(‎Removed claim: summary (P836): The object of the project is the construction of a photovoltaic installation with a total surface area of approximately 101.9 m² and a capacity of 17,08 kWp on the roof of the construction shop of the company in Elbląg (Elbląg g), with the use of the electricity produced for own use. The installation will consist of 61 solar modules, inverters in alternating current (such as electric sockets), mounting systems, conductors, cables, switchgear a...)
(‎Created claim: summary (P836): The subject of the project is the construction of a photovoltaic installation with a total area of approx. 101.9 m² and a capacity of 17.08 kWp on the roof of the company’s wholesale hall in Elbląg (gm. Elbląg), for the purpose of the electricity produced for its own use. The installation will consist of 61 photovoltaic modules, inverters changing DC into alternating current (such as electrical sockets), assembly system, connectors, wiring, swit...)
Property / summary
 
The subject of the project is the construction of a photovoltaic installation with a total area of approx. 101.9 m² and a capacity of 17.08 kWp on the roof of the company’s wholesale hall in Elbląg (gm. Elbląg), for the purpose of the electricity produced for its own use. The installation will consist of 61 photovoltaic modules, inverters changing DC into alternating current (such as electrical sockets), assembly system, connectors, wiring, switchgears and monitoring system. The project will be implemented in the period from 01.07.2017-30.06.2020. The specific tasks are at the same time the stages of the implementation of the investment. The project does not require a construction permit (installation less than 40 kW). Its implementation will result in the creation of a single new job. The applicant declares that he has the right to dispose of the property for the construction purposes on which the planned investment (the property act) will be located. The project is in line with the assumptions of the SzOOP (Energy Efficiency) because it focuses on actions aimed at improving energy security of Warmińsko-Mazurskie Voivodship by increasing production capacity based on renewable sources and the possibility of receiving generated energy and energy efficiency in the SME sector. Installation of a photovoltaic installation will ensure that the company gains an additional energy source, which will reduce the costs of the operation and reduce the harmful impact on the environment. The project supports the production and distribution of energy from renewable sources and increases their share in the region’s energy balance. (English)
Property / summary: The subject of the project is the construction of a photovoltaic installation with a total area of approx. 101.9 m² and a capacity of 17.08 kWp on the roof of the company’s wholesale hall in Elbląg (gm. Elbląg), for the purpose of the electricity produced for its own use. The installation will consist of 61 photovoltaic modules, inverters changing DC into alternating current (such as electrical sockets), assembly system, connectors, wiring, switchgears and monitoring system. The project will be implemented in the period from 01.07.2017-30.06.2020. The specific tasks are at the same time the stages of the implementation of the investment. The project does not require a construction permit (installation less than 40 kW). Its implementation will result in the creation of a single new job. The applicant declares that he has the right to dispose of the property for the construction purposes on which the planned investment (the property act) will be located. The project is in line with the assumptions of the SzOOP (Energy Efficiency) because it focuses on actions aimed at improving energy security of Warmińsko-Mazurskie Voivodship by increasing production capacity based on renewable sources and the possibility of receiving generated energy and energy efficiency in the SME sector. Installation of a photovoltaic installation will ensure that the company gains an additional energy source, which will reduce the costs of the operation and reduce the harmful impact on the environment. The project supports the production and distribution of energy from renewable sources and increases their share in the region’s energy balance. (English) / rank
 
Normal rank
Property / summary: The subject of the project is the construction of a photovoltaic installation with a total area of approx. 101.9 m² and a capacity of 17.08 kWp on the roof of the company’s wholesale hall in Elbląg (gm. Elbląg), for the purpose of the electricity produced for its own use. The installation will consist of 61 photovoltaic modules, inverters changing DC into alternating current (such as electrical sockets), assembly system, connectors, wiring, switchgears and monitoring system. The project will be implemented in the period from 01.07.2017-30.06.2020. The specific tasks are at the same time the stages of the implementation of the investment. The project does not require a construction permit (installation less than 40 kW). Its implementation will result in the creation of a single new job. The applicant declares that he has the right to dispose of the property for the construction purposes on which the planned investment (the property act) will be located. The project is in line with the assumptions of the SzOOP (Energy Efficiency) because it focuses on actions aimed at improving energy security of Warmińsko-Mazurskie Voivodship by increasing production capacity based on renewable sources and the possibility of receiving generated energy and energy efficiency in the SME sector. Installation of a photovoltaic installation will ensure that the company gains an additional energy source, which will reduce the costs of the operation and reduce the harmful impact on the environment. The project supports the production and distribution of energy from renewable sources and increases their share in the region’s energy balance. (English) / qualifier
 
point in time: 21 October 2020
Timestamp+2020-10-21T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 15:59, 21 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Photovoltaic installation for goods and services SCDO-MAX S.C.E. PACZKOWSKA, Mr D. Romanowski
Project in Poland financed by DG Regio

