(Removed claim: summary (P836): The project envisages the construction of a rooftop micro-photovoltaic equipment operating in an open circuit, i.e. an on-grid with a generation capacity of 39.9 kW. The main components of the installation are polycrystalline panels fixed to the aluminium, the aluminium support structure and the associated infrastructure, the DC circuits, the AC circuits and the solar inverter, visualisation of the job, the lightning system. The investment wil...) |
(Created claim: summary (P836): The project envisages the construction of a roof photovoltaic micro-installation working in an open grid system i.e. on-grid with a production capacity of 39,9 kW. The main elements of the installation are polycrystalline panels mounted on steel-aluminium support structure and associated infrastructure, DC circuits, AC circuits and photovoltaic inverter, operating visualisation circuits, lightning installation. The investment will be carried out...) |
||||||||||||||
Property / summary | |||||||||||||||
The project envisages the construction of a roof photovoltaic micro-installation working in an open grid system i.e. on-grid with a production capacity of 39,9 kW. The main elements of the installation are polycrystalline panels mounted on steel-aluminium support structure and associated infrastructure, DC circuits, AC circuits and photovoltaic inverter, operating visualisation circuits, lightning installation. The investment will be carried out on the premises of PGK sp. z o.o. on the roofs of the administrative building and workshop buildings. A photovoltaic micro-installation was designed, placed on the roofs of three buildings, i.e. two buildings. A and D located on the street. Communal 5 in Koszalin. The production capacity of the micro-installation will be 39.9 kW. It is planned to be connected to the internal electrical installation of the facility behind the measuring and settlement system (net) located in the corner of building A. Optimisation of the designed micro-installation was made in terms of maximum consumption of energy produced for the own needs of municipal buildings, reducing the possibility of generating surplus generation to a minimum. Construction works on roofs for which photovoltaic micro-installation has been designed are connected to the distribution network of the local operator i.e. Energa Operator S.A. with the common point of the PPE: 480037530116743456. The operating limit is located on the current terminals in a cable-measuring connector built in the corner of building A from the street side. Municipal – no change in the existing operating limit is foreseen under this project and the energy produced will be consumed for the plant’s own needs. (English) | |||||||||||||||
Property / summary: The project envisages the construction of a roof photovoltaic micro-installation working in an open grid system i.e. on-grid with a production capacity of 39,9 kW. The main elements of the installation are polycrystalline panels mounted on steel-aluminium support structure and associated infrastructure, DC circuits, AC circuits and photovoltaic inverter, operating visualisation circuits, lightning installation. The investment will be carried out on the premises of PGK sp. z o.o. on the roofs of the administrative building and workshop buildings. A photovoltaic micro-installation was designed, placed on the roofs of three buildings, i.e. two buildings. A and D located on the street. Communal 5 in Koszalin. The production capacity of the micro-installation will be 39.9 kW. It is planned to be connected to the internal electrical installation of the facility behind the measuring and settlement system (net) located in the corner of building A. Optimisation of the designed micro-installation was made in terms of maximum consumption of energy produced for the own needs of municipal buildings, reducing the possibility of generating surplus generation to a minimum. Construction works on roofs for which photovoltaic micro-installation has been designed are connected to the distribution network of the local operator i.e. Energa Operator S.A. with the common point of the PPE: 480037530116743456. The operating limit is located on the current terminals in a cable-measuring connector built in the corner of building A from the street side. Municipal – no change in the existing operating limit is foreseen under this project and the energy produced will be consumed for the plant’s own needs. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The project envisages the construction of a roof photovoltaic micro-installation working in an open grid system i.e. on-grid with a production capacity of 39,9 kW. The main elements of the installation are polycrystalline panels mounted on steel-aluminium support structure and associated infrastructure, DC circuits, AC circuits and photovoltaic inverter, operating visualisation circuits, lightning installation. The investment will be carried out on the premises of PGK sp. z o.o. on the roofs of the administrative building and workshop buildings. A photovoltaic micro-installation was designed, placed on the roofs of three buildings, i.e. two buildings. A and D located on the street. Communal 5 in Koszalin. The production capacity of the micro-installation will be 39.9 kW. It is planned to be connected to the internal electrical installation of the facility behind the measuring and settlement system (net) located in the corner of building A. Optimisation of the designed micro-installation was made in terms of maximum consumption of energy produced for the own needs of municipal buildings, reducing the possibility of generating surplus generation to a minimum. Construction works on roofs for which photovoltaic micro-installation has been designed are connected to the distribution network of the local operator i.e. Energa Operator S.A. with the common point of the PPE: 480037530116743456. The operating limit is located on the current terminals in a cable-measuring connector built in the corner of building A from the street side. Municipal – no change in the existing operating limit is foreseen under this project and the energy produced will be consumed for the plant’s own needs. (English) / qualifier | |||||||||||||||
point in time: 21 October 2020
|
Revision as of 19:19, 21 October 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of a photovoltaic installation with an installed capacity of 39,9 kWp on administrative and technical buildings PGK sp. z o.o. in Koszalin |
Project in Poland financed by DG Regio |
Statements
76,664.49 zloty
0 references
170,365.58 zloty
0 references
45.0 percent
0 references
3 April 2017
0 references
7 July 2017
0 references
PRZEDSIĘBIORSTWO GOSPODARKI KOMUNALNEJ SP. Z O.O.
