Q2743955 (Q2743955): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed label, description and/or aliases in en)
(‎Created claim: summary (P836): Through this project it is proposed: – extension of level 3 on the entire existing surface of the lower floor (existing), maintaining the sections of the elements on this level.- extension of the escape stairs up to the level of the 3rd floor and rehabilitation of the elevator – extension of Annex C8.1 from the height regime D+P to D+P+ 2E height regime – the vertical and horizontal extension of the elevator house, in order to place a new elevat...)
Property / summary
 
Through this project it is proposed: – extension of level 3 on the entire existing surface of the lower floor (existing), maintaining the sections of the elements on this level.- extension of the escape stairs up to the level of the 3rd floor and rehabilitation of the elevator – extension of Annex C8.1 from the height regime D+P to D+P+ 2E height regime – the vertical and horizontal extension of the elevator house, in order to place a new elevator with the possibility of access with a stretcher and on the stairs. The light courtyards will be made of reinforced concrete walls.In the rest of the building there will be done designing, recompartmenting works in order to create the corresponding flows (English)
Property / summary: Through this project it is proposed: – extension of level 3 on the entire existing surface of the lower floor (existing), maintaining the sections of the elements on this level.- extension of the escape stairs up to the level of the 3rd floor and rehabilitation of the elevator – extension of Annex C8.1 from the height regime D+P to D+P+ 2E height regime – the vertical and horizontal extension of the elevator house, in order to place a new elevator with the possibility of access with a stretcher and on the stairs. The light courtyards will be made of reinforced concrete walls.In the rest of the building there will be done designing, recompartmenting works in order to create the corresponding flows (English) / rank
 
Normal rank
Property / summary: Through this project it is proposed: – extension of level 3 on the entire existing surface of the lower floor (existing), maintaining the sections of the elements on this level.- extension of the escape stairs up to the level of the 3rd floor and rehabilitation of the elevator – extension of Annex C8.1 from the height regime D+P to D+P+ 2E height regime – the vertical and horizontal extension of the elevator house, in order to place a new elevator with the possibility of access with a stretcher and on the stairs. The light courtyards will be made of reinforced concrete walls.In the rest of the building there will be done designing, recompartmenting works in order to create the corresponding flows (English) / qualifier
 
point in time: 17 June 2021
Timestamp+2021-06-17T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 11:47, 17 June 2021

Project Q2743955 in Romania
Language Label Description Also known as
English
No label defined
Project Q2743955 in Romania

    Statements

    0 references
    7,485,329.6 Romanian Leu
    0 references
    1,497,065.92 Euro
    15 June 2021
    0 references
    10,693,327.86 Romanian Leu
    0 references
    2,138,665.572 Euro
    15 June 2021
    0 references
    0.7 percent
    0 references
    15 August 2018
    0 references
    31 July 2023
    0 references
    UAT Targu Carbunesti
    0 references
    Prin acest proiect se propune:- extinderea nivelului 3 pe toata suprafata existenta a etajului inferior(existent), mentinand sectiunile elementelor si pe acest nivel.- extinderea scarii de evacuare pana la nivelul etajului 3 si reabilitarea cesteia- extinderea anexei C8.1 de la regimul de inaltime D+P la regim de inaltime D+P+2E- extinderea pe verticala si orizontala a casei liftului, in vederea amplasarii unui ascensor nou cu posibilitate de acces cu targa si scaun rulant.- la nivelul subsolului se propune realizarea unor curti de lumina pentru accesul facil prin amplasarea unor scari de beton armat in aceste zone. Curtile de lumina vor fi realizate din pereti de beton armat.In restul imobilului se vor realiza lucrari de amenajare, recompartimentare in vederea creearii fluxurilor corespunzatoare (Romanian)
    0 references
    Through this project it is proposed: – extension of level 3 on the entire existing surface of the lower floor (existing), maintaining the sections of the elements on this level.- extension of the escape stairs up to the level of the 3rd floor and rehabilitation of the elevator – extension of Annex C8.1 from the height regime D+P to D+P+ 2E height regime – the vertical and horizontal extension of the elevator house, in order to place a new elevator with the possibility of access with a stretcher and on the stairs. The light courtyards will be made of reinforced concrete walls.In the rest of the building there will be done designing, recompartmenting works in order to create the corresponding flows (English)
    17 June 2021
    0 references
    GJ, Targu Carbunesti
    0 references

    Identifiers

    126881
    0 references