    Statements

    0 references
    72,062.15 zloty
    0 references
    17,294.92 Euro
    13 January 2020
    0 references
    84,779.0 zloty
    0 references
    20,346.96 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 July 2017
    0 references
    30 June 2020
    0 references
    PRZEDSIĘBIORSTWO HANDLOWO-USŁUGOWE BUDO-MAX S. C. E. PACZKOWSKA D. ROMANOWSKI
    0 references
    0 references

    54°11'56.0"N, 19°26'28.0"E
    0 references
    Przedmiotem projektu jest budowa instalacji fotowoltaicznej o łącznej powierzchni ok 101,9 m2 oraz mocy 17,08 kWp na dachu hali hurtowni przedsiębiorstwa w Elblągu (gm. Elbląg), z przeznaczeniem wyprodukowanej en. elektrycznej na potrzeby własne. Instalacja będzie składać się z 61 modułów fotowoltaicznych, falowników zmieniających prąd stały w przemienny (taki jak w gniazdach elektrycznych), systemu montażowego, konektorów, okablowania, rozdzielnic oraz systemu monitoringu. Projekt zostanie zrealizowany w okresie od 01.07.2017-30.06.2020 roku. Wyszczególnione zadania stanowią jednocześnie etapy realizacji inwestycji. Projekt nie wymaga pozwolenia na budowę (instalacja o mocy poniżej 40 kW). Efektem jego realizacji będzie stworzenie jednego nowego miejsca pracy. Wnioskodawca oświadcza, że posiada prawo do dysponowania nieruchomością na cele budowlane, na których zlokalizowana będzie planowana inwestycja (akt własności). Projekt wpisuje się w założenia SzOOP (Efektywność energetyczna) bo koncentruje się na działaniach zmierzających do poprawy bezpieczeństwa energetycznego województwa warmińsko-mazurskiego poprzez wzrost mocy wytwórczych w oparciu o źródła odnawialne i możliwości odbioru wytworzonej energii oraz racjonalizację zużycia energii w sektorze MŚP. Montaż instalacji fotowoltaicznej sprawi, że ?rma zyska dodatkowe źródło zasilania w energię, dzięki któremu ograniczy koszty prowadzonej działalności i zmniejszy szkodliwy wpływ na środowisko naturalne. Projekt wspiera wytwarzanie i dystrybucję energii pochodzącej ze źródeł odnawialnych-zwiększa ich udział w bilansie energetycznym regionu. (Polish)
    0 references
    The subject of the project is the construction of a photovoltaic installation with a total area of approx. 101.9 m² and a capacity of 17.08 kWp on the roof of the company’s wholesale hall in Elbląg (gm. Elbląg), for the purpose of the electricity produced for its own use. The installation will consist of 61 photovoltaic modules, inverters changing DC into alternating current (such as electrical sockets), assembly system, connectors, wiring, switchgears and monitoring system. The project will be implemented in the period from 01.07.2017-30.06.2020. The specific tasks are at the same time the stages of the implementation of the investment. The project does not require a construction permit (installation less than 40 kW). Its implementation will result in the creation of a single new job. The applicant declares that he has the right to dispose of the property for the construction purposes on which the planned investment (the property act) will be located. The project is in line with the assumptions of the SzOOP (Energy Efficiency) because it focuses on actions aimed at improving energy security of Warmińsko-Mazurskie Voivodship by increasing production capacity based on renewable sources and the possibility of receiving generated energy and energy efficiency in the SME sector. Installation of a photovoltaic installation will ensure that the company gains an additional energy source, which will reduce the costs of the operation and reduce the harmful impact on the environment. The project supports the production and distribution of energy from renewable sources and increases their share in the region’s energy balance. (English)
    21 October 2020
    0 references

    Identifiers

    RPWM.04.01.00-28-0093/17
    0 references