Reduction of energy consumption in Letoplast’s production process (1x 220 t + 2x 500 t) (Q16353): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Removed claim: summary (P836): The project aims at reducing energy intensity in the production process by ensuring an increase in the energy efficiency of the entire thermoplastics injection process. The production process of thermoplastics injection is an energy intensive process. The project will mainly concern energy savings, which is expressed by comparing the technology used at the same time as more energy-efficient technology with a closing force of 1x 220 t + 2x 500 ...)
(‎Created claim: summary (P836): The object of the project is to reduce energy performance in the production process, the project will ensure an increase in energy efficiency of the entire production process of thermoplastic injection moulding. The production process of thermoplastic injection moulding is an energy-intensive process. The project will primarily involve energy saving, which is expressed by comparing the currently used technology for more energy-efficient technolo...)
Property / summary
 
The object of the project is to reduce energy performance in the production process, the project will ensure an increase in energy efficiency of the entire production process of thermoplastic injection moulding. The production process of thermoplastic injection moulding is an energy-intensive process. The project will primarily involve energy saving, which is expressed by comparing the currently used technology for more energy-efficient technology with the clamping force of 1x 220 t + 2x 500 t. Place of realisation Pražská 258/91, Letovice. a. (English)
Property / summary: The object of the project is to reduce energy performance in the production process, the project will ensure an increase in energy efficiency of the entire production process of thermoplastic injection moulding. The production process of thermoplastic injection moulding is an energy-intensive process. The project will primarily involve energy saving, which is expressed by comparing the currently used technology for more energy-efficient technology with the clamping force of 1x 220 t + 2x 500 t. Place of realisation Pražská 258/91, Letovice. a. (English) / rank
 
Normal rank
Property / summary: The object of the project is to reduce energy performance in the production process, the project will ensure an increase in energy efficiency of the entire production process of thermoplastic injection moulding. The production process of thermoplastic injection moulding is an energy-intensive process. The project will primarily involve energy saving, which is expressed by comparing the currently used technology for more energy-efficient technology with the clamping force of 1x 220 t + 2x 500 t. Place of realisation Pražská 258/91, Letovice. a. (English) / qualifier
 
point in time: 22 October 2020
Timestamp+2020-10-22T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 16:33, 22 October 2020

Project in Czech Republic financed by DG Regio
Language Label Description Also known as
English
Reduction of energy consumption in Letoplast’s production process (1x 220 t + 2x 500 t)
Project in Czech Republic financed by DG Regio

    Statements

    0 references
    7,947,753.0 Czech koruna
    0 references
    317,910.12 Euro
    10 January 2020
    0 references
    26,492,510.0 Czech koruna
    0 references
    1,059,700.4 Euro
    10 January 2020
    0 references
    30 percent
    0 references
    27 April 2018
    0 references
    31 March 2021
    0 references
    Letoplast s.r.o.
    0 references
    0 references

    49°33'28.30"N, 16°34'48.76"E
    0 references
    67961
    0 references
    Předmětem projektu je snižování energetické náročnosti ve výrobním procesu, projektem bude zajištěno zvýšení energetické účinnosti celého výrobního procesu vstřikování termoplastů. Výrobní proces vstřikování termoplastů je energeticky velmi náročný proces. V rámci projektu se bude jednat především o energetickou úsporu, která je vyjádřena porovnáním současně používané technologie za technologii energeticky úspornější s uzavírací silou 1x 220t + 2x 500t. Místo realizace Pražská 258/91, Letovice. a. (Czech)
    0 references
    The object of the project is to reduce energy performance in the production process, the project will ensure an increase in energy efficiency of the entire production process of thermoplastic injection moulding. The production process of thermoplastic injection moulding is an energy-intensive process. The project will primarily involve energy saving, which is expressed by comparing the currently used technology for more energy-efficient technology with the clamping force of 1x 220 t + 2x 500 t. Place of realisation Pražská 258/91, Letovice. a. (English)
    22 October 2020
    0 references

    Identifiers

    CZ.01.3.10/0.0/0.0/17_101/0013546
    0 references