DIRECTOR OF THE SAN CONE — PATERNò (Q2021724): Difference between revisions
Jump to navigation
Jump to search
(Changed label, description and/or aliases in 2 languages: Changing unique label-description pair) |
(Removed claim: financed by (P890): Directorate-General for Regional and Urban Policy (Q8361), Removing unnecessary financed by statement) |
||
Property / financed by | |||
Property / financed by: Directorate-General for Regional and Urban Policy / rank | |||
Revision as of 04:39, 2 November 2020
Project Q2021724 in Italy
Language | Label | Description | Also known as |
---|---|---|---|
English | DIRECTOR OF THE SAN CONE — PATERNò |
Project Q2021724 in Italy |
Statements
5,599,013.63 Euro
0 references
7,578,939.49 Euro
0 references
73.88 percent
0 references
24 October 2017
0 references
15 December 2020
0 references
TERNA - RETE ELETTRICA NAZIONALE
0 references
L'ATTIVITà CONSISTE NELLA SOSTITUZIONE DEI CONDUTTORI CON ALTRI AD ALTA CAPACITà DI TRASPORTO DI TIPO ZTAL PER LE LINEE AEREE 150 KV TRA LA C.P. NICOLETTI E LA S.E. PATERNò, PER UN TOTALE DI CIRCA 80 KM. L'INTERVENTO SARà , INOLTRE, COMPRENSIVO DELLA SOSTITUZIONE DEI RELATIVI EQUIPAGGIAMENTI, DI SOSTEGNI E DELLA FUNE DI GUARDIA CON QUELLA INCORPORANTE FIBRA OTTICA (F.O), ANCHE AL FINE DI AUMENTARE LE FUNZIONALITà CONNESSE CON IL MONITORAGGIO DELLA RETE.TALI INTERVENTI CONSENTIRANNO DI AUMENTARE L'AFFIDABILITà DELLA RETE ELETTRICA DI TRASMISSIONE NAZIONALE E DI FAR FRONTE ALL'INTRODUZIONE IN RETE DI QUOTE SEMPRE MAGGIORI DI ENERGIE RINNOVABILI GARANTENDO MAGGIORE FLESSIBILITà DELLA CAPACITà DI TRASPORTO. (Italian)
0 references
THE ACTIVITY CONSISTS OF THE REPLACEMENT OF ZTAL TYPES FOR CONDUCTORS OF ZAL FOR THE 150 KV OVERHEAD LINES BETWEEN THE C.P. NICOLETTI AND THE AE PATERNò, AMOUNTING TO A TOTAL OF APPROXIMATELY 80 KM. IN ADDITION, THE INTERVENTION WILL INCLUDE THE REPLACEMENT OF THE RELATED EQUIPMENT, SUPPORTS AND GUARD ROPE WITH THAT INCORPORATING OPTICAL FIBRE (F.O), INCLUDING WITH A VIEW TO INCREASING THE OPERATIONAL TASKS ASSOCIATED WITH THE MONITORING OF THE NATIONAL TRANSMISSION GRID, AND WILL ENABLE THE AFFIDABILITY OF THE NATIONAL ELECTRICITY TRANSMISSION NETWORK TO BE INCREASED AND TO BE ABLE TO COPE WITH THE INTRODUCTION OF INCREASING SHARES OF RENEWABLE ENERGIES IN THE NETWORK BY ENSURING A HIGHER LEVEL OF TRANSPORT CAPACITY. (English)
0 references
Identifiers
G73G17001010007
0 references