Decentralisation of heating CA PZP Lobodice (Q16300): Difference between revisions
Jump to navigation
Jump to search
(Removed claim: summary (P836): The project addresses the replacement of the existing centralised heating solution on the central site of the Lobodice company Innogy Gas Storage, s.r.o. Central for decentralised solutions to local gas boilers. The replacement of heating elements in certain premises, the connection of generators on pipeline connections and the electricity grid and their management to MAR, as well as the dismantling of existing boiler plants, are also addresse...) |
(Created claim: summary (P836): The project deals with the replacement of the existing centralised heating of operating buildings of the central underground gas storage area Lobodice of the company innogy Gas Storage, s.r.o. central boiler for decentralised solution by local gas boilers. There are also solutions for replacement of heating units in some buildings, connection of boilers to gas-water connections and electrical network and their control of the MaR and also dismant...) |
||||||||||||||
Property / summary | |||||||||||||||
The project deals with the replacement of the existing centralised heating of operating buildings of the central underground gas storage area Lobodice of the company innogy Gas Storage, s.r.o. central boiler for decentralised solution by local gas boilers. There are also solutions for replacement of heating units in some buildings, connection of boilers to gas-water connections and electrical network and their control of the MaR and also dismantling the existing equipment of the boiler room. This solution will bring energy savings and increased operational reliability. a. (English) | |||||||||||||||
Property / summary: The project deals with the replacement of the existing centralised heating of operating buildings of the central underground gas storage area Lobodice of the company innogy Gas Storage, s.r.o. central boiler for decentralised solution by local gas boilers. There are also solutions for replacement of heating units in some buildings, connection of boilers to gas-water connections and electrical network and their control of the MaR and also dismantling the existing equipment of the boiler room. This solution will bring energy savings and increased operational reliability. a. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The project deals with the replacement of the existing centralised heating of operating buildings of the central underground gas storage area Lobodice of the company innogy Gas Storage, s.r.o. central boiler for decentralised solution by local gas boilers. There are also solutions for replacement of heating units in some buildings, connection of boilers to gas-water connections and electrical network and their control of the MaR and also dismantling the existing equipment of the boiler room. This solution will bring energy savings and increased operational reliability. a. (English) / qualifier | |||||||||||||||
point in time: 22 October 2020
|
Revision as of 16:14, 22 October 2020
Project in Czech Republic financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Decentralisation of heating CA PZP Lobodice |
Project in Czech Republic financed by DG Regio |
Statements
1,621,799.4 Czech koruna
0 references
5,405,998.0 Czech koruna
0 references
30 percent
0 references
16 October 2018
0 references
22 March 2019
0 references
30 April 2019
0 references
innogy Gas Storage, s.r.o.
0 references
10800
0 references
Projekt řeší náhradu stávajícího centralizovaného řešení vytápění provozních budov centrálního areálu podzemního zásobníku plynu Lobodice společnosti innogy Gas Storage, s.r.o. centrální kotelnou za decentralizované řešení místními plynovými kotli. Jsou řešeny i výměny topných těles v některých objektech, připojení kotlů na plynovodní přípojky a elektrickou síť a jejich řízení MaR a také demontáž stávajícího zařízení kotelny. Toto řešení přinese úsporu energie a zvýšení provozní spolehlivosti. a. (Czech)
0 references
The project deals with the replacement of the existing centralised heating of operating buildings of the central underground gas storage area Lobodice of the company innogy Gas Storage, s.r.o. central boiler for decentralised solution by local gas boilers. There are also solutions for replacement of heating units in some buildings, connection of boilers to gas-water connections and electrical network and their control of the MaR and also dismantling the existing equipment of the boiler room. This solution will bring energy savings and increased operational reliability. a. (English)
22 October 2020
0 references
Identifiers
CZ.01.3.10/0.0/0.0/17_101/0013405
0 references