(Created claim: summary (P836): The main objective of the project is to achieve 3019.8 kW of additional renewable electricity and heat generation capacity. In order to meet this goal, it is planned to purchase photovoltaic installations, biomass boilers, ground heat pumps and air heat pumps. This project will install 584 photovoltaic installations, 20 biomass boilers, 43 ground heat pumps and 90 air heat pumps for residents of Kolbuszów and Dzikowiec Commune., translated_summary) |
||||||||||||||
Property / summary | |||||||||||||||
The main objective of the project is to achieve 3019.8 kW of additional renewable electricity and heat generation capacity. In order to meet this goal, it is planned to purchase photovoltaic installations, biomass boilers, ground heat pumps and air heat pumps. This project will install 584 photovoltaic installations, 20 biomass boilers, 43 ground heat pumps and 90 air heat pumps for residents of Kolbuszów and Dzikowiec Commune. (English) | |||||||||||||||
Property / summary: The main objective of the project is to achieve 3019.8 kW of additional renewable electricity and heat generation capacity. In order to meet this goal, it is planned to purchase photovoltaic installations, biomass boilers, ground heat pumps and air heat pumps. This project will install 584 photovoltaic installations, 20 biomass boilers, 43 ground heat pumps and 90 air heat pumps for residents of Kolbuszów and Dzikowiec Commune. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The main objective of the project is to achieve 3019.8 kW of additional renewable electricity and heat generation capacity. In order to meet this goal, it is planned to purchase photovoltaic installations, biomass boilers, ground heat pumps and air heat pumps. This project will install 584 photovoltaic installations, 20 biomass boilers, 43 ground heat pumps and 90 air heat pumps for residents of Kolbuszów and Dzikowiec Commune. (English) / qualifier | |||||||||||||||
point in time: 8 July 2021
|
Revision as of 22:52, 7 July 2021
Project Q2711704 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | No label defined |
Project Q2711704 in Poland |
Statements
9,997,176.0 zloty
0 references
11,901,400.0 zloty
0 references
84.0 percent
0 references
30 April 2020
0 references
30 June 2022
0 references
GMINA KOLBUSZOWA
0 references
Głównym celem projektu jest uzyskanie 3019,8 kW dodatkowej zdolności wytwarzania energii elektrycznej i cieplnej ze źródeł odnawialnych. Aby spełnić ten cel planuje się zakup instalacji fotowoltaicznych, kotłów na biomasę, gruntowych pomp ciepła oraz powietrznych pomp ciepła.W ramach niniejszego projektu zostanie zamontowanych 584 instalacji fotowoltaicznych, 20 kotłów na biomasę, 43 gruntowe pompy ciepła oraz 90 powietrznych pomp ciepła dla mieszkańców Gminy Kolbuszowa i Gminy Dzikowiec. (Polish)
0 references
The main objective of the project is to achieve 3019.8 kW of additional renewable electricity and heat generation capacity. In order to meet this goal, it is planned to purchase photovoltaic installations, biomass boilers, ground heat pumps and air heat pumps. This project will install 584 photovoltaic installations, 20 biomass boilers, 43 ground heat pumps and 90 air heat pumps for residents of Kolbuszów and Dzikowiec Commune. (English)
8 July 2021
0 references
Identifiers
RPPK.03.01.00-18-0054/17
0 references