K2 atmitec s.r.o. – Modernisation and extension of the data centre (Q19426): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Removed claim: summary (P836): The purpose of the project is the extension of the Data Centre and the modernisation to reduce energy intensity. The current cooling of the Dx units will be extended and combined with another cooling system. Further to the optimisation of energy consumption, new storage technologies will be acquired to replace current and its low energy consumption significantly over the period during which the entire cooling data centre will work in a PUE mod...)
(‎Created claim: summary (P836): The object of the project is the extension of the data centre and modernisation in order to reduce energy performance. Existing DX cooling units will be extended and combined with another cooling system. In connection with the optimisation of energy consumption, new storage technologies will be acquired, replacing the current and low energy consumption significantly extending the period in which the whole data centre will operate in a mode with...)
Property / summary
 
The object of the project is the extension of the data centre and modernisation in order to reduce energy performance. Existing DX cooling units will be extended and combined with another cooling system. In connection with the optimisation of energy consumption, new storage technologies will be acquired, replacing the current and low energy consumption significantly extending the period in which the whole data centre will operate in a mode with a PUE value approaching 1 a.a. in terms of cooling. (English)
Property / summary: The object of the project is the extension of the data centre and modernisation in order to reduce energy performance. Existing DX cooling units will be extended and combined with another cooling system. In connection with the optimisation of energy consumption, new storage technologies will be acquired, replacing the current and low energy consumption significantly extending the period in which the whole data centre will operate in a mode with a PUE value approaching 1 a.a. in terms of cooling. (English) / rank
 
Normal rank
Property / summary: The object of the project is the extension of the data centre and modernisation in order to reduce energy performance. Existing DX cooling units will be extended and combined with another cooling system. In connection with the optimisation of energy consumption, new storage technologies will be acquired, replacing the current and low energy consumption significantly extending the period in which the whole data centre will operate in a mode with a PUE value approaching 1 a.a. in terms of cooling. (English) / qualifier
 
point in time: 22 October 2020
Timestamp+2020-10-22T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 17:02, 22 October 2020

Project in Czech Republic financed by DG Regio
Language Label Description Also known as
English
K2 atmitec s.r.o. – Modernisation and extension of the data centre
Project in Czech Republic financed by DG Regio

    Statements

    0 references
    14,000,000.0 Czech koruna
    0 references
    560,000.0 Euro
    10 January 2020
    0 references
    40,000,000.0 Czech koruna
    0 references
    1,600,000.0 Euro
    10 January 2020
    0 references
    35 percent
    0 references
    1 November 2015
    0 references
    21 March 2018
    0 references
    31 March 2018
    0 references
    K2 atmitec s.r.o.
    0 references
    0 references

    49°50'27.60"N, 18°16'41.70"E
    0 references
    70200
    0 references
    Předmětem projektu je rozšíření datového centra a modernizace za účelem snížení energetické náročnosti. Stávající chlazení DX jednotkami bude rozšířeno a kombinováno s dalším systémem chlazení. V souvislosti s optimalizací energetické spotřeby budou dále pořízeny nové technologie uložení dat, které nahradí stávající a svou nízkou energetickou spotřebou významně prodlouží období, ve kterém bude celé datové centrum z hlediska chlazení pracovat v režimu s hodnotou PUE blížící se 1. a. (Czech)
    0 references
    The object of the project is the extension of the data centre and modernisation in order to reduce energy performance. Existing DX cooling units will be extended and combined with another cooling system. In connection with the optimisation of energy consumption, new storage technologies will be acquired, replacing the current and low energy consumption significantly extending the period in which the whole data centre will operate in a mode with a PUE value approaching 1 a.a. in terms of cooling. (English)
    22 October 2020
    0 references

    Identifiers

    CZ.01.4.04/0.0/0.0/15_011/0001944
    0 references