troço Ovar-Gaia inclui a construção de desnivelamentos para supressão de passagens de nível, a renovação integral da via entre o PK 296+600 e o PK 332+780, a instalação de sistemas de sinalização eletrónica, telecomunicações e controlo automático de velocidade entre o PK 299+885 e o PK 332+760 e a realização de estudos e projetos. (Portuguese)
0 references
The assistance covered by this application corresponds to the 2nd phase of modernisation of the Ovar-Gaia section, including the construction of level crossings, the complete renewal of the track between the PK 296+ 600 and the PK 332+ 780, the installation of electronic signalling systems, telecommunications and automatic speed control between the PK 299+ 885 and the PK 332+ 760 and the carrying out of studies and projects. (English)
8 July 2021