Installation for generating power generating power of 400 kW in the Municipality of Kąty Wrocławskie (Q95401): Difference between revisions
Jump to navigation
Jump to search
(Changed an Item) |
(Created claim: summary (P836): The MAIN project is intended to mobilise the production of electricity from solar radiation in the company AG, a project to connect the installation of the photovoltaic power plant to the transmission grid. The specific objectives of the project shall be to: The purchase, installation and launch of the photovoltaic installation, the connection of the installation to the distribution network in accordance with the TAURON Danalacja S.A., — the use...) |
||
Property / summary | |||
The MAIN project is intended to mobilise the production of electricity from solar radiation in the company AG, a project to connect the installation of the photovoltaic power plant to the transmission grid. The specific objectives of the project shall be to: The purchase, installation and launch of the photovoltaic installation, the connection of the installation to the distribution network in accordance with the TAURON Danalacja S.A., — the use of part of the electricity produced from the installation according to the connection conditions TAURON — Distribution S.A., — an increase in the share of renewable energy sources to meet the needs of the company, — installation and deployment of a smart energy management system and demonstration and educational installations for the promotion of RES in the region. The activities to be carried out are: 1. Installation of the plant (a) Purchase of solar panels with a total nominal output of 412,60 kWp (in quantities of between 1190 and 1380 units, measured at standard STC conditions) and an annual yield of ca. 365.36 MWh and 14 inverters having a power of 378 kW (from AC side) together with additional attachments. (b) Installation of an existing installation on the roof of an existing production building owned by the Applicant. (c) Provision to the electricity distribution network. (D) Development and implementation of promotional and educational measures as an educational component, accompanying the investment, and aimed at raising public awareness of the benefits of RES. Activities will take the form of: — the publication of information on the environmental effects of the design and operation of the plant on the sites of the firm and on promotional publications, — in the form of an electronic information board presenting the process of converting the solar energy into electricity, the amount of energy generated at the time, the quantity of energy generated, the environmental benefit; (English) | |||
Property / summary: The MAIN project is intended to mobilise the production of electricity from solar radiation in the company AG, a project to connect the installation of the photovoltaic power plant to the transmission grid. The specific objectives of the project shall be to: The purchase, installation and launch of the photovoltaic installation, the connection of the installation to the distribution network in accordance with the TAURON Danalacja S.A., — the use of part of the electricity produced from the installation according to the connection conditions TAURON — Distribution S.A., — an increase in the share of renewable energy sources to meet the needs of the company, — installation and deployment of a smart energy management system and demonstration and educational installations for the promotion of RES in the region. The activities to be carried out are: 1. Installation of the plant (a) Purchase of solar panels with a total nominal output of 412,60 kWp (in quantities of between 1190 and 1380 units, measured at standard STC conditions) and an annual yield of ca. 365.36 MWh and 14 inverters having a power of 378 kW (from AC side) together with additional attachments. (b) Installation of an existing installation on the roof of an existing production building owned by the Applicant. (c) Provision to the electricity distribution network. (D) Development and implementation of promotional and educational measures as an educational component, accompanying the investment, and aimed at raising public awareness of the benefits of RES. Activities will take the form of: — the publication of information on the environmental effects of the design and operation of the plant on the sites of the firm and on promotional publications, — in the form of an electronic information board presenting the process of converting the solar energy into electricity, the amount of energy generated at the time, the quantity of energy generated, the environmental benefit; (English) / rank | |||
Normal rank |
Revision as of 07:11, 6 March 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Installation for generating power generating power of 400 kW in the Municipality of Kąty Wrocławskie |
Project in Poland financed by DG Regio |
Statements
1,212,900.0 zloty
0 references
2,295,180.0 zloty
0 references
65.0 percent
0 references
1 October 2016
0 references
31 October 2017
0 references
AG-PROJEKT SKOCZYLAS SPÓŁKA JAWNA
0 references
CELEM GŁÓWNYM projektu jest uruchomienie produkcji energii elektrycznej pochodzącej z promieniowania słonecznego w przedsiębiorstwie AG Projekt, z podłączeniem nowo powstałej instalacji elektrowni fotowoltaicznej do sieci przesyłowej. CELAMI SZCZEGÓŁOWYMI projektu są: - zakup, instalacja i uruchomienie instalacji fotowoltaicznej, - podłączenie instalacji do sieci dystrybucyjnej zgodnie z warunkami przyłączeniowymi TAURON Dystrybucja S.A., - wykorzystanie części wytworzonej energii elektrycznej z instalacji wg warunków przyłączeniowych TAURON Dystrybucja S.A., - zwiększenie udziału odnawialnych źródeł energii w zaspokojeniu na potrzeby przedsiębiorstwa, - instalacja i uruchomienie inteligentnego systemu zarządzania energią oraz instalacji demonstracyjno-edukacyjnej promującej OZE w regionie. Planowanymi do realizacji działaniami są: 1. Uruchomienie instalacji a) Zakup paneli fotowoltaicznych o łącznej mocy nominalnej minimum 412,60 kWp (w ilości od 1190 do1380 szt., pomiar w warunkach standardowych STC) i rocznym uzysku ok. 365,36 MWh oraz 14 inwerterów o mocy 378 kW (od strony AC) wraz z dodatkowymi elementami montażowymi. b) Montaż instalacji na dachu istniejącego budynku produkcyjnego należącego do Wnioskodawcy. c) Podłączenie do sieci dystrybucji energii elektrycznej. d) Opracowanie i realizacja akcji promocyjno-edukacyjnych jako element dydaktyczny, towarzyszący inwestycji, a mający na celu podniesienie świadomości społecznej na temat korzyści płynącej z wykorzystania OZE. Działania będą miały formę: - publikacji informacji o efektach ekologicznych projektu i działania instalacji na stronach firmy oraz publikatorach promocyjnych, - w formie elektronicznej tablicy informacyjnej prezentującej proces przetwarzania energii słonecznej na elektryczną, ilość generowanej w danej chwili energii, ilość wytworzonej energii narastające, korzyści dla środowiska naturalnego; (Polish)
0 references
The MAIN project is intended to mobilise the production of electricity from solar radiation in the company AG, a project to connect the installation of the photovoltaic power plant to the transmission grid. The specific objectives of the project shall be to: The purchase, installation and launch of the photovoltaic installation, the connection of the installation to the distribution network in accordance with the TAURON Danalacja S.A., — the use of part of the electricity produced from the installation according to the connection conditions TAURON — Distribution S.A., — an increase in the share of renewable energy sources to meet the needs of the company, — installation and deployment of a smart energy management system and demonstration and educational installations for the promotion of RES in the region. The activities to be carried out are: 1. Installation of the plant (a) Purchase of solar panels with a total nominal output of 412,60 kWp (in quantities of between 1190 and 1380 units, measured at standard STC conditions) and an annual yield of ca. 365.36 MWh and 14 inverters having a power of 378 kW (from AC side) together with additional attachments. (b) Installation of an existing installation on the roof of an existing production building owned by the Applicant. (c) Provision to the electricity distribution network. (D) Development and implementation of promotional and educational measures as an educational component, accompanying the investment, and aimed at raising public awareness of the benefits of RES. Activities will take the form of: — the publication of information on the environmental effects of the design and operation of the plant on the sites of the firm and on promotional publications, — in the form of an electronic information board presenting the process of converting the solar energy into electricity, the amount of energy generated at the time, the quantity of energy generated, the environmental benefit; (English)
0 references
Identifiers
RPDS.03.01.00-02-0109/16
0 references