0 references
Projekt przewiduje budowę dachowej mikroinstalacji fotowoltaicznej pracującej w układzie otwartym na sieć tzn. on-grid o mocy wytwórczej 39,9 kW. Głównymi elementami instalacji są panele polikrystaliczne mocowane na stalowo-aluminiowej konstrukcji wsporczej oraz infrastruktura towarzyszącą, obwody DC, obwody AC oraz inwerter fotowoltaiczny, obwody wizualizacji pracy, instalacja odgromowa. Inwestycja realizowana będzie na terenie siedziby PGK sp. z o.o. na dachach budynku administracyjnego oraz budynków warsztatowych. Zaprojektowano mikroinstalację fotowoltaiczną umieszczoną na dachach trzech obiektów stanowiących dwa budynki tj. A i D zlokalizowane przy ul. Komunalnej 5 w Koszalinie. Moc wytwórcza przedmiotowej mikroinstalacji wynosić będzie 39,9kW. Przewidziano przyłączenie jej do wewnętrznej instalacji elektrycznej obiektu za układem pomiarowo-rozliczeniowym (netto) zlokalizowanym w narożniku budynku A. Optymalizacji projektowanej mikroinstalacji dokonano pod kątem maksymalnej konsumpcji energii wyprodukowanej na własne potrzeby obiektów komunalnych, redukując możliwość powstawania nadwyżek generacyjnych do minimum. Obiekty budowlane na dachach których zaprojektowano mikroinstalację fotowoltaiczną przyłączone są do sieci dystrybucyjnej lokalnego operatora tj. ENERGA Operator S.A. ze wspólnym punktem PPE: 480037530116743456. Granica eksploatacji znajduje się na zaciskach prądowych w złączu kablowo-pomiarowym zabudowanym w narożniku budynku A od strony ul. Komunalnej – w ramach niniejszego projektu nie przewiduje się zmiany istniejącej granicy eksploatacji a produkowana energia zużywana będzie na potrzeby własne obiektu. (Polish)
0 references
The project envisages the construction of a roof photovoltaic micro-installation working in an open grid system i.e. on-grid with a production capacity of 39,9 kW. The main elements of the installation are polycrystalline panels mounted on steel-aluminium support structure and associated infrastructure, DC circuits, AC circuits and photovoltaic inverter, operating visualisation circuits, lightning installation. The investment will be carried out on the premises of PGK sp. z o.o. on the roofs of the administrative building and workshop buildings. A photovoltaic micro-installation was designed, placed on the roofs of three buildings, i.e. two buildings. A and D located on the street. Communal 5 in Koszalin. The production capacity of the micro-installation will be 39.9 kW. It is planned to be connected to the internal electrical installation of the facility behind the measuring and settlement system (net) located in the corner of building A. Optimisation of the designed micro-installation was made in terms of maximum consumption of energy produced for the own needs of municipal buildings, reducing the possibility of generating surplus generation to a minimum. Construction works on roofs for which photovoltaic micro-installation has been designed are connected to the distribution network of the local operator i.e. Energa Operator S.A. with the common point of the PPE: 480037530116743456. The operating limit is located on the current terminals in a cable-measuring connector built in the corner of building A from the street side. Municipal – no change in the existing operating limit is foreseen under this project and the energy produced will be consumed for the plant’s own needs. (English)
21 October 2020
0 references
Identifiers
RPZP.02.10.00-32-A095/16